BLD-Final | 8/16/2002 | 8/16/2002 | 8/16/2002 | | DONE |
|
|
|
Final - approved for perm. occ. per Russ Owen
|
BLD-Final | 8/15/2002 | 8/15/2002 | 8/15/2002 | P | PART |
Russ Owen
|
|
|
|
Permanent Occupancy | | 8/15/2002 | 8/15/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
BLD-Final | 6/25/2002 | 6/25/2002 | 6/25/2002 | P | PART |
Russ Owen
|
|
|
Grid ceiling in conference room. 6/25/2002 3:23:19 PM
|
BLD-Final | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PART |
Russ Owen
|
|
|
ok for a temporary oc pending fire/life safety, has pending corrections for a permanent oc. 6/18/2002 5:08:25 PM
|
FIRE-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PART |
Troy Cobbley
|
|
|
Fire alarm and fire life/safety finaled. Fire sprinkler given temp for the window sprinklers per Dave Miller.
|
BLD-Final | 6/14/2002 | 6/17/2002 | 6/17/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/14/2002 10:29:54 AM c/n posted. 6/14/2002 4:42:18 PM
|
BLD-Framing/Rough-in | 3/29/2002 | 3/29/2002 | 3/29/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/29/2002 12:03:22 PM
|
BLD-Framing/Rough-in | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/18/2002 12:12:01 PM
|
BLD-Framing/Rough-in | 3/6/2002 | 3/7/2002 | 3/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/6/2002 4:21:01 PM Ok to insulate mechanical room. Note(2) 1hr walls will be fured out as to accomodate electrical panels. 3/7/2002 12:07:07 PM
|
BLD-Framing/Rough-in | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/6/2002 4:17:58 PM ok to drywall 2nd floor. 3/6/2002 4:20:13 PM
|
BLD-Framing/Rough-in | 3/1/2002 | 3/1/2002 | 3/1/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/1/2002 10:38:51 AM
|
BLD-Framing/Rough-in | 2/28/2002 | 2/28/2002 | 2/28/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/28/2002 4:00:33 PM
|
BLD-Framing/Rough-in | 2/22/2002 | 2/22/2002 | 2/22/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/22/2002 4:42:15 PM see notes under 01-00736. 2/22/2002 4:50:29 PM
|
BLD-Framing/Rough-in | 2/20/2002 | 2/20/2002 | 2/20/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/20/2002 3:22:41 PM Ok to complete insulation at second floor. 2/20/2002 3:26:01 PM
|
BLD-Framing/Rough-in | 2/19/2002 | 2/19/2002 | 2/19/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/19/2002 2:42:18 PM
|
BLD-Framing/Rough-in | 2/15/2002 | 2/15/2002 | 2/15/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/15/2002 11:26:50 AM Need to complete all fire stoping west of the first 2hr wall. 2/15/2002 11:32:12 AM
|
BLD-Framing/Rough-in | 2/14/2002 | 2/14/2002 | 2/14/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/14/2002 4:54:36 PM
|
BLD-Framing/Rough-in | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/13/2002 3:48:54 PM
|
BLD-Framing/Rough-in | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | NR |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/12/2002 12:13:18 PM See bld01-00737 for notes. 2/12/2002 4:21:45 PM
|
BLD-Framing/Rough-in | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/8/2002 11:19:48 AM see notes under 01-00736. 2/8/2002 4:14:19 PM
|
BLD-Framing/Rough-in | 2/7/2002 | 2/7/2002 | 2/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/7/2002 8:09:11 AM See note on bld01-00737 for comments this day. 2/7/2002 4:57:20 PM
|
BLD-Framing/Rough-in | 2/5/2002 | 2/5/2002 | 2/5/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/5/2002 4:27:55 PM see bld01-00729 2/5/2002 4:31:53 PM
|
BLD-Conference | 2/4/2002 | 2/4/2002 | 2/4/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/4/2002 12:11:13 PM seee notes under 01-00736. 2/4/2002 1:01:13 PM
|
BLD-Conference | 2/1/2002 | 2/1/2002 | 2/1/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 408 On 2/1/2002 11:38:09 AM. This day I posted another c/n for the same items as yester day. IE: shear nailing not done ,2 hr wall corrections not, done,st 22 strap, misc, fire caulking. Note at this time work has rapidly been progressing. 2/1/2002 6:00:15 PM
|
BLD-Framing/Rough-in | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PART |
Russ Owen
|
|
|
rich- ###-#### fr insp Posted a c/nat the site. 1/31/2002 2:07:59 PM
|
BLD-Framing/Rough-in | 1/28/2002 | 1/29/2002 | 1/29/2002 | P | PART |
Russ Owen
|
|
|
###-#### fourth floor walls ok to insulate except for 2 hr area sep walls and electrical room. 1/30/2002 9:15:07 AM
|
BLD-Framing/Rough-in | 1/25/2002 | 1/28/2002 | 1/28/2002 | A | PART |
