Permanent Occupancy | | 5/22/2002 | 5/22/2002 | | DONE |
|
|
|
|
BLD-Final | 11/27/2001 | 11/28/2001 | 11/28/2001 | A | PART |
Tom Arcoraci
|
|
|
DARRELL ###-#### --FN ok for temp when code enforcement signs ok for perm when others sign perm occ 11/28/2001 11:22:46 AM
|
FIRE-Final Inspection | 11/26/2001 | 11/26/2001 | 11/26/2001 | P | PASS |
Rick Jackson
|
|
|
###-#### APRIL address on permit reflects 3842; address on building reflects 3818; address on approved plans reflects 3820; April went to addressing and corrected address - 3818!!! 11/26/2001 4:16:57 PM
|
BLD-Footing | 11/1/2001 | 11/1/2001 | 11/1/2001 | A | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 11/1/2001 9:58:08 AM holes for parking canopys
|
BLD-Footing | 10/30/2001 | 10/31/2001 | 10/31/2001 | P | FAIL |
Dave Hannah
|
|
|
Phillip, ###-####no plans on site 10/31/2001 3:24:39 PM
|
BLD-Footing | 10/29/2001 | 10/30/2001 | 10/30/2001 | A | CANC |
Dave Hannah
|
|
|
###-####
|
BLD-Footing | 10/26/2001 | 10/29/2001 | 10/29/2001 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/26/2001 at 15:23:01. Contact: ###-####. BY CONTRACTOR 10/29/2001 9:20:47 AM
|
BLD-Aging Inspection | 9/10/2001 | 9/10/2001 | 9/10/2001 | | PASS |
Jim Storey
|
|
|
wip 9/10/2001 7:55:24 AM
|
BLD-Energy code compliance | 7/9/2001 | 7/10/2001 | 7/10/2001 | A | PASS |
Dave Hannah
|
|
|
energy code dwayne ###-####
|
BLD-Framing/Rough-in | 7/9/2001 | 7/10/2001 | 7/10/2001 | A | DONE |
Dave Hannah
|
|
|
fr insp-- dwayne ###-####
|
BLD-Energy code compliance | 7/3/2001 | 7/6/2001 | 7/6/2001 | A | NR |
Russ Owen
|
|
|
Daryl ###-####left c/n to complete and recall. 7/6/2001 10:16:08 AM
|
BLD-Framing/Rough-in | 6/26/2001 | 6/27/2001 | 6/27/2001 | A | PASS |
Jim Storey
|
|
|
Darrel ###-####
|
BLD-Framing/Rough-in | 6/6/2001 | 6/6/2001 | 6/6/2001 | P | PART |
Jim Storey
|
|
|
shear nail on the first floor April ###-#### first floor stair wells sheer nailling ok for gyp. cover. 6/6/2001 4:53:16 PM
|
BLD-Framing/Rough-in | 6/1/2001 | 6/4/2001 | 6/4/2001 | P | PART |
Jim Storey
|
|
|
###-#### second floor exterior nailling ok 6/4/2001 3:29:54 PM
|
BLD-Foundation | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | PASS |
Steven Webb
|
|
|
Duane ###-#### Already poured--contractor said had special inspection (MTI). 5/24/2001 11:23:59 AM
|
BLD-Foundation | 5/23/2001 | 5/23/2001 | 5/23/2001 | P | FAIL |
Russ Owen
|
|
|
slab DAryl ###-#### all int footings are required to 16 in wide accross the bottom,also rebar is not held inplace laying in bottom of footing. notified contractor at site. 12/23/2001 2:40:30 PM
|
BLD-Conference | 5/11/2001 | 5/11/2001 | 5/11/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/11/2001 8:42:15 AM w/ bldr re insp req's
|
BLD-Footing | 5/2/2001 | 5/2/2001 | 5/2/2001 | P | PART |
Carl Dependahl
|
|
|
Darrell ###-####...ftgs, pour at own risk , pend soils report 5/2/2001 5:28:13 PM
|