Permanent Occupancy | | 11/30/2001 | 11/30/2001 | | DONE |
|
|
|
|
BLD-Final | 11/26/2001 | 11/27/2001 | 11/27/2001 | A | PART |
Russ Owen
|
|
|
SHANE ###-#### . ok needs plumbing for perm oc. 11/27/2001 11:50:27 AM
|
BLD-Final | 11/7/2001 | 11/8/2001 | 11/8/2001 | A | PART |
Russ Owen
|
|
|
###-####. Needs revised exterior exit system for out door dining , plan shows panic hardware at gates and also they have gated area constructed different from plans. Gates have been removed for temporary oc, also need dead bolt removed from office. Also has waitress booths in close prox to exit doors they were shown on fixture plans to be at present location ,main floor plan does no show them at all, contractor will be having new smaller one made. Ok for temporary oc only at this time. 11/8/2001 11:34:45 AM
|
FIRE-Final Inspection | 11/7/2001 | 11/7/2001 | 11/7/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/7/2001 3:07:58 PM Fire/life safety is finaled. OK for perm occ
|
BLD-Final | 11/1/2001 | 11/1/2001 | 11/1/2001 | P | NR |
Russ Owen
|
|
|
###-####. needs all other signatures. 11/1/2001 4:12:14 PM
|
BLD-Framing/Rough-in | 10/25/2001 | 10/26/2001 | 10/26/2001 | A | PART |
Russ Owen
|
|
|
CELLING GRID ###-#### SHANE Found 3 lights in kitchen with no slack wires, contractor not on site. no c/n posted.. 10/26/2001 9:50:14 AM
|
BLD-Framing/Rough-in | 10/23/2001 | 10/23/2001 | 10/23/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-#### shaft inspection shaft ok 10/23/2001 2:40:38 PM
|
BLD-Framing/Rough-in | 10/2/2001 | 10/2/2001 | 10/2/2001 | P | PART |
Russ Owen
|
|
|
###-#### 2 layer wrap on duct above grease hoods,still needs top of hood protection. 10/2/2001 3:41:36 PM
|
BLD-Energy code compliance | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-#### SHANE ok to cover walls 9/20/2001 9:21:25 AM
|
BLD-Energy code compliance | 9/17/2001 | 9/18/2001 | 9/18/2001 | A | PART |
Russ Owen
|
|
|
###-#### SHANE ok to sheetrock kitchen/restrooms. front dining area ok subject to ele inspection. 9/18/2001 11:03:10 AM
|
BLD-Framing/Rough-in | 9/14/2001 | 9/17/2001 | 9/17/2001 | P | PART |
Russ Owen
|
|
|
###-#### SHANE only items left are a-35 at soffit and fire blocking c/n in office. 9/17/2001 2:03:02 PM
|
BLD-Framing/Rough-in | 9/13/2001 | 9/14/2001 | 9/14/2001 | P | PART |
Russ Owen
|
|
|
###-#### SHANE. rear kitchen and restroom areas only c/n posted. 9/14/2001 4:04:31 PM
|
BLD-Framing/Rough-in | 9/7/2001 | 9/10/2001 | 9/10/2001 | A | PART |
Tom Arcoraci
|
|
|
SHEER PANEL ###-#### SHANE
|
BLD-Framing/Rough-in | 9/6/2001 | 9/7/2001 | 9/7/2001 | A | FAIL |
Russ Owen
|
|
|
shear panel and a hd holddowns shane ###-####. hold -downs ok, shear nailing incomplete. recall. 9/7/2001 11:48:37 AM
|
BLD-Conference | 8/28/2001 | 8/29/2001 | 8/29/2001 | A | PART |
Russ Owen
|
|
|
###-####. need details from engineer for rear wall connection to parapet,also still needs inspection of entire exterior shear questions only today. 8/29/2001 11:05:46 AM
|
BLD-Framing/Rough-in | 7/13/2001 | 7/16/2001 | 7/16/2001 | A | PASS |
Russ Owen
|
|
|
Shane ###-####conduit removed and replaced with steel,also walls ok. 7/16/2001 12:23:26 PM
|
BLD-Foundation | 7/11/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Russ Owen
|
|
|
Robert ###-####c/n posted for area with pvc eletrical condiut in footing, engineer has allowed steel schedual 40,will replace and recall. 7/13/2001 8:56:04 AM
|
BLD-Footing | 7/9/2001 | 7/10/2001 | 7/10/2001 | P | FAIL |
Russ Owen
|
|
|
ft insp robert- ###-#### c/n posted for electrical conduit in footing. 7/10/2001 4:37:10 PM
|