Permit Information
Permit NumberBLD01-01014
StatusFinaled
Name IDAHO ATHLETIC CLUB (PHASE II/III)
Site Address 2999 N LAKEHARBOR LN
Project NameIDAHO ATHLETIC CLUB-II & III
Customer Number 
ePlanReviewNo
Description
IDAHO ATHLETIC CLUB ADDITION (PHASES II & III) - TO CONSTRUCT THE FINAL TWO PHASES OF THE NEW IDAHO ATHLETIC CLUB. PHASE II IS A 11,700 SQ. FT., TWO STORY ADDITION AT THE WEST SIDE OF THE EXISTING PHASE I. THE FIRST FLOOR OF PHASE TWO IS A SHELL AND CORE FOR THE FUTURE POOL ROOM. THE SECOND FLOOR WILL BE FINISHED AS AN EXERCISE ROOM. FIRST FLOOR: 5,850 SQ. FT., SECOND FLOOR: 5,850 SQ. FT.. SEPARATE PERMITS WILL BE REQUIRED TO CONSTRUCT THE SWIMMING POOL AND SPA. A SEPARATE TENANT IMPROVEMENT PERMIT IS ALSO REQUIRED TO FINISH THE POOL ROOM OF OCCUPANCY. PHASE THREE IS A 10,370 SQ. FT., TWO STORY ADDITION AT THE EAST SIDE OF THE EXISTING PHASE I BUILDING. THE FIRST FLOOR IS A SHELL ONLY FOR FUTURE OFFICE AND RETAIL SPACE. THE SECOND FLOOR IS A SHELL ONLY FOR A FUTURE EXERCISE ROOM. FIRST FLOOR: 5,270 SQ. FT., SECOND FLOOR: 5,100 SQ. FT.. SEPARATE TENANT IMPROVEMENT PERMITS WILL BE REQUIRED TO FINISH THIS PHASE FOR OCCUPANCY. THERE IS NO OCCUPANCY ALLOWED UNDER THIS PERMIT FOR THE FIRST FLOOR OF PHASE TWO OR FOR PHASE THREE. BOTH PHASES ARE BEING CONSTRUCTED OF MASONRY EXTERIOR WALL, CONCRETE FLOORS AND STRUCTURAL ROOF FRAMING WITH METAL ROOF DECK. ALL PHASES OF THIS BUILDING ARE FULLY FIRE SPRINKLED. THE SPRINKLERS ARE BEING USED FOR ONE-HOUR SUBSTITUTION. DRH00-117/CUP00-00060/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/21/200112/26/200112/26/2001APART
DetailsTony Young
###-####
ok for perm. occupancy after other trade inspectors are ok 12/26/2001 10:55:22 AM
BLD-Final11/30/200111/30/200111/30/2001 PART
DetailsTony Young
Ok for temp. occ.. Pool permit #bld01-03043 has been issued and approved for temp. occ. also. Ok for final when all agencies/fees approved.
BLD-Final11/16/200111/19/200111/19/2001APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 11/16/2001 at 12:27:12. Contact: ###-####.
ok as long as others are ok 11/19/2001 10:26:20 AM
BLD-Final11/15/200111/16/200111/16/2001AFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 11/15/2001 at 15:35:23. Contact: ###-####.
c/n posted 11/16/2001 12:24:35 PM
BLD-Final11/14/200111/15/200111/15/2001PCANC
DetailsTony Young
Scheduled by a contractor via Hello! on 11/14/2001 at 08:42:48. Contact: ###-####.
FIRE-Final Inspection11/14/200111/15/200111/15/2001APASS
DetailsTroy Cobbley
OK for perm occ 11/16/2001 10:13:42 AM
Code Occupancy Approval11/13/200111/14/200111/14/2001AFAIL
DetailsTony Young
Scheduled by Inspector: MSG On 11/13/2001 3:01:16 PM 10:00 a.m. inspection per request from Kent-Petra Construction for final occupancy inspection (lndscpng, prkng lot, etc.)
called Carol M, said she will call Mike 11/14/2001 9:13:18 AM
Code Occupancy Approval11/13/200111/14/200111/14/2001APASS
DetailsMichael Garner
Scheduled by Inspector: MSG On 11/13/2001 3:01:16 PM 10:00 a.m. inspection per request from Kent-Petra Construction for final occupancy inspection (lndscpng, prkng lot, etc.)

