BLD-Final | 8/23/2002 | 8/23/2002 | 8/23/2002 | P | PASS |
Russ Owen
|
|
|
ok for a perm oc. 8/23/2002 2:53:47 PM
|
BLD-Framing/Rough-in | 8/23/2002 | 8/23/2002 | 8/23/2002 | P | PASS |
Russ Owen
|
|
|
special inspection report ok . 8/23/2002 2:51:36 PM
|
Permanent Occupancy | | 8/23/2002 | 8/23/2002 | | DONE |
|
|
|
|
BLD-Final | 8/20/2002 | 8/20/2002 | 8/20/2002 | P | PART |
Russ Owen
|
|
|
Pending all req signatures, and special inspection approval from engineer. 8/20/2002 3:17:08 PM
|
BLD-Final | 8/15/2002 | 8/16/2002 | 8/16/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/15/2002 at 15:22:18. Contact: ###-####. OK for a temp oc needs front door hardware key locks and special insp report approved by the engineer. 8/16/2002 4:06:10 PM c/n posted. 8/16/2002 4:06:15 PM
|
FIRE-Final Inspection | 8/6/2002 | 8/7/2002 | 8/7/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 8/7/2002 8:11:10 AM
|
BLD-Conference | 7/26/2002 | 7/29/2002 | 7/29/2002 | A | PART |
Russ Owen
|
|
|
|
BLD-Conference | 7/25/2002 | 7/26/2002 | 7/26/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/25/2002 at 14:54:10. Contact: ###-####.
|
FIRE-Conference | 7/25/2002 | 7/26/2002 | 7/26/2002 | A | DONE |
Troy Cobbley
|
|
|
spoke with the contractor about life/safety requirements prior to the final inspection 7/26/2002 11:02:09 AM
|
BLD-Framing/Rough-in | 7/3/2002 | 7/5/2002 | 7/5/2002 | A | PART |
Tom Arcoraci
|
|
|
ken - ###-#### ok to cover int and front 7/5/2002 10:11:50 AM
|
BLD-Framing/Rough-in | 6/13/2002 | 6/17/2002 | 6/17/2002 | A | PART |
Russ Owen
|
|
|
MASONRY WALL ###-#### SHAWN . did this on 6/14/ pm . ok pending special inspection. 6/17/2002 2:32:25 PM
|
BLD-Footing | 5/29/2002 | 5/31/2002 | 5/31/2002 | P | PART |
Russ Owen
|
|
|
ft insp- drew ###-####. 50 % complete, MTI will perform special inspection. 5/31/2002 4:14:56 PM
|