Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD01-00460
StatusFinaled
Name LES SCHWAB TIRE CENTERS OF
Site Address 6017 W FAIRVIEW AVE
Project NameLES SCHWAB TIRES
Customer Number 
ePlanReviewNo
Description
(LES SCHWAB TIRES) To add approximately 3,640 sq.ft. to the existing vehicle repair garage and modify existing CMU wall to a two hour area separation wall. The area separation wall will divide this building into two separate buildings. The east portion will be 4,140 sq.ft and the remainder building will be 15,900 sq.ft. Additional work included in this permit is to remodel the interior retail sales area and provide a one-hour occupancy separation wall between the repair garage area and the office, retail areas. All construction per the approved plans, attached comment list and CABO/ANSI A117.1. DRH01-00014 PC#165-01 MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/25/20024/26/20024/26/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 04/25/2002 at 13:13:26. Contact: ###-####. ok for perm 4/26/2002 4:56:35 PM
FIRE-Final Inspection4/26/20024/26/20024/26/2002APASS
DetailsTroy Cobbley
fire life/safety, fire alarm and fire sprinkler finaled
Permanent Occupancy 4/26/20024/26/2002 DONE
Details
BLD-Final4/12/20024/15/20024/15/2002PNR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 04/12/2002 at 15:16:42. Contact: ###-####.
BLD-Final1/30/20021/31/20021/31/2002AFAIL
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/30/2002 at 09:48:13. Contact: ###-####. needs door label ect in 2 hr wall 1/31/2002 12:19:37 PM
BLD-Framing/Rough-in1/14/20021/15/20021/15/2002APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/14/2002 at 12:14:07. Contact: ###-####. wip ok to cover bath walls and ceiling 1/15/2002 10:17:39 AM
BLD-Framing/Rough-in12/27/200112/28/200112/28/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/27/2001 at 15:01:24. Contact: ###-####. wip 1 hr occ sep wall 12/28/2001 9:23:38 AM
BLD-Framing/Rough-in12/17/200112/18/200112/18/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/17/2001 at 09:18:59. Contact: ###-####. wip 12/18/2001 8:34:52 AM
BLD-Wall cover12/17/200112/18/200112/18/2001PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 12/17/2001 3:35:24 PM partial occ sep wall ok 12/18/2001 2:39:09 PM
BLD-Wall cover12/17/200112/17/200112/17/2001PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 12/17/2001 3:34:42 PM
BLD-Wall cover12/14/200112/14/200112/14/2001PCANC
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 12/14/2001 9:33:05 AM wip 12/14/2001 1:52:03 PM
BLD-Conference11/30/200111/30/200111/30/2001APASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 11/30/2001 8:13:43 AM occ sep ok to have truss pass thru if fire stopped around truss per mike phillips 11/30/2001 8:40:21 AM
BLD-Framing/Rough-in11/28/200111/29/200111/29/2001PFAIL
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/28/2001 at 14:57:40. Contact: ###-####. need new detail for occ wall
cn issued 11/29/2001 12:42:01 PM
BLD-Framing/Rough-in10/31/200111/1/200111/1/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/31/2001 at 09:06:58. Contact: ###-####. wip 11/1/2001 9:30:06 AM
BLD-Conference10/19/200110/19/200110/19/2001PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 10/19/2001 3:20:21 PM wip 10/19/2001 4:44:32 PM
BLD-Framing/Rough-in10/12/200110/12/200110/12/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/12/2001 at 07:22:43. Contact: ###-####. wip 10/12/2001 11:18:37 AM
BLD-Framing/Rough-in10/12/200110/12/200110/12/2001PPART
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 10/12/2001 10:25:57 AM wip 10/12/2001 2:56:03 PM
BLD-Framing/Rough-in9/26/200110/3/200110/3/2001APART
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 9/26/2001 8:34:05 AM wip 10/3/2001 8:37:23 AM
BLD-Framing/Rough-in9/28/200110/1/200110/1/2001ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 09/28/2001 at 09:42:49. Contact: ###-####.
BLD-Framing/Rough-in10/1/200110/1/200110/1/2001PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/01/2001 at 10:09:50. Contact: ###-####. roof nailing and straping 10/1/2001 4:49:10 PM
BLD-Framing/Rough-in9/18/20019/26/20019/26/2001APART
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 9/18/2001 4:30:33 PM see randy WIP 9/26/2001 11:24:10 AM
BLD-Framing/Rough-in9/17/20019/18/20019/18/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 09/17/2001 at 11:45:57. Contact: ###-####. spec insp 9/18/2001 3:27:21 AM
BLD-Footing9/5/20019/6/20019/6/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 09/05/2001 at 11:24:59. Contact: ###-####.
BLD-Conference8/29/20018/29/20018/29/2001PPASS
DetailsTom Arcoraci
for conf --randy-- ###-#### pre job conf 8/29/2001 5:07:01 AM