Permit Information
Permit NumberBLD00-03538
StatusFinaled
Name ADA COUNTY
Site Address 190 E FRONT ST
Project NameCOURTHOUSE-PARKING GARAGE
Customer Number 
ePlanReviewNo
Description
CIVIC PLAZA PUBLIC PARKING GARAGE- TO CONSTRUCT A NEW 109,660 SQ. FT., THREE TIER PARKING GARAGE WITH A 41,600 SQ. FT., BASEMENT. THIS PARKING GARAGE WILL HAVE 432 TOTAL PARKING SPACES. THIS BUILDING INCLUDES A 20,225 SQ. FT. AREA AT THE SOUTH SIDE OF THE GROUND LEVEL, THAT IS BEING CONSTUCTED AS A SHELL AREA FOR FUTURE FINISH AS RETAIL TENANT SPACE. THIS GARAGE IS BEING CONSTUCTED AS A POST TENSION CONCRETE STRUCTURE. THIS BUILDING IS FULLY FIRE SPRINKLED. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. SEPARATE TENANT IMPROVEMENT PERMITS ARE REQUIRED TO FINISH THE RETAIL SPACES FOR OCCUPANCY. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THIS BUILDING IS BEING CONSTRUCTED WITH A STRUCTURAL SUPPORT DECK FOR A POSSIBLE FUTURE EXPANSION. DRH00-00164/PC#1011-00/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/15/20023/15/20023/15/2002APASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 3/15/2002 9:48:54 AM Note: structural final is approved...ext landscape & paving deferred (ok'd by P&Z; "Roof"(3hr occupancy separation )firestops to be installed and protected from subsquent apt. construction atop parking structure.
BLD-Final3/13/20023/14/20023/14/2002ACANC
DetailsCarl Dependahl
###-#### MEL resched. per contractor. 3/14/2002 11:22:56 AM
BLD-Final3/14/20023/14/20023/14/2002PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 3/14/2002 11:17:22 AM ###-####
BLD-Conference3/12/20023/13/20023/13/2002APASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 3/12/2002 3:42:06 PM Mel ###-#### w/ Mike Phillips re future apts above.. 3hr .expansion joint firestop assy req'd, (by MK or apt. contractor?) 3/13/2002 3:49:27 PM
BLD-Conference3/11/20023/12/20023/12/2002APASS
DetailsCarl Dependahl
###-#### MEL
BLD-Conference3/7/20023/8/20023/8/2002APASS
DetailsCarl Dependahl
jack ###-#### for conf; glazing assy ok w/ 1" max sealant 3/8/2002 3:55:56 PM
BLD-Conference3/7/20023/7/20023/7/2002PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 3/7/2002 3:08:30 PM w/ John Resseigh,CHSQA: 1" max. space for sealants (FD150,3M) at 2hr windows at shaft ok per Technical Glass Products.
BLD-Conference3/5/20023/5/20023/5/2002APART
DetailsCarl Dependahl
Added by Inspector: 340 On 3/5/2002 9:34:52 AM W/ glazer, need specific info re fire sealant...send fax
BLD-Conference2/26/20022/26/20022/26/2002APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 2/26/2002 9:35:44 AM w/ Tom Basel, Comm'l Glass...still need listing for firestop annular space at fire windows
BLD-Final2/8/20022/11/20022/11/2002AFAIL
DetailsCarl Dependahl
###-#### JACK need masonry ok & glazing/firestop specs 2/11/2002 12:38:54 PM
BLD-Final2/11/20022/11/20022/11/2002PFAIL
DetailsCarl Dependahl
fn =jack- ###-#### ...keep c/n 2/11/2002 5:14:03 PM
BLD-Conference1/30/20021/30/20021/30/2002APART
DetailsCarl Dependahl
Added by Inspector: 340 On 1/30/2002 11:51:23 AM w/ Jack/ mcalvaine...awaiting eng's report re masonry reports/approval
BLD-Other1/28/20021/28/20021/28/2002PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/28/2002 12:38:58 PM ext glazing system "fix" installed ok
BLD-Final1/24/20021/25/20021/25/2002PPART
DetailsCarl Dependahl
###-####; rec'd engs spec for glazing frames, wip; rec'd eng's ok for guards...stamped; keep c/n, ok for t/o. 1/25/2002 4:09:13 PM
BLD-Final1/24/20021/24/20021/24/2002PNR
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 1/24/2002 11:58:16 AM ###-####...keep c/n re gla 1/24/2002 5:09:28 PM zing & engs approval letters 1/24/2002 5:10:02 PM
BLD-Final1/23/20021/24/20021/24/2002ANR
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 1/23/2002 6:14:44 PM mel ###-#### 9-10 am keep c/n, need stamped letters, gla 1/24/2002 12:00:10 PM zing issues 1/24/2002 12:00:26 PM
