Permit Information
Permit NumberBLD01-01109
StatusFinaled
Name ST ALPHONSUS REG MEDICAL CENTER
Site Address 131 N ALLUMBAUGH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
(ST ALPHONSUS BEHAVIORAL HEALTH SERVICES-ADDITION AND REMODEL) To remodel the existing 20,000 sq.ft. psychatric services and support medical facility and add 1,315 sq.ft., (630 s.f. as training classroom on the west side of building adjacent to office area and 685 s.f.as new entry, waiting, reception and admin area), per approved plans on file, CUP01-00030 AND DRH01-00062. NOTE: This building is fully fire sprinklered; is 1-hour fire-resistive construction throughout & the "I-3" Occupancy is divided into 3,900 sq. ft. areas by a 2-hour Area Separation wall & separated from the "B" occupancy by a conbination 2-hour Area & Occupancy Separation wall. There is a 1-hour rated exit corridor system serving the "I" occupancy. A CERTIFICATE OF OCCUPANCY IS REQUIRED AS A CONDITION OF THIS PERMIT. (P.C.#0367-01)/drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/5/20033/6/20033/6/2003APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 3/5/2003 at 9:08:39 AM. Contact: ###-####. ok for perm occ 3/6/2003 2:29:05 PM
Permanent Occupancy 3/6/20033/6/2003 DONE
Details
BLD-Final3/4/20033/4/20033/4/2003PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 3/4/2003 at 9:54:24 AM. Contact: ###-####. needs mech final 3/4/2003 4:10:46 PM
Code Occupancy Approval  3/4/2003 PASS
ALL DONE SO SIGNED FINAL.
FIRE-Final Inspection2/28/20032/28/20032/28/2003PPASS
DetailsTroy Cobbley
Fire life safety, fire alarm and fire sprinklers finaled
BLD-Aging Inspection2/11/20032/11/20032/11/2003 PASS
DetailsTom Arcoraci
wip 2/11/2003 7:47:29 AM
Extend Permit 180 days 12/10/200212/10/2002 DONE
I talk to Tom about this.
BLD-Aging Inspection12/9/200212/9/200212/9/2002 FAIL
DetailsTom Arcoraci
temp expired 12/9/2002 10:35:33 AM
BLD-Final8/13/20028/14/20028/14/2002APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 08/13/2002 at 15:45:46. Contact: ###-####.ok for temp occ entry area only 8/14/2002 11:15:38 AM
FIRE-Final Inspection8/12/20028/13/20028/13/2002PPART
DetailsTroy Cobbley
lobby area OK to occupy 8/13/2002 3:39:04 PM
FIRE-Final Inspection6/12/20026/14/20026/14/2002APART
DetailsTroy Cobbley
Doctors office area ok to occupy 6/14/2002 2:05:33 PM
BLD-Conference6/6/20026/6/20026/6/2002PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 6/6/2002 11:30:38 AM meet with arch after 1 pm will continue 1 hr wall and wrap beam at new const per plan 6/6/2002 2:28:13 PM
BLD-Conference5/20/20025/20/20025/20/2002PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 5/20/2002 8:27:22 AM
BLD-Conference5/16/20025/17/20025/17/2002APASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 5/16/2002 4:58:35 PM struc members need 1 hr protection 5/20/2002 7:40:47 AM
BLD-Wall cover5/16/20025/16/20025/16/2002PPART
DetailsTom Arcoraci
###-#### jan ok to cover phase 3. new entry struc members need 1 hr protection 5/16/2002 4:25:58 PM
FIRE-Final Inspection5/2/20025/3/20025/3/2002PPART
DetailsTroy Cobbley
group/rec room ok for occupancy 5/3/2002 3:55:58 PM
FIRE-Final Inspection4/26/20024/29/20024/29/2002APART
DetailsTroy Cobbley
nurses station area OK of occ 4/29/2002 4:36:58 PM
BLD-Framing/Rough-in4/26/20024/26/20024/26/2002PPART
DetailsTom Arcoraci
ok to cover jan ###-#### ok to cover 2 hr wall in group rec room 4/26/2002 12:00:37 PM
FIRE-Final Inspection4/25/20024/26/20024/26/2002PFAIL
DetailsTroy Cobbley
Inspection was for the nurse station area. Earthquake straps are missing from the new and existing fire sprinkler pipe hangers and notification circuit for this area was not working 4/26/2002 4:10:01 PM
FIRE-Final Inspection4/4/20024/5/20024/5/2002PPART
DetailsTroy Cobbley
Classroom area is ok to occupy. Penatrations through corridor wall repair work needs to be verified with manufactures installation sheets 4/5/2002 4:14:50 PM
FIRE-Final Inspection4/1/20024/2/20024/2/2002PFAIL
DetailsTroy Cobbley
This inspection was for the classroom. No fire sprinkler plans on site, need to add duct detectors to hvac unit, provide fire sprinkler canopies, add fire extinguisher, repair penatrations though 2-hour wall, test fire alarm system 4/2/2002 4:39:22 PM
FIRE-Final Inspection3/27/20023/28/20023/28/2002PFAIL
DetailsRick Jackson
###-#### JAN wanted to occupy the group room; sprinklers within 6 feet of each other, need to test the smoke detector and notification within the group room/bathroom 3/28/2002 4:18:08 PM
FIRE-Conference3/27/20023/27/20023/27/2002PCANC
DetailsTroy Cobbley
###-#### JAN
BLD-Other3/5/20023/6/20023/6/2002APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 03/05/2002 at 11:49:08. Contact: ###-####. ceiling grid in new nurses station 3/6/2002 1:00:00 PM
BLD-Final3/4/20023/5/20023/5/2002AFAIL
DetailsJim Sly
###-#### JAN Complete 2hr wall. 3/5/2002 12:05:39 PM
BLD-Framing/Rough-in1/30/20021/31/20021/31/2002APART
DetailsTom Arcoraci
ok to cover--jan-- ###-#### ok to cover nurse sta 1/31/2002 11:05:15 AM
BLD-Wall cover1/3/20021/3/20021/3/2002PPASS
DetailsTom Arcoraci
###-#### ok to cover class room 1/3/2002 3:31:51 PM
BLD-Framing/Rough-in12/19/200112/20/200112/20/2001PPART
DetailsTom Arcoraci
###-#### ok to cover ext at front entry 12/20/2001 4:06:49 PM
BLD-Framing/Rough-in11/27/200111/28/200111/28/2001PPART
DetailsRuss Owen
jan ###-#### wall. ext walls of class room. 11/28/2001 4:43:45 PM
BLD-Conference11/20/200111/20/200111/20/2001PPART
DetailsTom Arcoraci
###-#### JAN need detail for attachment of flat studs to angle hold down 11/20/2001 3:11:34 PM
BLD-Concrete11/1/200111/2/200111/2/2001APART
DetailsTom Arcoraci
###-#### JAN pending spec insp 11/1/2001 3:32:38 PM
BLD-Conference10/15/200110/15/200110/15/2001PPASS
DetailsTom Arcoraci
###-#### JAN wip ok 10/15/2001 1:41:35 PM
BLD-Foundation9/13/20019/14/20019/14/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 09/13/2001 at 12:21:39. Contact: ###-####.subject to s-i. 9/14/2001 12:03:47 PM
BLD-Framing/Rough-in9/11/20019/12/20019/12/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 09/11/2001 at 16:18:03. Contact: ###-####.
BLD-Footing9/4/20019/5/20019/5/2001APART
DetailsTom Arcoraci
###-#### JAN wip spec on site 9/5/2001 3:18:17 AM