Permanent Occupancy | | 1/15/2002 | 1/15/2002 | | DONE |
|
|
|
|
BLD-Final | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/12/2001 at 15:08:25. Contact: ###-####. ok for perm occ 12/13/2001 10:40:42 AM
|
FIRE-Final Inspection | 12/5/2001 | 12/5/2001 | 12/5/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/5/2001 2:15:48 PM Fire life/safety finaled. Fire alarm finaled. Sprinkler system not finaled
|
BLD-Framing/Rough-in | 10/11/2001 | 10/11/2001 | 10/11/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/11/2001 at 11:23:07. Contact: ###-####.
int. framing in existing shop ok pending trades 10/15/2001 8:21:38 AM
|
BLD-Final | 9/27/2001 | 9/28/2001 | 9/28/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 09/27/2001 at 16:16:06. Contact: ###-####.
showroom ok for temp.occ. pending FLSaftey sign-off, c/n on ADA restrooms 9/28/2001 4:26:40 PM
|
FIRE-Alarm Testing | 9/27/2001 | 9/28/2001 | 9/28/2001 | A | NR |
Joe Tawney
|
|
|
approved plans not on site but system is installed. 9/28/2001 5:39:34 PM 9/28/2001 5:40:27 PM
|
FIRE-Final Inspection | 9/27/2001 | 9/28/2001 | 9/28/2001 | A | PART |
Joe Tawney
|
|
|
OK to occup. new showroom waiting for rough-in on existing 9/28/2001 5:41:50 PM
|
BLD-Final | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 10:42:28. Contact: ###-####.
parts room ok for temporary occupy after fire and life signs off. NOTE; NO OCCUPANCY CERTIFICATE TO BE ISSUED YET, UNTIL COMPLETE SCOPE OF WORK IS FINISHED. 9/20/2001 10:34:11 AM
|
FIRE-Final Inspection | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | FAIL |
Joe Tawney
|
|
|
Final on shop area only. Fail mount fire Ext and exit door hdwre 9/20/2001 9:25:52 AM
|
FIRE-Final Inspection | 9/20/2001 | 9/20/2001 | 9/20/2001 | P | PART |
Joe Tawney
|
|
|
Reinsp OK for temporary Occ of new shop in NW corner of bldg 9/20/2001 4:14:54 PM
|
BLD-Conference | 8/30/2001 | 8/30/2001 | 8/30/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/30/2001 3:50:10 PM ok to use new parts room w operational wet sprinklers at that area; ok per Joe T.
|
BLD-Final | 8/30/2001 | 8/30/2001 | 8/30/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/30/2001 at 10:32:10. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/24/2001 at 07:57:22. Contact: ###-####.
interior steel headers between new and old ok pending eng. letter on bolts and s.i. on welds, ok to cover after welding inspection 8/24/2001 4:14:16 PM
|
BLD-Footing | 8/22/2001 | 8/22/2001 | 8/22/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 07:30:38. Contact: ###-####.
int. pads for beam between show rooms 8/22/2001 3:51:47 PM
|
BLD-Framing/Rough-in | 8/22/2001 | 8/22/2001 | 8/22/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 07:31:31. Contact: ###-####.office walls and ceiling in 3 offices 8/22/2001 3:53:16 PM
|
BLD-Conference | 8/13/2001 | 8/14/2001 | 8/14/2001 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/13/2001 at 16:02:39. Contact: ###-####.
conf. on final, temp. occ., ada reqmts., etc. 8/14/2001 12:28:57 PM
|
BLD-Framing/Rough-in | 8/2/2001 | 8/3/2001 | 8/3/2001 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/02/2001 at 14:37:55. Contact: ###-####. 8/3/2001 9:19:58 AM non load bearing walls inside ext area still need elec inspection 8/3/2001 11:23:19 AM
|
BLD-Framing/Rough-in | 7/24/2001 | 7/25/2001 | 7/25/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/24/2001 at 10:53:00. Contact: ###-####.c/n on part, ok to rock unaffected areas, verify rest of upper fire wall later 7/25/2001 10:55:27 AM
|
BLD-Framing/Rough-in | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | PART |
Tony Young
|
|
|
c/n posted, ok to insulate unaffected areas 7/18/2001 3:23:58 PM
|
BLD-Framing/Rough-in | 7/16/2001 | 7/17/2001 | 7/17/2001 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/16/2001 at 10:31:21. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/17/2001 | 7/17/2001 | 7/17/2001 | P | CANC |
Tony Young
|
|
|
no time 7/17/2001 6:31:44 PM
|
BLD-Conference | 7/10/2001 | 7/11/2001 | 7/11/2001 | A | PART |
Tony Young
|
|
|
take plan back yo architect for clarification of 1 hr sep. wall at added room 7/11/2001 11:54:33 AM
|
BLD-Conference | 7/9/2001 | 7/10/2001 | 7/10/2001 | A | CANC |
Tony Young
|
|
|
re-schedule 7/10/2001 4:05:23 PM
|
BLD-Conference | 7/6/2001 | 7/9/2001 | 7/9/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/06/2001 at 09:17:22. Contact: ###-####.
|
BLD-Conference | 6/26/2001 | 6/27/2001 | 6/27/2001 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/26/2001 at 13:29:22. Contact: ###-####.
conf. on adding to plan, told them to have arch. draw and write up addition and changes and call back for review// may need to go to plan review 6/27/2001 3:24:59 PM
|
BLD-Conference | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/04/2001 at 15:04:25. Contact: ###-####. CN ISSUED NEED NEW DETAILS FOR ONE HOUR WALL WHERE JOISTS NOW PASS THRU IT 6/5/2001 10:36:58 AM
|
BLD-Conference | 5/31/2001 | 6/1/2001 | 6/1/2001 | A | PASS |
Tony Young
|
|
|
###-####.
conf. on sheetrock on existing roof deck, ok if stepped on during construction 6/1/2001 10:02:13 AM
|
BLD-Footing | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/23/2001 at 14:26:27. Contact: ###-####.
not ready yet, pending s. i. report 5/24/2001 9:39:26 AM
|
BLD-Footing | 5/9/2001 | 5/9/2001 | 5/9/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/09/2001 at 10:27:46. Contact: ###-####.
already poured, pending S. i. report 5/9/2001 3:49:10 PM
|
BLD-Conference | 5/7/2001 | 5/7/2001 | 5/7/2001 | A | PASS |
Tony Young
|
|
|
met w/ dixie and heating contractor on area seperation wall and other items 5/7/2001 10:02:51 AM
|
BLD-Foundation | 5/7/2001 | 5/7/2001 | 5/7/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/07/2001 at 10:56:42. Contact: ###-####.
pending s. i. tests 5/7/2001 3:34:31 PM
|
BLD-Footing | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/04/2001 at 11:27:34. Contact: ###-####.
verbal corrections, pending s. i. report 5/4/2001 2:53:37 PM
|
BLD-Conference | 5/2/2001 | 5/2/2001 | 5/2/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/02/2001 at 07:16:46. Contact: ###-####.
conference on special inspections 5/2/2001 3:45:37 PM
|