BLD-Final | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 15:22:40. Contact: ###-####. c.c # 20979 issued 11/21/2001 10:24:13 AM
|
BLD-Final | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 09:23:11. Contact: ###-####.
|
BLD-Final | 11/19/2001 | 11/19/2001 | 11/19/2001 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/19/2001 at 10:47:18. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/12/2001 | 10/12/2001 | 10/12/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/12/2001 at 06:45:46. Contact: ###-####. insulation ok all c/n items completed ok cover 10/12/2001 9:30:15 AM
|
BLD-Energy code compliance | 10/11/2001 | 10/11/2001 | 10/11/2001 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/11/2001 at 06:29:36. Contact: ###-####. c/n items not completed 10/11/2001 10:11:03 AM
|
BLD-Framing/Rough-in | 10/10/2001 | 10/10/2001 | 10/10/2001 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/10/2001 at 00:38:36. Contact: ###-####. c/n on site ok to insulate 10/10/2001 11:10:26 AM
|
BLD-Framing/Rough-in | 10/10/2001 | 10/10/2001 | 10/10/2001 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/10/2001 at 00:41:29. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/9/2001 | 10/9/2001 | 10/9/2001 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 06:08:24. Contact: ###-####. needs plumbing rough in and city appr plans on site 10/9/2001 10:20:44 AM
|
BLD-Wall cover | 9/27/2001 | 9/27/2001 | 9/27/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/27/2001 at 07:33:10. Contact: ###-####.
|
BLD-Foundation | 8/13/2001 | 8/13/2001 | 8/13/2001 | P | PART |
Dave Hannah
|
|
|
###-#### mana wall work in progress 8/13/2001 2:23:42 PM
|
BLD-Footing | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/09/2001 at 14:57:52. Contact: ###-####.
|
BLD-Footing | 8/9/2001 | 8/9/2001 | 8/9/2001 | P | NR |
Dave Hannah
|
|
|
###-#### crew having problems old concrete slab conflicting with ftg and drain ditch dumping water in excavation 8/9/2001 3:20:18 PM
|