Code Occupancy Approval1/24/20021/24/20021/24/2002APASS
DetailsWm. Michael Meloy
Scheduled by Inspector: WMM On 1/24/2002 10:18:13 AM Inspection noted completion of all items, except the proponed ones. Staffed with Tempra Wilson who said OK to final. Incompleted items are covered by other CUP's. 1/24/2002 1:59:58 PM
BLD-Conference1/22/20021/23/20021/23/2002APASS
DetailsCarl Dependahl
###-#### mel...keep c/n, need all signatures and eng's, arch's reports. 1/24/2002 9:43:24 AM
BLD-Conference1/17/20021/17/20021/17/2002PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/17/2002 3:53:13 PM w/ John Rose' of chsqa re c/n...will have glazing attachment checked; pursue prior corrections, verify door ratings
BLD-Conference1/16/20021/16/20021/16/2002PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 1/16/2002 12:23:35 PM c/n issued, need affidavit, complete all corretions, do not conceal w/ o reinsp
BLD-Final1/14/20021/14/20021/14/2002PFAIL
DetailsCarl Dependahl
###-####, need all other oks...eng's final reports, etc. 1/14/2002 2:14:19 PM
BLD-Framing/Rough-in1/11/20021/11/20021/11/2002PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 1/11/2002 5:09:34 PM need manuf's attachment schedule for glazing walls at elevator lobbies
FIRE-Final Inspection1/11/20021/11/20021/11/2002PPASS
DetailsRick Jackson
JACK ###-####
BLD-Final1/8/20021/10/20021/10/2002PNR
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/08/2002 at 12:52:37. Contact: ###-####. fire failled left phone measage to have contractor to call back if insp. was needed. no call returned at end of work day. 1/10/2002 4:42:41 PM
FIRE-Final Inspection1/10/20021/10/20021/10/2002PFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 1/10/2002 12:04:13 PM c/n issued; exit signs; sprinkler head with tape on it; stairs cleaned of scaffolding etc. 1/10/2002 12:08:17 PM
BLD-Final1/3/20021/3/20021/3/2002PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 01/03/2002 at 10:39:10. Contact: ###-####....keep c/n, need fire ok, too. 1/3/2002 6:16:22 PM
BLD-Final12/28/20011/2/20021/2/2002AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/28/2001 at 14:29:01. Contact: ###-####. c/n, need eng's report for struct & cable rails, attachment for exterior glazing, seal enclosure for stairs,firestops, fire & other insps. 1/3/2002 8:08:22 AM
BLD-Framing/Rough-in12/28/200112/31/200112/31/2001ACANC
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 5:41:51 PM Mike
BLD-Framing/Rough-in12/28/200112/31/200112/31/2001ACANC
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 5:41:51 PM Mike
BLD-Framing/Rough-in12/28/200112/31/200112/31/2001AFAIL
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 5:41:51 PM Mike; keep c/n, complete elev/stair enclosures, show eng's ok for p.t. decks, etc. 12/31/2001 5:43:05 PM
BLD-Framing/Rough-in12/28/200112/31/200112/31/2001ACANC
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 5:41:51 PM Mike
BLD-Conference12/28/200112/28/200112/28/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 10:20:20 AM w/ state elev insp...no temp occ 12/28/2001 5:39:49 PM
BLD-Conference12/28/200112/28/200112/28/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 10:20:20 AM w/ state elev insp...no temp occ 12/28/2001 5:39:49 PM
BLD-Conference12/28/200112/28/200112/28/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 10:20:20 AM w/ state elev insp...no temp occ 12/28/2001 5:39:49 PM
BLD-Conference12/28/200112/28/200112/28/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 10:20:20 AM w/ state elev insp...no temp occ 12/28/2001 5:39:49 PM
BLD-Conference12/28/200112/28/200112/28/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/28/2001 10:20:20 AM w/ state elev insp...no temp occ 12/28/2001 5:39:49 PM
BLD-Final12/20/200112/21/200112/21/2001ANR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/20/2001 at 08:20:37. Contact: ###-####.
