Permanent Occupancy | | 6/12/2002 | 6/12/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/4/2001 | 12/4/2001 | 12/4/2001 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/4/2001 11:32:33 AM Fire life/safety finaled. Fire door inspected and checked out OK
|
BLD-Final | 11/30/2001 | 12/3/2001 | 12/3/2001 | A | PART |
Jim Storey
|
|
|
###-#### LARRY temp occ ok pending p&z and ele perm sign off bond in place for landscaping. 12/3/2001 5:09:20 PM
|
BLD-Framing/Rough-in | 11/9/2001 | 11/13/2001 | 11/13/2001 | A | PASS |
Jim Storey
|
|
|
CEILING GRID ###-#### LARRY ceilling ok for cover. 11/13/2001 8:56:01 AM
|
FIRE-Supply Line Flush | 11/9/2001 | 11/13/2001 | 11/13/2001 | A | PART |
Troy Cobbley
|
|
|
Supply line flush and hydro OK 11/13/2001 10:39:13 AM
|
BLD-Framing/Rough-in | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | PART |
Jim Storey
|
|
|
###-#### LARRY CEILING GRID perimitor rooms ok for cover main ceilling pending ele approval as wel as approval from fire for all ceilling. 11/6/2001 9:13:19 AM
|
BLD-Framing/Rough-in | 11/6/2001 | 11/6/2001 | 11/6/2001 | P | PART |
Jim Storey
|
|
|
overhead inspection ###-#### ceilling ok pending others. 11/7/2001 8:18:25 AM
|
FIRE-Sprinkler Rough-in | 11/2/2001 | 11/5/2001 | 11/5/2001 | A | FAIL |
Troy Cobbley
|
|
|
approved plans not on site 11/5/2001 9:22:37 AM
|
BLD-Framing/Rough-in | 11/1/2001 | 11/2/2001 | 11/2/2001 | A | FAIL |
Russ Owen
|
|
|
###-#### LARRY CEILING GRID. perimeter wires needed and lights not in place. 11/2/2001 10:56:36 AM
|
BLD-Framing/Rough-in | 10/16/2001 | 10/16/2001 | 10/16/2001 | P | PASS |
Jim Storey
|
|
|
###-#### fire gyp on mez ok for lap and nailling. 10/17/2001 11:52:48 AM
|
BLD-Framing/Rough-in | 10/1/2001 | 10/2/2001 | 10/2/2001 | P | PASS |
Jim Storey
|
|
|
###-#### office ok. 10/3/2001 9:07:14 AM
|
BLD-Framing/Rough-in | 9/25/2001 | 9/26/2001 | 9/26/2001 | A | PART |
Jim Storey
|
|
|
###-#### LARRY ROOF DECK INSPECTION roof deck welding rfi to engineer for perimitor weld north and south walls west end of roof deck reweld atchment and sheer configuration perplan un noted. 9/26/2001 10:15:49 AM
|
BLD-Concrete | 8/28/2001 | 8/29/2001 | 8/29/2001 | P | PASS |
Jim Storey
|
|
|
###-#### MIKE ft at col. special insp. / reviewed roof erection in process tilt panels weld and back pour ok for cover/ recieved engineer office beam modifaction approved and archived to city. 8/30/2001 9:10:12 AM
|
BLD-Concrete | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PART |
Jim Storey
|
|
|
larry ###-#### concrete west ft cover with special insp. not ready at this time added to scope of special./ engineering change for #6 barto be relayed to my self to place at ft not epoxy. 8/20/2001 10:11:27 AM
|
BLD-Concrete | 8/15/2001 | 8/16/2001 | 8/16/2001 | P | PASS |
Jim Storey
|
|
|
retilt bar insp larry- ###-#### rebar ok pending special insp.report. 8/16/2001 4:34:40 PM
|
BLD-Concrete | 8/14/2001 | 8/14/2001 | 8/14/2001 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 8/14/2001 8:24:34 AM c/n made ok rebar ok for colm design and top chord.
|
BLD-Concrete | 8/10/2001 | 8/13/2001 | 8/13/2001 | P | FAIL |
Jim Storey
|
|
|
rebar in the tilt walls Larry ###-####c/n no seperation of steel mats at top 1/3 vert steel above door openings. 8/13/2001 4:43:33 PM
|
BLD-Foundation | 7/25/2001 | 7/26/2001 | 7/26/2001 | P | PART |
Jim Storey
|
|
|
###-#### placed with out city insp on walls office foundation/ pending special insp. report all though no reqired per plan. 7/26/2001 3:17:04 PM
|
BLD-Footing | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PASS |
Jim Storey
|
|
|
###-#### ft ok 7/23/2001 3:13:40 PM
|