BLD-Final | 7/16/2002 | 7/17/2002 | 7/17/2002 | A | PASS |
Carl Dependahl
|
|
|
scott; Phone #: ###-####
|
Permanent Occupancy | | 7/17/2002 | 7/17/2002 | | DONE |
|
|
|
|
BLD-Final | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | NR |
Carl Dependahl
|
|
|
###-####
|
BLD-Final | 6/17/2002 | 6/17/2002 | 6/17/2002 | P | NR |
Carl Dependahl
|
|
|
SCOTT ###-####
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | P | NR |
Carl Dependahl
|
|
|
scott ###-#### fn will recall 6/14/2002 5:14:35 PM
|
BLD-Final | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | NR |
Jim Storey
|
|
|
|
BLD-Final | 3/27/2002 | 3/27/2002 | 3/27/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/27/2002 3:20:42 PM c/n, handrail extensions, caulk-seal penetrations, complete misc finish items & obtain other permanent finals...ok for t/o
|
FIRE-Final Inspection | 3/25/2002 | 3/26/2002 | 3/26/2002 | A | PASS |
Rick Jackson
|
|
|
###-#### scott
|
BLD-Aging Inspection | 1/14/2002 | 1/14/2002 | 1/17/2002 | | NR |
Carl Dependahl
|
|
|
apts, wip. 1/17/2002 9:18:57 AM
|
BLD-Energy code compliance | 11/14/2001 | 11/14/2001 | 11/14/2001 | P | PASS |
Carl Dependahl
|
|
|
###-#### SCOTT insul ok. 11/14/2001 5:08:25 PM
|
BLD-Framing/Rough-in | 11/14/2001 | 11/14/2001 | 11/14/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/14/2001 5:09:29 PM apt units all floors ok to cover,
|
BLD-Framing/Rough-in | 11/13/2001 | 11/14/2001 | 11/14/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/13/2001 at 18:02:31. Contact: ###-####....keep c/n, 2hr wall at west ok to add 2nd layer....need complete firestops at 1hr lids added at "closets", drop clg areas & soffited areas at party walls. complete R.C. install at 2nd fl lids, ok to insul thru-out. 11/14/2001 11:00:27 AM
|
BLD-Framing/Rough-in | 11/12/2001 | 11/13/2001 | 11/13/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/12/2001 at 17:17:27. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/12/2001 | 11/12/2001 | 11/13/2001 | P | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/12/2001 at 11:18:37. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | FAIL |
Carl Dependahl
|
|
|
###-#### SCOTT verbal c/n: complete firestops, 1hr lid at closets & soffit areas where missed, strap brg wall top plates as need. ok to insul. 11/6/2001 4:54:09 PM
|
BLD-Framing/Rough-in | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | NR |
Carl Dependahl
|
|
|
###-#### scott
|
BLD-Framing/Rough-in | 10/8/2001 | 10/9/2001 | 10/9/2001 | A | NR |
Carl Dependahl
|
|
|
fr insp -scott ###-####
|
BLD-Conference | 8/10/2001 | 8/10/2001 | 8/10/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/10/2001 4:47:29 PM c/n, firestops, 2hr wall, etc.
|
BLD-Conference | 7/10/2001 | 7/10/2001 | 7/10/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/10/2001 5:30:44 PM w/ Mike re elev. shaft at s-3 parking...need rated door
|
BLD-Conference | 6/29/2001 | 7/3/2001 | 7/3/2001 | A | PART |
Carl Dependahl
|
|
|
scott ###-#### please call before going out, mark resubmittal re shafts & hvac penetrations to comply w/ ubc 711.3 7/3/2001 2:04:46 PM
|
BLD-Conference | 6/21/2001 | 6/21/2001 | 6/21/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/21/2001 1:29:53 PM e 2hr walls...draft-stops, fireblocks& ass'ys
|
BLD-Conference | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/19/2001 12:23:20 PM w/ owner, framer re 1hr const, 2hr walls
|
BLD-Conference | 6/18/2001 | 6/18/2001 | 6/18/2001 | P | PASS |
Carl Dependahl
|
|
|
scott ###-####; initial conf, verbal c/n re 2hr wall 6/22/2001 4:27:21 PM
|