BLD-Final | 10/2/2001 | 10/3/2001 | 10/3/2001 | A | PASS |
Russ Owen
|
|
|
###-####. ok permanent occupancy. 10/3/2001 10:17:59 AM
|
Permanent Occupancy | | 10/3/2001 | 10/3/2001 | | DONE |
|
|
|
|
BLD-Final | 9/12/2001 | 9/13/2001 | 9/13/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/12/2001 at 13:29:42. Contact: ###-####. need s-i final letter need to support cantilevered projection above front counter,need to fire tap 1 hr shafts. all other signatures have been signed for permanent oc. wright brothers is contact ###-####. 9/13/2001 11:11:11 AM
|
BLD-Final | 9/12/2001 | 9/13/2001 | 9/13/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/12/2001 at 13:29:42. Contact: ###-####. need s-i final letter need to support cantilevered projection above front counter,need to fire tap 1 hr shafts. all other signatures have been signed for permanent oc. wright brothers is contact ###-####. 9/13/2001 11:11:11 AM
|
BLD-Conference | 8/31/2001 | 8/31/2001 | 8/31/2001 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/31/2001 at 08:39:10. Contact: ###-####.
|
BLD-Final | 8/31/2001 | 8/31/2001 | 8/31/2001 | P | PART |
Russ Owen
|
|
|
###-####ok temp oc c/n posted for other items. 8/31/2001 3:54:22 PM
|
FIRE-Final Inspection | 8/31/2001 | 8/31/2001 | 8/31/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/31/2001 3:22:22 PM
|
FIRE-Final Inspection | 8/30/2001 | 8/30/2001 | 8/30/2001 | P | CANC |
Joe Tawney
|
|
|
fire fn - cathy ###-#### Cancel Reschedule 8/30/2001 5:13:49 PM
|
FIRE-Final Inspection | 8/29/2001 | 8/29/2001 | 8/29/2001 | P | FAIL |
Joe Tawney
|
|
|
Reinsp Fail C/N issued 8/29/2001 2:07:39 PM
|
BLD-Conference | 8/28/2001 | 8/28/2001 | 8/28/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/28/2001 at 10:53:58. Contact: ###-####. kitchen grid. 8/28/2001 2:09:49 PM
|
BLD-Conference | 8/26/2001 | 8/27/2001 | 8/27/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/26/2001 at 20:17:39. Contact: ###-####. kitchen grid. 8/27/2001 11:34:57 AM
|
FIRE-Alarm Testing | 8/24/2001 | 8/27/2001 | 8/27/2001 | A | FAIL |
Joe Tawney
|
|
|
###-#### matt Final Fail Hoods tested OK. Need air bal report. Not ready on other issues 8/27/2001 11:14:48 AM
|
BLD-Conference | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel 8/24/2001 1:27:39 PM
|
BLD-Conference | 8/20/2001 | 8/21/2001 | 8/21/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/20/2001 at 21:49:57. Contact: ###-####.front dining grid ok. 8/21/2001 4:05:32 PM
|
BLD-Conference | 8/15/2001 | 8/16/2001 | 8/16/2001 | A | CANC |
Tom Arcoraci
|
|
|
###-####
|
BLD-Framing/Rough-in | 8/16/2001 | 8/16/2001 | 8/16/2001 | P | FAIL |
Tom Arcoraci
|
|
|
grid ceiling Matt ###-#### GRID INCOMPLETE MADE VERBAL TO SUPER WILL NEED TO RECALL 8/16/2001 3:06:56 AM
|
BLD-Conference | 8/9/2001 | 8/9/2001 | 8/9/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/09/2001 at 07:35:05. Contact: ###-####.. need to sheetrock above shafts, built as per detail, NOTE: detail porly drawn at roof penetration of shafts now constructed But constructed as per plans. 8/9/2001 4:25:04 PM
|
BLD-Conference | 8/7/2001 | 8/7/2001 | 8/7/2001 | P | PART |
Russ Owen
|
|
|
###-#### MATT
. working on shafts for grease hoods, 8/7/2001 3:46:32 PM
|
BLD-Framing/Rough-in | 7/24/2001 | 7/25/2001 | 7/25/2001 | A | PART |
Russ Owen
|
|
|
Matt ###-####ok to sheetrock ,still needs a draft stop at inside attic and need 1 hour shafts inspected. 7/25/2001 10:56:42 AM
|
BLD-Framing/Rough-in | 7/23/2001 | 7/24/2001 | 7/24/2001 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/23/2001 at 17:28:53. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/23/2001 at 09:55:29. Contact: ###-####.c/n posted ok to insulate. 7/23/2001 3:41:13 PM
|
BLD-Wall cover | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/23/2001 at 09:57:06. Contact: ###-####.c/n posted ,ok to insulate. 7/23/2001 3:40:50 PM
|
BLD-Framing/Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 10:54:49. Contact: ###-####. 7/13/2001 8:48:05 AM. need to construct some of the roof area mansard as per the structural details as shown on plans,i have gone over these areas with contractor,will recall before covering. 7/13/2001 8:52:45 AM
|
BLD-Framing/Rough-in | 7/9/2001 | 7/10/2001 | 7/10/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/09/2001 at 14:21:27. Contact: ###-####.c/n posted. 7/10/2001 11:58:18 AM
|
BLD-Footing | 6/21/2001 | 6/22/2001 | 6/22/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 13:22:13. Contact: ###-####.
|
BLD-Foundation | 6/21/2001 | 6/22/2001 | 6/22/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 13:22:50. Contact: ###-####.
|
BLD-Footing | 6/21/2001 | 6/21/2001 | 6/21/2001 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 08:06:13. Contact: ###-####.
|
BLD-Foundation | 6/21/2001 | 6/21/2001 | 6/21/2001 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 08:05:19. Contact: ###-####.
|
BLD-Footing | 6/19/2001 | 6/20/2001 | 6/20/2001 | P | FAIL |
Russ Owen
|
|
|
###-#### verbal c/n with contractor from wright brothers, front wall req 2 bars top and bottom also 6 in wider footing at the front entry also inst shear footings require a 6 in raise above the slab,also clearance to earth at several locations, not this is a mono pour for footing and slab. 1/20/2002 5:18:37 PM
|