BLD-Final | 1/11/2002 | 1/11/2002 | 1/11/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/11/2002 1:50:47 PM Ok perm oc. cards delivered tto store this day.1/11/2002 1:57:14 PM 1/11/2002 2:02:09 PM
|
FIRE-Final Inspection | 1/15/2002 | 11/18/2001 | 11/18/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 1/15/2002 12:26:58 PM Fire life/safety finaled
|
BLD-Final | 11/9/2001 | 11/9/2001 | 11/9/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 11/9/2001 1:59:46 PM . Needs Fire/Life Safety, Zoning, ACHD . And non- compliance items on final special inspection report approved by the project engineer. See permit #bld01-02385 for Denver mattres Tennant improvement. 11/9/2001 2:05:19 PM
|
BLD-Final | 11/9/2001 | 11/9/2001 | 11/9/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 11/9/2001 4:01:08 PM ok temp oc , see am inspection history for addn info. 11/9/2001 4:20:33 PM
|
BLD-Final | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | NR |
Russ Owen
|
|
|
###-#### ELDEN NEEDS TEMP OCCUPANCY
|
BLD-Framing/Rough-in | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 11:44:04. Contact: ###-####. ok to cover baths in center and west bld 9/20/2001 9:43:55 AM
|
BLD-Framing/Rough-in | 8/28/2001 | 8/28/2001 | 8/28/2001 | P | PART |
Russ Owen
|
|
|
craig-- ###-####--fr insp ok to cover areas with-out plumbing. 8/28/2001 5:08:16 PM
|
BLD-Conference | 8/20/2001 | 8/20/2001 | 8/20/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 8/20/2001 3:53:30 PM
|
BLD-Framing/Rough-in | 8/10/2001 | 8/10/2001 | 8/10/2001 | P | PART |
Russ Owen
|
|
|
FR INSP- DIRK - ###-#### . NOTE:needs a tennant improvement permit, schell only. 8/13/2001 12:21:49 PM
|
BLD-Foundation | 6/27/2001 | 6/27/2001 | 6/27/2001 | P | PART |
Russ Owen
|
|
|
###-#### subject to si. 6/27/2001 3:24:21 PM
|
BLD-Footing | 6/25/2001 | 6/26/2001 | 6/26/2001 | A | PART |
Russ Owen
|
|
|
corey ###-#### special inspection reports on site. 6/26/2001 11:56:16 AM
|
BLD-Concrete | 6/14/2001 | 6/15/2001 | 6/15/2001 | A | PART |
Russ Owen
|
|
|
###-#### subject to s-i. 1/15/2002 4:06:29 PM
|
BLD-Foundation | 6/13/2001 | 6/14/2001 | 6/14/2001 | A | PART |
Russ Owen
|
|
|
stem wall eric ###-#### ok subject to special insp. 1/14/2002 12:27:25 PM
|
BLD-Foundation | 6/13/2001 | 6/13/2001 | 6/13/2001 | P | PART |
Russ Owen
|
|
|
corey ###-####
|
BLD-Foundation | 6/11/2001 | 6/11/2001 | 6/11/2001 | P | PASS |
Dave Hannah
|
|
|
corey ###-#### MTI on site testing and inspecting 6/11/2001 1:50:12 PM
|
BLD-Footing | 6/7/2001 | 6/8/2001 | 6/8/2001 | A | PART |
Russ Owen
|
|
|
pour at 10:30= cory ###-#### subject to s-i. 1/8/2002 4:01:02 PM
|
BLD-Footing | 6/6/2001 | 6/6/2001 | 6/6/2001 | P | PART |
Russ Owen
|
|
|
cory ###-#### s-i required insp. 1/6/2002 5:14:33 PM
|
BLD-Footing | 6/1/2001 | 6/1/2001 | 6/1/2001 | P | PART |
Russ Owen
|
|
|
pouring at 1:00 corey ###-#### subject to ,mti inspection. 1/4/2002 9:38:09 AM
|
BLD-Footing | 5/30/2001 | 5/30/2001 | 5/30/2001 | P | PART |
Russ Owen
|
|
|
pouring at 2 ###-#### final pour footings. 12/30/2001 4:31:21 PM
|
BLD-Framing/Rough-in | 5/30/2001 | 5/30/2001 | 5/30/2001 | P | PART |
Russ Owen
|
|
|
fr insp --dirk ###-#### interior non bearing walls and east to west tall walls ok to cover. 12/30/2001 4:31:00 PM
|
BLD-Foundation | 5/29/2001 | 5/29/2001 | 5/29/2001 | P | PART |
Russ Owen
|
|
|
###-#### inspection will be performed by mti. 12/30/2001 10:11:57 AM
|
BLD-Footing | 5/24/2001 | 5/24/2001 | 5/24/2001 | P | PART |
Jim Storey
|
|
|
###-#### pour 3:30 pending rfi's and special insp report bach time on waiting truck in qustion. 5/24/2001 4:14:11 PM
|
BLD-Footing | 5/22/2001 | 5/22/2001 | 5/22/2001 | P | PART |
Russ Owen
|
|
|
Cory ###-#### north and east footing ok also inspections by special inspector required for design also cmu wall above went over requirements with contractor. MTI will be contracted. 12/22/2001 2:51:07 PM
|