Permit Information
Permit NumberBLD01-00729
StatusFinaled
Name HILTON GARDEN INN
Site Address 7699 W SPECTRUM ST
Project NameHILTON GARDEN INN-BLDG A
Customer Number 
ePlanReviewNo
Description
( Section 1 of 3 West Section) * Two, two hour area separation walls will divide this four story, 137 unit hotel into three separate buildings. This section contains 39 units and has the assembly rooms. All construction is per the approved plans, attached comment list and CABO/ANSI A117.1. Refer to 01-00736 an 01-00737 for other portions of this building. NOTE: This building is fully fire sprinklered for story increase. CUP01-00009 PC#250-01 PLAN MODIFICATION 4/22/02 * To add a raised skylight and roof area at the prefunction breakout area hallway south of the assembly rooms. MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection12/8/200312/8/200312/8/2003 DONE
DetailsRuss Owen
BLD-Final8/16/20028/16/20028/16/2002 DONE
Final ok - approved for perm. occ. per Russ Owen.
BLD-Final8/15/20028/15/20028/15/2002PPART
DetailsRuss Owen
Permanent Occupancy 8/15/20028/15/2002 DONE
Details
FIRE-Final Inspection8/12/20028/12/20028/12/2002APASS
DetailsTroy Cobbley
fire life/safety finaled
FIRE-Final Inspection8/12/20028/12/20028/12/2002APASS
DetailsTroy Cobbley
fire life/safety finaled
BLD-Final6/18/20026/18/20026/18/2002PPART
DetailsRuss Owen
Needs fire/life safety for a temporary oc, has pending corrections for a permanent oc. 6/18/2002 5:07:17 PM 6/18/2002 5:07:36 PM
FIRE-Final Inspection6/18/20026/18/20026/18/2002PPART
DetailsTroy Cobbley
Fire alarm and fire life/safety finaled. Fire sprinkler given temp per Dave Miller for the window sprinklers
BLD-Final6/17/20026/17/20026/17/2002PCANC
DetailsRuss Owen
Scheduled by Inspector: 407 On 6/17/2002 10:26:41 AM
BLD-Final6/14/20026/14/20026/14/2002AFAIL
DetailsRuss Owen
Scheduled by Inspector: 407 On 6/14/2002 10:29:12 AM c/n posted. 6/14/2002 4:42:29 PM
BLD-Framing/Rough-in6/6/20026/7/20026/7/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 6/6/2002 3:57:27 PM
BLD-Framing/Rough-in6/5/20026/6/20026/6/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 6/5/2002 1:11:25 PM complete front lobby and main restrooms. ceiling. 6/6/2002 3:57:15 PM
BLD-Framing/Rough-in6/4/20026/5/20026/5/2002APART
DetailsRuss Owen
CLAY ###-####
BLD-Conference5/22/20025/23/20025/23/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 5/22/2002 5:25:55 PM ok to cover rear raised roof. 5/23/2002 11:15:13 AM
BLD-Framing/Rough-in5/21/20025/21/20025/21/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 5/21/2002 11:49:34 AM kitchen hood 5/21/2002 12:34:12 PM
BLD-Framing/Rough-in5/21/20025/21/20025/21/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 5/21/2002 3:40:05 PM need truss details for rear roof ext. 5/21/2002 4:31:05 PM
BLD-Framing/Rough-in5/20/20025/20/20025/20/2002PPART
DetailsRuss Owen
###-#### will recall. 5/20/2002 4:59:27 PM
BLD-Framing/Rough-in5/1/20025/1/20025/1/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 5/1/2002 1:14:39 PM lower corridor ok fire caulk penetrations ok in room sections of corridor. only, rest not yet complete..5/1/2002 2:36:41 PM 5/1/2002 2:36:59 PM
BLD-Framing/Rough-in3/18/20023/18/20023/18/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/18/2002 12:11:40 PM beam in kitchen with holes needs approval also need the top of wall connections completed at the 2 1st floor shear walls. 3/19/2002 10:00:09 AM
BLD-Framing/Rough-in2/28/20022/28/20022/28/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/28/2002 4:00:14 PM
