BLD-Aging Inspection | 12/8/2003 | 12/8/2003 | 12/8/2003 | | DONE |
Russ Owen
|
|
|
|
BLD-Final | 8/16/2002 | 8/16/2002 | 8/16/2002 | | DONE |
|
|
|
Final ok - approved for perm. occ. per Russ Owen.
|
BLD-Final | 8/15/2002 | 8/15/2002 | 8/15/2002 | P | PART |
Russ Owen
|
|
|
|
Permanent Occupancy | | 8/15/2002 | 8/15/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled
|
BLD-Final | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PART |
Russ Owen
|
|
|
Needs fire/life safety for a temporary oc, has pending corrections for a permanent oc. 6/18/2002 5:07:17 PM 6/18/2002 5:07:36 PM
|
FIRE-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PART |
Troy Cobbley
|
|
|
Fire alarm and fire life/safety finaled. Fire sprinkler given temp per Dave Miller for the window sprinklers
|
BLD-Final | 6/17/2002 | 6/17/2002 | 6/17/2002 | P | CANC |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/17/2002 10:26:41 AM
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/14/2002 10:29:12 AM c/n posted. 6/14/2002 4:42:29 PM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/7/2002 | 6/7/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/6/2002 3:57:27 PM
|
BLD-Framing/Rough-in | 6/5/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/5/2002 1:11:25 PM complete front lobby and main restrooms. ceiling. 6/6/2002 3:57:15 PM
|
BLD-Framing/Rough-in | 6/4/2002 | 6/5/2002 | 6/5/2002 | A | PART |
Russ Owen
|
|
|
CLAY ###-####
|
BLD-Conference | 5/22/2002 | 5/23/2002 | 5/23/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 5/22/2002 5:25:55 PM ok to cover rear raised roof. 5/23/2002 11:15:13 AM
|
BLD-Framing/Rough-in | 5/21/2002 | 5/21/2002 | 5/21/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 5/21/2002 11:49:34 AM kitchen hood 5/21/2002 12:34:12 PM
|
BLD-Framing/Rough-in | 5/21/2002 | 5/21/2002 | 5/21/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 5/21/2002 3:40:05 PM need truss details for rear roof ext. 5/21/2002 4:31:05 PM
|
BLD-Framing/Rough-in | 5/20/2002 | 5/20/2002 | 5/20/2002 | P | PART |
Russ Owen
|
|
|
###-#### will recall. 5/20/2002 4:59:27 PM
|
BLD-Framing/Rough-in | 5/1/2002 | 5/1/2002 | 5/1/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 5/1/2002 1:14:39 PM lower corridor ok fire caulk penetrations ok in room sections of corridor. only, rest not yet complete..5/1/2002 2:36:41 PM 5/1/2002 2:36:59 PM
|
BLD-Framing/Rough-in | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/18/2002 12:11:40 PM beam in kitchen with holes needs approval also need the top of wall connections completed at the 2 1st floor shear walls. 3/19/2002 10:00:09 AM
|
BLD-Framing/Rough-in | 2/28/2002 | 2/28/2002 | 2/28/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/28/2002 4:00:14 PM
|
BLD-Framing/Rough-in | 2/22/2002 | 2/22/2002 | 2/22/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/22/2002 4:43:03 PM see notesm under 01-00736. 2/22/2002 4:50:47 PM
|
BLD-Framing/Rough-in | 2/20/2002 | 2/20/2002 | 2/20/2002 | P | PART |
Russ Owen
|
|
|
fr rich- ###-#### 2nd floor ok to insulate. 2/20/2002 3:21:10 PM
|
BLD-Framing/Rough-in | 2/18/2002 | 2/19/2002 | 2/19/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/18/2002 at 17:24:40. Contact: .3rd floor need fire stoping at 3 rest room walls/ will recall. 2/19/2002 2:42:59 PM
|