BLD-Framing/Rough-in12/21/200112/21/200112/21/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 12/21/2001 7:01:47 PM c/n issued, complete stair shafts, rails, glazing, rec'd const. joint firestop info, will review...need spec. insp/eng's reports.
BLD-Framing/Rough-in12/20/200112/21/200112/21/2001AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/20/2001 at 08:19:37. Contact: ###-####....see c/n, need eng's letter/ok 12/21/2001 11:58:25 AM
BLD-Conference12/11/200112/11/200112/11/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 12/11/2001 9:44:03 AM w/ John R.(?) arch w/ CHSQA re occ sep...1hr sep preferred/ req'd w/ shell as office tenant(McAlvaine) wants temp occ...
BLD-Framing/Rough-in12/11/200112/11/200112/11/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/11/2001 at 09:40:36. Contact: ###-####...wip, need wrap beams at upper level, ok to infill deck, seal shafts 12/11/2001 6:24:17 PM
BLD-Conference11/27/200111/27/200111/27/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 11/27/2001 11:13:18 AM need specs for expansion joint & firestops at occ. sep.
BLD-Framing/Rough-in11/19/200111/19/200111/19/2001PPART
DetailsDave Hannah
###-#### MIKE crew has installed ultra block first part of a two part systm on east stair tower basement to second floor and west stair tower basement to third floor ok to cover with culking the second part 11/19/2001 3:58:07 PM
BLD-Concrete11/15/200111/16/200111/16/2001PPART
DetailsCarl Dependahl
mike- ###-#### concrete; last segment, upper floor deck pending spec insp re 11/16/2001 5:37:24 PM
BLD-Framing/Rough-in11/15/200111/16/200111/16/2001APART
DetailsCarl Dependahl
fire proofing insp--mike ###-####...ultra bond safing installed at stairs, need sealants & expansion joint firestop at occ. sep. 11/16/2001 5:35:25 PM
BLD-Concrete11/9/200111/9/200111/9/2001PPART
DetailsCarl Dependahl
###-#### pt deck, pend reports. 11/9/2001 4:36:59 PM
BLD-Footing11/9/200111/9/200111/9/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 11/9/2001 4:36:33 PM w/ arch and Robin Carnes at site re stair enclosure...no extra penetrations allowed; provide 2hr assy for hydraulic line.
BLD-Concrete10/29/200111/2/200111/2/2001PPART
DetailsRuss Owen
###-#### MIKE s-i required pending rep. 11/2/2001 12:23:14 PM
BLD-Framing/Rough-in10/31/200111/2/200111/2/2001ANR
DetailsRuss Owen
###-#### MIKE REBAR
BLD-Wall cover11/1/200111/2/200111/2/2001ANR
DetailsRuss Owen
Scheduled by Inspector: 407 On 11/1/2001 5:13:48 PM
BLD-Energy code compliance10/31/200111/1/200111/1/2001ACANC
DetailsRuss Owen
###-#### MIKE
BLD-Concrete10/29/200110/30/200110/30/2001APART
DetailsRuss Owen
###-#### MIKE . Pending mti report. 10/31/2001 9:08:47 AM
BLD-Concrete10/17/200110/19/200110/19/2001PPART
DetailsCarl Dependahl
mike-- ###-#### concrete ; 10/19/2001 4:40:40 PM
BLD-Concrete10/17/200110/17/200110/17/2001PPART
DetailsCarl Dependahl
concrete ###-#### - mike upper pt deck...pend mti report 10/17/2001 4:08:04 PM
BLD-Concrete10/9/200110/12/200110/12/2001PPART
DetailsCarl Dependahl
###-#### MIKE cols' & p.t. deck pend mti report 10/12/2001 4:01:30 PM
BLD-Concrete10/9/200110/11/200110/11/2001PPART
DetailsJim Storey
###-#### MIKE covered with special insp reports pending 10/11/2001 2:58:52 PM
BLD-Concrete10/9/200110/10/200110/10/2001PPART
DetailsCarl Dependahl
###-#### MIKE...cols at upper deck, pend report 10/10/2001 2:55:12 PM
BLD-Concrete10/10/200110/10/200110/10/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 10/10/2001 9:07:00 AM west end, upper deck & col's ok pend MTI reports...met onsite w/supt.