I walked the property after reviewing approved changes on the plans. I signed the final for this property - case closed. 11/14/2001 3:27:10 PM
BLD-Energy code compliance11/12/200111/13/200111/13/2001PCANC
DetailsTony Young
Scheduled by a contractor via Hello! on 11/12/2001 at 09:18:16. Contact: ###-####.
BLD-Conference11/6/200111/6/200111/6/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 11/06/2001 at 09:42:19. Contact: ###-#### ,,,profit mtg 11/6/2001 2:27:59 PM
BLD-Concrete10/24/200110/25/200110/25/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/24/2001 at 14:51:01. Contact: ###-####.slab around pool area, si was there, pending rpt 10/25/2001 9:50:54 AM
BLD-Foundation10/10/200110/11/200110/11/2001ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 10/10/2001 at 14:48:34. Contact: ###-####.due to rain 10/11/2001 10:00:32 AM
BLD-Foundation10/9/200110/10/200110/10/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/09/2001 at 11:45:30. Contact: ###-####.
BLD-Foundation10/9/200110/10/200110/10/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/09/2001 at 11:46:19. Contact: ###-####.
s. i. on site 10/10/2001 3:33:15 PM
BLD-Foundation10/8/200110/9/200110/9/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/08/2001 at 15:55:33. Contact: ###-####.
BLD-Concrete10/8/200110/8/200110/8/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/08/2001 at 09:08:49. Contact: ###-####.
si on site 10/9/2001 9:05:02 AM
BLD-Foundation10/4/200110/8/200110/8/2001APART
DetailsTony Young
###-####
masonary, si on site 10/8/2001 11:07:20 AM
BLD-Foundation10/4/200110/5/200110/5/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/04/2001 at 15:13:33. Contact: ###-####.
corrections on rebar, si on site to oversee fixes 10/5/2001 10:46:24 AM
BLD-Foundation10/3/200110/4/200110/4/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/03/2001 at 15:49:29. Contact: ###-####.
already done ,si on site 10/4/2001 3:38:08 PM
BLD-Foundation10/2/200110/3/200110/3/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/02/2001 at 16:00:12. Contact: ###-####.
already poured, si on site 10/3/2001 4:03:55 PM
BLD-Foundation10/2/200110/2/200110/2/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 10/02/2001 at 08:44:44. Contact: ###-####.
pending si report 10/2/2001 2:41:00 PM
BLD-Concrete8/29/20018/30/20018/30/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 08/29/2001 at 16:07:20. Contact: ###-####.already grouted, si was onsite, pending report 8/30/2001 3:19:05 PM
BLD-Foundation8/28/20018/29/20018/29/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 08/28/2001 at 13:24:30. Contact: ###-####.
not ready, si will be on site 8/29/2001 9:14:54 AM
BLD-Foundation8/28/20018/28/20018/28/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/28/2001 at 07:46:13. Contact: ###-####....masonry, pend insp report. 8/28/2001 4:47:12 PM
BLD-Foundation8/23/20018/24/20018/24/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 08/23/2001 at 15:22:05. Contact: ###-####.pending si report 8/24/2001 11:55:31 AM
BLD-Other8/22/20018/23/20018/23/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 08/22/2001 at 15:50:47. Contact: ###-####.grout, allready done, pending si report 8/23/2001 10:28:36 AM
BLD-Conference8/17/20018/17/20018/17/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 8/17/2001 5:26:06 PM w/ Tony & contractor re finals
BLD-Foundation7/24/20017/24/20017/24/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 07/24/2001 at 11:16:04. Contact: ###-####.
pending s. i. report 7/24/2001 3:46:26 PM
BLD-Foundation7/20/20017/20/20017/20/2001PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 07/20/2001 at 07:46:23. Contact: ###-####.west side of bldg 7/20/2001 3:45:06 PM