BLD-Aging Inspection | 8/15/2003 | 8/15/2003 | 8/15/2003 | | CANC |
Russ Owen
|
|
|
|
BLD-Aging Inspection | 1/14/2002 | 1/14/2002 | 1/14/2002 | | PART |
Russ Owen
|
|
|
no insp called for . 1/14/2002 10:19:21 AM
|
BLD-Conference | 11/13/2001 | 11/13/2001 | 11/13/2001 | | DONE |
|
|
|
permit extension
|
BLD-Aging Inspection | 10/16/2001 | 10/16/2001 | 10/16/2001 | | PART |
Russ Owen
|
|
|
2nd phase not started yet. 10/16/2001 10:59:34 AM
|
BLD-Aging Inspection | 8/16/2001 | 8/16/2001 | 8/16/2001 | | PART |
Russ Owen
|
|
|
2nd faze not yet started. 8/22/2001 1:10:16 PM
|
BLD-Final | 6/5/2001 | 6/5/2001 | 6/5/2001 | P | PART |
Russ Owen
|
|
|
John Taylor ###-#### need to install the new stair case and upper floor offfice area work has not been completed, need penetrations on firewall, caulked and removed 6 in exhaust duct out of firewall. 1/5/2002 4:31:04 PM
|
FIRE-Final Inspection | 5/23/2001 | 5/30/2001 | 5/30/2001 | A | PASS |
Joe Tawney
|
|
|
Reinsp Pass on phase II of permit 5/30/2001 8:49:00 AM
|
BLD-Final | 5/18/2001 | 5/18/2001 | 5/18/2001 | P | FAIL |
Joe Tawney
|
|
|
Added by Inspector: 406 On 5/18/2001 2:12:10 PM Reinsp Fail Fire door and batteries in FACP, Knox Box, breaker lock for FACP
|
BLD-Framing/Rough-in | 4/23/2001 | 4/23/2001 | 4/23/2001 | P | PART |
Russ Owen
|
|
|
tom ###-#### ok to sheetrock lower floor walls only ,upper floor not done.also ceiling not done. 11/23/2001 3:49:21 PM
|
FIRE-Final Inspection | 2/28/2001 | 3/1/2001 | 3/1/2001 | A | FAIL |
Joe Tawney
|
|
|
Final Fail C/N issued. 3/2/2001 8:16:30 AM
|
BLD-Framing/Rough-in | 2/27/2001 | 2/28/2001 | 2/28/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/27/2001 at 10:03:00. Contact: .went over req for final. 2/28/2001 1:36:14 PM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/21/2001 | 2/21/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 12:45:20. Contact: .1st layer drywall at lid over office. 2/21/2001 1:52:18 PM
|
BLD-Framing/Rough-in | 2/14/2001 | 2/15/2001 | 2/15/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/14/2001 at 16:40:44. Contact: .Ok to cover new tall wall ,now constructed ok, architect has revised line of separation wall, ok as revised only i have requested a detail for the 1 hr horizontal portion of the wall over the office area. 2/15/2001 12:48:58 PM
|
BLD-Framing/Rough-in | 2/8/2001 | 2/9/2001 | 2/9/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 11:43:47. Contact: ###-####.Need to have architect reveiw the existing construction and submit any neccessary revisions as the firewall at north of existing rest room is not being cont as plans. south of this is ok. also architect needs to provide a detail for support of the new tall firewall in the shop. went over these items with building tenant/contractor. 2/9/2001 10:56:48 AM
|