BLD-Concrete10/3/200110/5/200110/5/2001PPART
DetailsCarl Dependahl
###-####
BLD-Concrete10/3/200110/4/200110/4/2001APART
DetailsCarl Dependahl
###-####...c/n issued re spec insp for masonry...ok pend report 10/4/2001 12:14:31 PM
BLD-Concrete9/28/200110/1/200110/1/2001APART
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 9/28/2001 4:41:20 PM partial, panel 11, pend report 10/1/2001 5:03:53 PM
BLD-Concrete9/28/200110/1/200110/1/2001PPART
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 9/28/2001 5:10:15 PM pt deck panel 11, pend report 10/1/2001 6:21:27 PM
BLD-Concrete9/25/20019/28/20019/28/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/25/2001 at 17:35:13. Contact: ###-####. parking struct. p 9/28/2001 5:10:50 PM end report 9/28/2001 5:11:02 PM
BLD-Concrete9/25/20019/27/20019/27/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/25/2001 at 17:34:18. Contact: ###-####.pend insp report 9/27/2001 2:50:21 PM
BLD-Concrete9/25/20019/26/20019/26/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/25/2001 at 17:33:26. Contact: ###-####. mcalvaine at parking struct; pt deck under spec insp...masonry? 9/26/2001 3:33:21 PM
BLD-Conference9/21/20019/21/20019/21/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 9/21/2001 5:50:49 PM w/ supt.need verify spec insps/engs ok for pt deck & masonry
BLD-Conference8/21/20018/21/20018/21/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 8/21/2001 9:46:14 AM mel ###-####; walk thru; pt deck pend SI report & eng's ok. 8/21/2001 4:35:52 PM
BLD-Concrete8/14/20018/15/20018/15/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/14/2001 at 12:39:03. Contact: ###-####....wip, p.t deck ok pend spec insp report. 8/15/2001 2:54:55 PM
BLD-Concrete7/23/20017/25/20017/25/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/23/2001 at 11:10:48. Contact: ###-####. placed w/si pending report. 7/25/2001 4:32:54 PM
BLD-Concrete7/23/20017/24/20017/24/2001APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 07/23/2001 at 11:09:56. Contact: ###-####. first floor pan deck and one column nw corner 7/24/2001 12:03:10 PM
BLD-Concrete7/3/20017/5/20017/5/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/03/2001 at 07:44:06. Contact: ###-####. placed with special insp, pending report 7/5/2001 10:33:29 AM. 7/5/2001 10:33:32 AM
BLD-Concrete6/7/20016/7/20016/7/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 6/7/2001 4:36:37 PM pt deck, need 2nd mat steel, wip
BLD-Concrete6/4/20016/5/20016/5/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/04/2001 at 15:56:51. Contact: ###-####...p.t deck center portion, looks ok. pending MTI report 6/5/2001 1:33:52 PM
BLD-Concrete5/31/20015/31/20015/31/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/31/2001 at 07:55:39. Contact: ###-####...1st deck, west 1/2...P.T. tendons, bar in place, appears ok pending spec. insp's report... consulted w/ Robin re rfi's 5/31/2001 3:40:36 PM
BLD-Concrete5/10/20015/14/20015/14/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/10/2001 at 10:59:39. Contact: . col's, walls, pending report. 5/14/2001 11:40:47 AM
BLD-Concrete5/10/20015/11/20015/11/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/10/2001 at 10:58:51. Contact: .pending insp report 5/11/2001 2:55:22 PM
BLD-Concrete5/10/20015/10/20015/10/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/10/2001 at 10:58:09. Contact: .pend mti reports 5/11/2001 10:21:56 AM
BLD-Concrete5/10/20015/10/20015/10/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 5/10/2001 4:17:31 PM COL'S, PEND SPEC INSP REPORT
BLD-Concrete5/3/20015/3/20015/3/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 5/3/2001 2:00:17 PM col's at S.E. corner...appear ok, pending insp reports.
