Permit Information
Permit NumberBLD01-00617
StatusFinaled
Name FAIRVIEW OFFICE PARK
Site Address 10020 W FAIRVIEW AVE
Project NameFAIRVIEW OFFICE PARK
Customer Number 
ePlanReviewNo
Description
To construct a new, two story, wood framed, 10,670 sq. ft. shell and core office building with elevator and restrooms on each floor. The first floor is 5,370 sq.ft and the second floor is 5,300 sq.ft. Each floor has four unfinished areas at 1,025 sq.ft each for rent. All construction per the approved plans, attached comment list and CABO/ANSI A117.1. NOTE: This building is a shell and core only. To occupy the future office spaces permits and Certicicate of Occupancies are required to finish and occupying these spaces. MJP DRH00-00248 PC#199-01 MODIFICATION * 8/28/01 Change construction materials in the walls from wood studs to metal stud framing. All changes are per approved plans and structural engineer's calculations. MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/14/20025/14/20025/14/2002PPASS
DetailsDave Hannah
###-#### VAL
BLD-Final5/13/20025/13/20025/13/2002PCANC
DetailsRuss Owen
###-####
Code Occupancy Approval5/13/20025/13/20025/13/2002PDONE
DetailsWm. Michael Meloy
Signed off 5/14/2002 11:46:32 AM
Code Occupancy Approval  5/13/2002 PASS
FIRE-Final Inspection5/10/20025/10/20025/10/2002PPASS
DetailsTroy Cobbley
fire life/safety finaled 5/13/2002 8:01:47 AM
BLD-Final5/7/20025/8/20025/8/2002ANR
DetailsDave Hannah
###-####
BLD-Final5/7/20025/8/20025/8/2002ACANC
DetailsDave Hannah
###-#### Gave back to Dave. 5/8/2002 11:15:44 AM
FIRE-Final Inspection5/1/20025/2/20025/2/2002PFAIL
DetailsTroy Cobbley
elevator recall did not work, change door hardware to ADA approved type, remove thumbturn and put up sticker on main exit, provide fire extinguisher, relocate 2nd floor smoke detector to deck, verify need for "knox box". Approved plan notes are missing. Notified Val that there may be other items on the notes that will need addressing 5/2/2002 3:30:18 PM
FIRE-Final Inspection5/1/20025/2/20025/2/2002ACANC
DetailsTroy Cobbley
duplicate inspection 5/2/2002 2:04:38 PM
BLD-Framing/Rough-in4/1/20024/1/20024/1/2002PPART
DetailsDave Hannah
###-#### VALc/n on site 4/1/2002 3:02:48 PM
BLD-Conference2/1/20022/1/20022/1/2002PDONE
DetailsDave Hannah
###-####
BLD-Conference1/23/20021/23/20021/23/2002PDONE
DetailsDave Hannah
Added by Inspector: 425 On 1/23/2002 3:47:16 PM Bob A Val and myself disscussed 1hr wall on east side of building
BLD-Energy code compliance1/17/20021/18/20021/18/2002APASS
DetailsDave Hannah
###-####
BLD-Framing/Rough-in1/15/20021/16/20021/16/2002APART
DetailsDave Hannah
fr insp chris ###-#### trusses are ok draft stop ok freaming ok needs hangers for sec floor south end have to check 1hr ext wall 1/16/2002 12:57:10 PM
BLD-Framing/Rough-in1/11/20021/11/20021/11/2002PFAIL
DetailsDave Hannah
###-#### didnt do a c/n to much all the truss supports not in all the 2ply truss not nailed no supprots under ends of beams and grider trusses hangers missing or not nailed beam straping need eng on inter shear wall draft stoppes in attic 1/11/2002 3:37:16 PM
BLD-Framing/Rough-in1/9/20021/10/20021/10/2002ANR
DetailsTom Arcoraci
###-####
BLD-Aging Inspection12/24/200112/24/200112/24/2001 DONE
DetailsDave Hannah
W.I.P 12/24/2001 10:14:36 AM
BLD-Framing/Rough-in10/23/200110/24/200110/24/2001APASS
DetailsDave Hannah
shear insp --val ###-#### OK TO COVER EXT WALLS 10/24/2001 10:35:20 AM
BLD-Framing/Rough-in10/16/200110/17/200110/17/2001AFAIL
DetailsDave Hannah
###-#### after 9am shear nailing on southwall need rfi from engineer 10/17/2001 12:26:42 PM
BLD-Conference8/29/20018/29/20018/29/2001PDONE
DetailsDave Hannah
val-- ###-#### for conf we are going back to org city approved plans for wood framing 8/29/2001 3:25:51 PM
BLD-Footing8/29/20018/29/20018/29/2001PPASS
DetailsDave Hannah
###-####
BLD-Footing8/22/20018/22/20018/22/2001PPASS
DetailsDave Hannah
okay by mike phillups to do footing inspection val ###-#### columns and ext stairs footings 8/22/2001 4:07:12 PM
BLD-Footing8/7/20018/7/20018/7/2001PPASS
DetailsDave Hannah
for elevator ###-####
BLD-Footing7/31/20018/1/20018/1/2001ANR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 07/31/2001 at 16:27:10. Contact: ###-####. 11am boards only 1/2 up. i reschedualed this myself. 8/1/2001 11:13:48 AM
BLD-Footing8/1/20018/1/20018/1/2001PPASS
DetailsRuss Owen
Scheduled by Inspector: 407 On 8/1/2001 11:53:22 AM walls. 8/1/2001 4:13:08 PM
BLD-Footing7/26/20017/27/20017/27/2001APASS
DetailsDave Hannah
###-####
BLD-Footing7/25/20017/26/20017/26/2001ACANC
DetailsDave Hannah
###-#### cancelled by val