BLD-Final | 7/17/2002 | 7/17/2002 | 7/17/2002 | P | PASS |
Carl Dependahl
|
|
|
dave; Phone #: ###-####; rails ok per 7/17/2002 3:46:59 PM 408 7/17/2002 3:50:39 PM
|
Permanent Occupancy | | 7/17/2002 | 7/17/2002 | | DONE |
|
|
|
|
BLD-Final | 5/14/2002 | 5/14/2002 | 5/14/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/14/2002 at 09:09:38. Contact: ###-####. ok for temp 5/14/2002 5:01:41 PM
|
BLD-Final | 5/11/2002 | 5/13/2002 | 5/13/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/11/2002 at 12:49:59. Contact: ###-####. need complete rail & temp. glass install... 5/13/2002 2:06:58 PM
|
BLD-Final | 5/9/2002 | 5/10/2002 | 5/10/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/09/2002 at 16:53:44. Contact: ###-####. need plbg final...chk rails per ubc 1003 5/10/2002 4:05:32 PM
|
FIRE-Final Inspection | 5/9/2002 | 5/10/2002 | 5/10/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/09/2002 at 16:53:09. Contact: ###-####.
|
Code Occupancy Approval | | | 4/11/2002 | | PASS |
|
|
|
SIGNED TEMP ON THIS BUILDING AND WILL HOLD FOR ALL LANDSCAPE OF PROJECT, LARGE BOND HAD BEEN POSTED.
|
BLD-Energy code compliance | 2/25/2002 | 2/25/2002 | 2/25/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/25/2002 2:10:53 PM walls ok to cover
|
BLD-Framing/Rough-in | 2/25/2002 | 2/25/2002 | 2/25/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/25/2002 2:09:43 PM ok to insul; need verify int. gypsum shear panels when installed
|
BLD-Wall cover | 2/22/2002 | 2/25/2002 | 2/25/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/22/2002 at 16:29:19. Contact: ###-####...see frame insp same date. 2/25/2002 2:10:28 PM
|
BLD-Wall cover | 2/20/2002 | 2/21/2002 | 2/21/2002 | P | NH |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/20/2002 at 11:47:51. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/19/2002 | 2/20/2002 | 2/20/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/19/2002 at 12:05:55. Contact: ###-####., w.i.p. on stairs., ok to insul 2/21/2002 9:16:21 AM 2/21/2002 9:16:55 AM 2/21/2002 9:18:02 AM
|
BLD-Framing/Rough-in | 2/18/2002 | 2/19/2002 | 2/19/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/18/2002 at 18:25:32. Contact: ###-####. C/n, complete fireblocks, nail protectors, repair overbored or cut studs at wet walls, seal draft stops per UBC 708; add firestop pads at elec . boxes w/i 24" on tenant separation walls per 709. Stairs to be completed...check at final w/ rails. 2/19/2002 1:29:42 PM
|
BLD-Aging Inspection | 12/18/2001 | 12/18/2001 | 12/18/2001 | | NR |
Carl Dependahl
|
|
|
apts, wip 12/18/2001 4:32:46 PM
|
BLD-Framing/Rough-in | 10/16/2001 | 10/16/2001 | 10/16/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/16/2001 at 08:19:15. Contact: ###-####... 10/16/2001 2:52:49 PM has c/n in effect w/ bld01-00531...shear walls. resolve prior to full frame approval. 10/16/2001 2:54:26 PM
|
BLD-Framing/Rough-in | 10/10/2001 | 10/11/2001 | 10/10/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/10/2001 at 11:13:44. Contact: ###-####. ext nailing ok 10/10/2001 4:39:32 PM
|
BLD-Conference | 10/10/2001 | 10/10/2001 | 10/10/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/10/2001 4:36:27 PM w/ new supt. Dave re c/n in effect for 1st fl shear walls
|
BLD-Foundation | 8/23/2001 | 8/24/2001 | 8/24/2001 | A | PART |
Carl Dependahl
|
|
|
###-####= JIM FD SLAB
|
BLD-Framing/Rough-in | 8/3/2001 | 8/3/2001 | 8/3/2001 | P | PART |
Carl Dependahl
|
|
|
re bar-- jim ###-####
|
BLD-Foundation | 7/18/2001 | 7/19/2001 | 7/19/2001 | P | PASS |
Jim Storey
|
|
|
re-bar ###-####
|