BLD-Concrete4/30/20014/30/20014/30/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/30/2001 4:21:00 PM Wip; PEND REPORTS; walls to deck...2hr req'd...looks ok
BLD-Concrete4/12/20014/18/20014/23/2001PPART
DetailsCarl Dependahl
###-#### MIKE wip...pend reports 4/23/2001 10:55:23 AM
BLD-Concrete4/12/20014/20/20014/20/2001PPART
DetailsJim Storey
MIKE ###-#### placed with special insp.pending report. 4/20/2001 3:21:24 PM
BLD-Concrete4/12/20014/19/20014/19/2001PPART
DetailsJim Storey
MIKE ###-#### pws pending report. 4/19/2001 3:01:23 PM
BLD-Concrete4/12/20014/17/20014/17/2001PPART
DetailsCarl Dependahl
MIKE ###-####; cols, wall ok pend report 4/17/2001 5:37:07 PM
BLD-Concrete4/12/20014/16/20014/16/2001PPART
DetailsCarl Dependahl
MIKE ###-####; walls 1st level. cols all E-W gridlines WIP, appears ok pend spec insp reports 4/16/2001 4:37:37 PM
BLD-Concrete4/12/20014/13/20014/13/2001PPART
DetailsCarl Dependahl
MIKE ###-####...wip, pend insp report 4/13/2001 2:30:53 PM
BLD-Concrete4/12/20014/12/20014/12/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/12/2001 9:16:24 AM pend report; call all insps
BLD-Concrete4/12/20014/12/20014/12/2001PPART
DetailsCarl Dependahl
MIKE ###-####; pend spec insp report. 4/12/2001 6:13:57 PM
BLD-Concrete4/9/20014/9/20014/9/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/9/2001 6:20:11 PM WIP, col's & ftg's
BLD-Conference4/4/20014/4/20014/4/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/4/2001 11:47:00 AM w/ Proj. mgr Bob Gridley & Robin Carnes; fnd insps under spec insp Mike Spiker w/ MTI
BLD-Concrete3/26/20013/29/20013/29/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 03/26/2001 at 16:31:25. Contact: ###-####. wip 3/29/2001 1:40:36 PM
BLD-Concrete3/26/20013/28/20013/28/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/26/2001 at 16:30:30. Contact: ###-####. placed w/specia insp. pendingreport. 3/28/2001 2:14:34 PM
BLD-Concrete3/26/20013/27/20013/27/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 03/26/2001 at 16:29:41. Contact: ###-####. wip spec insp 3/27/2001 1:45:15 PM
BLD-Footing3/23/20013/23/20013/23/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 3/23/2001 8:27:07 AM north slope shot-creted to prevent sluff...ok non struct. per supt. WIP on north ftgs, mti onsite
BLD-Footing3/19/20013/20/20013/20/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/19/2001 at 15:04:58. Contact: ###-####.
BLD-Footing3/15/20013/16/20013/16/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/15/2001 at 16:34:27. Contact: ###-####.pend insp report 3/16/2001 3:42:39 PM
BLD-Footing3/13/20013/14/20013/14/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/13/2001 at 14:09:55. Contact: ###-####. placed with special insp. pending report. 3/14/2001 9:37:54 AM
BLD-Footing3/7/20013/9/20013/9/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/07/2001 at 13:08:13. Contact: ###-####. B & K ftgs at west 1/2 south wall line 3/9/2001 12:43:04 PM