Russ Owen
|
|
|
###-#### n 1/28/2002 11:06:36 AM Went over roof trusses at 4 th floor there are correction to be made .a. w 1/28/2002 1:23:23 PM
|
BLD-Framing/Rough-in | 1/25/2002 | 1/25/2002 | 1/25/2002 | P | PART |
Russ Owen
|
|
|
###-#### ok to insulate upper floor dividing walls except for 2 hr area sep walls. amlmmmm 1/25/2002 4:52:08 PM
|
BLD-Framing/Rough-in | 1/18/2002 | 1/22/2002 | 1/22/2002 | A | PART |
Russ Owen
|
|
|
###-####. need to clairify mbr connection to steel beam and interior shear wall nailing. 1/22/2002 4:25:49 PM
|
BLD-Framing/Rough-in | 1/11/2002 | 1/11/2002 | 1/11/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/11/2002 12:02:26 PM Ok to insulate east side interior walls between rooms only first and second floors only,as to have shear walls applied after insulation. 1/11/2002 12:07:31 PM
|
BLD-Conference | 1/9/2002 | 1/10/2002 | 1/10/2002 | A | PART |
Russ Owen
|
|
|
###-####.Went over fire stoping with cont and hilti rep. 1/10/2002 11:20:20 AM
|
BLD-Framing/Rough-in | 1/7/2002 | 1/8/2002 | 1/8/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/7/2002 6:05:41 PM . need new details for penetrations . 1/8/2002 12:00:33 PM
|
BLD-Framing/Rough-in | 1/7/2002 | 1/7/2002 | 1/7/2002 | P | PART |
Russ Owen
|
|
|
###-#### 3 floor shear behind tubs east of 2 hr area sep wall. 1/7/2002 6:02:53 PM
|
BLD-Framing/Rough-in | 1/3/2002 | 1/3/2002 | 1/3/2002 | P | PART |
Russ Owen
|
|
|
###-#### . Informed contractor that all floor ceiling assemblies are required to be fire stoped at the top plates and florr line ,plumbing ele and conduit etc to maintain 1 hr fire resistive construction. bettween floors. no c/n posted. They will contact rep for product used and recall when ready. 1/3/2002 5:18:00 PM 1/4/2002 4:47:54 PM
|
BLD-Framing/Rough-in | 12/19/2001 | 12/20/2001 | 12/20/2001 | A | PART |
Russ Owen
|
|
|
###-#### RICH. 12/20/2001 4:55:01 PM. 12/20/2001 4:55:38 PMc/n posted. 12/20/2001 4:57:01 PM
|
BLD-Framing/Rough-in | 12/18/2001 | 12/18/2001 | 12/18/2001 | P | PART |
Russ Owen
|
|
|
rich ###-####
|
BLD-Framing/Rough-in | 12/14/2001 | 12/14/2001 | 12/14/2001 | P | PART |
Russ Owen
|
|
|
RICH ###-####. lower floor top half of east corridor. 12/14/2001 3:47:30 PM
|
BLD-Conference | 12/6/2001 | 12/6/2001 | 12/6/2001 | P | PART |
Russ Owen
|
|
|
###-####. went over penetration with electrician, also hds have now been placed in walls at east stair tower. 12/7/2001 11:11:43 AM
|
BLD-Framing/Rough-in | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 15:42:23. Contact: . shear ok north and south 1-3 floors east side and 1-3 floors north west side 11/21/2001 10:25:39 AM 11/21/2001 10:26:25 AM
|
BLD-Framing/Rough-in | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | CANC |
Tom Arcoraci
|
|
|
###-#### CLAY SHEER NAIL will recall for am 11/20/2001 3:24:54 PM
|
BLD-Framing/Rough-in | 10/24/2001 | 10/24/2001 | 10/24/2001 | P | FAIL |
Russ Owen
|
|
|
###-#### RICH INTERIOR & EXTERIOR SHEER NAIL . Need more info on MBR hold down req for studs. c/n. 10/24/2001 3:51:31 PM
|
BLD-Framing/Rough-in | 10/19/2001 | 10/19/2001 | 10/19/2001 | P | PART |
Russ Owen
|
|
|
SHEER NAIL ###-#### RICH NEW ADDRESS OF 7699 W SPECTRUM STREET. needs to add 2nd row of nailing at the hold downs system. 10/19/2001 3:55:03 PM
|
BLD-Framing/Rough-in | 8/30/2001 | 8/31/2001 | 8/31/2001 | A | PART |
Russ Owen
|
|
|
###-####. looked at some interior upper section of wall shear panels only. 8/31/2001 12:30:09 PM
|
BLD-Conference | 8/3/2001 | 8/6/2001 | 8/6/2001 | A | PART |
Russ Owen
|
|
|
###-####. 2hr stair enclosure, question reg, beam into walls. pending more info. 8/6/2001 4:46:30 PM
|
BLD-Foundation | 7/9/2001 | 7/9/2001 | 7/9/2001 | P | PART |
Russ Owen
|
|
|
Rich ###-####s-i pending. 7/10/2001 11:59:50 AM
|
BLD-Foundation | 7/5/2001 | 7/5/2001 | 7/5/2001 | P | PART |
Russ Owen
|
|
|
###-####subject to s-i. 7/5/2001 3:25:19 PM
|
BLD-Footing | 6/28/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Russ Owen
|
|
|
pouring at 1:30 clay ###-####
|
BLD-Foundation | 6/28/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Russ Owen
|
|
|
clay pouring at1:30 ###-####
|
BLD-Footing | 6/26/2001 | 6/26/2001 | 6/26/2001 | P | PART |
Russ Owen
|
|
|
pouring at 2:00 Clay ###-####
|
BLD-Footing | 6/25/2001 | 6/25/2001 | 6/25/2001 | P | PART |
Russ Owen
|
|
|
pour at 2:30 ###-#### 100 foot of rear east. 6/25/2001 4:16:20 PM
|