BLD-Framing/Rough-in | 2/14/2002 | 2/15/2002 | 2/15/2002 | A | FAIL |
Russ Owen
|
|
|
###-#### RICH . Need to complete fire stop at penetrations west of the first 2 hr wall. 2/15/2002 11:27:45 AM
|
BLD-Framing/Rough-in | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | PART |
Russ Owen
|
|
|
###-#### RICH Shear ok at rest of west side of 3rd floor. ok to insulate the ceiling of the 2nd floor. still need fire caulking and shear nailing done at west side of 1st 2hr wall to the west exterior wall. 2/13/2002 3:48:24 PM
|
BLD-Framing/Rough-in | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | PART |
Russ Owen
|
|
|
R/I RICH ###-#### See bld 01-00736 for notes. 2/12/2002 4:21:30 PM
|
BLD-Framing/Rough-in | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/8/2002 11:20:58 AM see notes under 01-00736. 2/8/2002 4:14:33 PM
|
BLD-Framing/Rough-in | 2/7/2002 | 2/7/2002 | 2/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/7/2002 8:07:26 AM see bld 00736 for comments this day.2/7/2002 4:56:29 PM 2/7/2002 4:56:52 PM
|
BLD-Framing/Rough-in | 2/4/2002 | 2/5/2002 | 2/5/2002 | A | PART |
Russ Owen
|
|
|
###-#### went over roof trusses all ok except 1 truss at east end. The 4th floor still needs the area separation wall ele boxes paded and penetrations done note this wall has been insulated and drywalled. also there are pvc plumbing penetration which will be relocated and will need verification of protection. The 3rd floor can be insulated but has the same problem with the area separation walls and pvc flue pipes,also shear walls are not complete and rest room ceilings will need to be inspected prior to the drop celings being put in. See also bld 01-00737,01-00736. 2/5/2002 4:27:20 PM 2/5/2002 4:29:36 PM
|
BLD-Conference | 2/4/2002 | 2/4/2002 | 2/4/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/4/2002 12:11:40 PM see notes under 01--00736. 2/4/2002 1:01:29 PM
|
BLD-Framing/Rough-in | 1/21/2002 | 1/22/2002 | 1/22/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 14:46:56. Contact: ###-####.
|
BLD-Aging Inspection | 12/10/2001 | 12/10/2001 | 12/10/2001 | | PART |
Russ Owen
|
|
|
wip. 12/12/2001 4:18:42 PM
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | PART |
Russ Owen
|
|
|
work in process. 10/9/2001 11:58:57 AM
|
BLD-Foundation | 8/6/2001 | 8/7/2001 | 8/7/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 11:40:32. Contact: ###-####. spec on site 8/6/2001 10:37:59 PM
|
BLD-Footing | 7/19/2001 | 7/19/2001 | 7/19/2001 | P | PART |
Russ Owen
|
|
|
###-####.subject to s-i. 7/20/2001 3:33:20 PM
|
BLD-Footing | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Russ Owen
|
|
|
###-####
|
BLD-Foundation | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Russ Owen
|
|
|
|
BLD-Foundation | 7/10/2001 | 7/10/2001 | 7/10/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/10/2001 at 10:38:48. Contact: .ok pending s-i report. 7/10/2001 4:36:46 PM
|
BLD-Foundation | 7/5/2001 | 7/6/2001 | 7/6/2001 | A | PART |
Russ Owen
|
|
|
###-####
|
BLD-Footing | 6/27/2001 | 6/28/2001 | 6/28/2001 | A | PART |
Russ Owen
|
|
|
Clay ###-#### ok subject to special insp. 6/28/2001 9:10:18 AM
|
BLD-Conference | 6/26/2001 | 6/27/2001 | 6/27/2001 | A | PART |
Russ Owen
|
|
|
Clay ###-#### meet with contractor,architect and subs for pre-job conference. 6/27/2001 10:46:30 AM
|