BLD-Final | 3/28/2002 | 3/29/2002 | 3/29/2002 | A | PASS |
Russ Owen
|
|
|
fn mike ###-#### -re-insp . ok perm oc. 3/29/2002 2:19:00 PM
|
Permanent Occupancy | | 3/29/2002 | 3/29/2002 | | DONE |
|
|
|
|
BLD-Final | 3/19/2002 | 3/20/2002 | 3/20/2002 | P | PART |
Russ Owen
|
|
|
mike- ###-#### fn occ . Need pillow pad installation requirements. 3/20/2002 4:37:37 PM 3/20/2002 4:38:06 PM
|
BLD-Final | 2/14/2002 | 2/15/2002 | 2/15/2002 | A | PART |
Russ Owen
|
|
|
MIKE ###-#### Ok for a temp oc c/n posted. 2/15/2002 1:17:17 PM
|
FIRE-Final Inspection | 2/13/2002 | 2/14/2002 | 2/14/2002 | A | PASS |
Troy Cobbley
|
|
|
Fire life/safety finaled. Structural inspector to review door hardware 2/15/2002 8:30:14 AM
|
FIRE-Final Inspection | 2/7/2002 | 2/7/2002 | 2/7/2002 | P | NR |
Troy Cobbley
|
|
|
contractor was not ready for inspection 2/7/2002 5:21:21 PM
|
BLD-Framing/Rough-in | 2/5/2002 | 2/6/2002 | 2/6/2002 | A | PART |
Russ Owen
|
|
|
above ceiling insp mike ###-#### Needs a few pods 2 holes at corridor wall contractor notifed no c/n. 2/6/2002 3:14:31 PM
|
BLD-Conference | 1/16/2002 | 1/16/2002 | 1/16/2002 | P | NR |
Troy Cobbley
|
|
|
spoke with contractor about rough-in spection for sprinklers, verified locations of duct detectors and in-duct detectors with dampers 1/16/2002 3:42:32 PM
|
BLD-Framing/Rough-in | 1/15/2002 | 1/15/2002 | 1/15/2002 | P | PART |
Russ Owen
|
|
|
ceiling\\###-#### mike. west area ok east still in process. Also recieved ok from Architect fr cell walls not to deck and ok for column fire proffing in place of sheetrocked protection,still waiting for 2 hour occupancy wll change at the rear area of restrooms, also still need to caulk mis penetrations through out at exit corid and 2 hr oc wall around holding cell.s 1/17/2002 1:16:38 PM
|
BLD-Framing/Rough-in | 12/4/2001 | 12/5/2001 | 12/5/2001 | A | PART |
Russ Owen
|
|
|
MIKE ###-####. Still need ok for interior columns fire-proffing inst of sheetrock assembly, also need ok for walls of holding cells not constructed to roof deck, and 2 hr wall (east) around the holding cell does not jog in rear of restrooms wall is continous with corridor and will have (2) 90 min access doors to the service plumbing at rear walls of the restrooms. These items require documentation from architect for changes to the approved plans. contractor notified. This day. Note: walls can now be sheetrocked. Ceilings not in at this time also all penetration fire stops and dampers will need insp prior to ceiling cover. 12/5/2001 12:36:49 PM 12/5/2001 12:41:50 PM
|
BLD-Framing/Rough-in | 11/2/2001 | 11/5/2001 | 11/5/2001 | A | PART |
Russ Owen
|
|
|
###-#### MIKE OR COLLIN. Only the right rear south area evidence and office ok to cover rest not ready, found a duct w-out fire damper at west side of 1 hr corridor,contractor notified also all interior columns have been fire profed with spray applied plan shows drywall listing need ok from architect. 11/6/2001 10:56:02 AM
|
BLD-Aging Inspection | 10/25/2001 | 10/25/2001 | 10/25/2001 | | PART |
Russ Owen
|
|
|
no insp called for. 10/25/2001 5:01:28 PM
|
BLD-Aging Inspection | 8/16/2001 | 8/16/2001 | 8/16/2001 | | FAIL |
Russ Owen
|
|
|
c/n posted. 8/23/2001 3:40:19 PM
|