(PERKING COI LLP)(ONE FRONT STREET-4TH FLR) To construct a 7,548 sq.ft. office tenant on the 4th floor per approved plans on file. Work to include, construction of approximately 57 lf of one-hour tenant demising wall, approximately 144 lf of one-hour fire resistive corridor walls, interior noncombustible partitions to create hallways, office spaces, breakroom, reception area, small conference rooms, installation of suspended ceiling system, mechanical, electrical and plumbing. Miscelaneous related finishes. A SEPARATE PERMIT IS REQUIRED TO FINISH AND OCCUPY THE REMAINING 3944 SF AREA ON THE FOURTH FLOOR. NOTE: This building is fully fire sprinklered for 1-hr. substitution. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. (P.C.#0179-01)*RMH*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection7/19/20017/19/20017/19/2001APASS
DetailsRick Jackson
Added by Inspector: 409 On 7/19/2001 8:04:12 AM
Permanent Occupancy 7/19/20017/19/2001 DONE
Details
BLD-Final7/17/20017/18/20017/18/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/17/2001 at 08:41:24. Contact: ###-####. final ok pending fire sign off. 7/18/2001 5:04:48 PM
BLD-Final7/17/20017/18/20017/18/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/17/2001 at 08:41:24. Contact: ###-####. final ok pending fire sign off. 7/18/2001 5:04:48 PM
FIRE-Alarm Testing7/17/20017/18/20017/18/2001AFAIL
DetailsRick Jackson
BUCK ###-#### FIRE ALM TEST c/n issued 7/18/2001 9:41:54 AM
FIRE-Final Inspection7/17/20017/18/20017/18/2001AFAIL
DetailsRick Jackson
AT 8:30 ??? BUCK-- ###-#### FN FIRE
FIRE-Alarm Testing7/16/20017/17/20017/17/2001PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/16/2001 at 11:11:36. Contact: ###-####. CANCEL PER BUCK
FIRE-Final Inspection7/16/20017/17/20017/17/2001PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/16/2001 at 11:12:47. Contact: ###-####.--CANCEL PER BUCK/MLS
BLD-Conference7/12/20017/12/20017/12/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 7/12/2001 11:40:41 AM w/ bldr...need fire & elec for t/o; verified 3hr doors at bsmt elev shaft entry
FIRE-Hydro test above ground7/2/20017/2/20017/2/2001PPASS
DetailsJoe Tawney
###-#### OK on 4th flr hydro test 7/2/2001 1:01:02 PM
FIRE-Sprinkler Rough-in6/26/20016/26/20016/26/2001PPASS
DetailsRick Jackson
Doug ###-#### r/i okay to cover 6/26/2001 10:48:06 AM
BLD-Other6/22/20016/22/20016/22/2001AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/22/2001 at 07:27:07. Contact: ###-####. need wires pods, firecaulk corridor 6/22/2001 12:11:11 PM
BLD-Other6/20/20016/21/20016/21/2001ANR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/20/2001 at 14:55:28. Contact: ###-####.
BLD-Framing/Rough-in5/9/20015/9/20015/9/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 5/9/2001 10:58:25 AM ok to usr frt wood at door/window openings w/i assy
BLD-Conference5/1/20015/1/20015/1/2001PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 05/01/2001 at 08:38:52. Contact: ###-####. w/ contractor, ok to use frt wood within walls 5/1/2001 4:10:48 PM
BLD-Wall cover4/25/20014/26/20014/26/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/25/2001 at 15:21:28. Contact: ###-####.complete firestops & submit detail for tunnel...ok to cover 4/26/2001 12:24:43 PM
BLD-Wall cover4/19/20014/19/20014/19/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 04/19/2001 at 11:11:01. Contact: ###-####. top of corridor ceilling only. 4/19/2001 3:01:59 PM