BLD-Framing/Rough-in2/22/20022/22/20022/22/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/22/2002 4:43:03 PM see notesm under 01-00736. 2/22/2002 4:50:47 PM
BLD-Framing/Rough-in2/20/20022/20/20022/20/2002PPART
DetailsRuss Owen
fr rich- ###-#### 2nd floor ok to insulate. 2/20/2002 3:21:10 PM
BLD-Framing/Rough-in2/18/20022/19/20022/19/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/18/2002 at 17:24:40. Contact: .3rd floor need fire stoping at 3 rest room walls/ will recall. 2/19/2002 2:42:59 PM
BLD-Framing/Rough-in2/14/20022/15/20022/15/2002AFAIL
DetailsRuss Owen
###-#### RICH . Need to complete fire stop at penetrations west of the first 2 hr wall. 2/15/2002 11:27:45 AM
BLD-Framing/Rough-in2/13/20022/13/20022/13/2002PPART
DetailsRuss Owen
###-#### RICH Shear ok at rest of west side of 3rd floor. ok to insulate the ceiling of the 2nd floor. still need fire caulking and shear nailing done at west side of 1st 2hr wall to the west exterior wall. 2/13/2002 3:48:24 PM
BLD-Framing/Rough-in2/12/20022/12/20022/12/2002PPART
DetailsRuss Owen
R/I RICH ###-#### See bld 01-00736 for notes. 2/12/2002 4:21:30 PM
BLD-Framing/Rough-in2/8/20022/8/20022/8/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/8/2002 11:20:58 AM see notes under 01-00736. 2/8/2002 4:14:33 PM
BLD-Framing/Rough-in2/7/20022/7/20022/7/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/7/2002 8:07:26 AM see bld 00736 for comments this day.2/7/2002 4:56:29 PM 2/7/2002 4:56:52 PM
BLD-Framing/Rough-in2/4/20022/5/20022/5/2002APART
DetailsRuss Owen
###-#### went over roof trusses all ok except 1 truss at east end. The 4th floor still needs the area separation wall ele boxes paded and penetrations done note this wall has been insulated and drywalled. also there are pvc plumbing penetration which will be relocated and will need verification of protection. The 3rd floor can be insulated but has the same problem with the area separation walls and pvc flue pipes,also shear walls are not complete and rest room ceilings will need to be inspected prior to the drop celings being put in. See also bld 01-00737,01-00736. 2/5/2002 4:27:20 PM 2/5/2002 4:29:36 PM
BLD-Conference2/4/20022/4/20022/4/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/4/2002 12:11:40 PM see notes under 01--00736. 2/4/2002 1:01:29 PM
BLD-Framing/Rough-in1/21/20021/22/20021/22/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/21/2002 at 14:46:56. Contact: ###-####.
BLD-Aging Inspection12/10/200112/10/200112/10/2001 PART
DetailsRuss Owen
wip. 12/12/2001 4:18:42 PM
BLD-Aging Inspection10/8/200110/8/200110/8/2001 PART
DetailsRuss Owen
work in process. 10/9/2001 11:58:57 AM
BLD-Foundation8/6/20018/7/20018/7/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 08/06/2001 at 11:40:32. Contact: ###-####. spec on site 8/6/2001 10:37:59 PM
BLD-Footing7/19/20017/19/20017/19/2001PPART
DetailsRuss Owen
###-####.subject to s-i. 7/20/2001 3:33:20 PM
BLD-Footing7/12/20017/12/20017/12/2001PPART
DetailsRuss Owen
###-####
BLD-Foundation7/12/20017/12/20017/12/2001PPART
DetailsRuss Owen
BLD-Foundation7/10/20017/10/20017/10/2001PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 07/10/2001 at 10:38:48. Contact: .ok pending s-i report. 7/10/2001 4:36:46 PM
BLD-Foundation7/5/20017/6/20017/6/2001APART
DetailsRuss Owen
###-####
BLD-Footing6/27/20016/28/20016/28/2001APART
DetailsRuss Owen
Clay ###-#### ok subject to special insp. 6/28/2001 9:10:18 AM
BLD-Conference6/26/20016/27/20016/27/2001APART
DetailsRuss Owen
Clay ###-#### meet with contractor,architect and subs for pre-job conference. 6/27/2001 10:46:30 AM