Permit Information
Permit NumberBLD01-01345
StatusFinaled
Name ST LUKES REG MEDICAL CENTER
Site Address 148 E JEFFERSON ST
Project NameST LUKES-IS BLDG
Customer NumberSTL21-516
ePlanReviewNo
Description
(HUMAN RESOURCES - IS BUILDING, MAIN FLOOR)(SLRMC SUPPORT FACILITY) To remodel an existing 4,323 sq.ft. main floor portion of the existing 5,123 s.f. (4,323 + 800 s.f. storage unit area. Also has an 870 s.f. basement.) of this existing Data Center Office for Medical Records for use as the HUMAN RESOURCES - IS OFFICE BUILDING per approved plans on file. To include removal of raised computer data room floor panels in southwest corner of building; construction of new 2 x 10 floor joists at 16" on center over new pony walls on footing (clear span approx. 7 ft.), sheathed W/ 3/4" T&G, O.S.B.; to construct non-bearing walls to create offices to support staff needs; two new accessible restrooms. NOTE: A CERTIFICATE OF OCCUPANCY IS REQUIRED AS A CONDITION OF THIS PERMIT, BUT NO C.O. WILL BE ISSUED AND OCCUPANCY IS BE ALLOWED UNTIL THE DEFFERED SUBMITTAL AND CONDITIONS LISTED IN ATTACHED PLAN REVIEW CONCERNING THE COMPRESSED GAS STORAGE AREA HAS BEEN SATISFACTORILY ADDRESSED AND ANY FIRE/LIFE SAFETY CONCERNS ABATED FOR CODE COMPLIANCE. This building is fully sprinklered. (P.C.#0426-01)/drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/9/20034/9/20034/9/2003PDONE
DetailsDave Hannah
DAN; Phone #: ###-#### Internet Inspection Request from: Darla Downs
Permanent Occupancy 4/9/20034/9/2003 DONE
Details
BLD-Final4/4/20034/4/20034/4/2003APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/4/2003 at 7:22:27 AM. Contact: ###-####.ok for perm occ 4/4/2003 1:11:19 PM
BLD-Final3/4/20033/5/20033/5/2003ANR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 3/4/2003 at 2:00:48 PM. Contact: ###-####...need verify gas storage final as per permit req's 3/5/2003 4:05:41 PM
BLD-Aging Inspection3/3/20033/3/20033/3/2003 PASS
DetailsDave Hannah
called construction office they will schedule final 3/4/2003 11:26:07 AM
BLD-Conference12/17/200212/19/200212/19/2002APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/17/2002 at 15:48:28. Contact: ###-####.
BLD-Aging Inspection12/12/200212/12/200212/17/2002 PASS
DetailsCarl Dependahl
called Stan Brown, proj mgr, will advise re final status 12/17/2002 11:23:39 AM
BLD-Final8/22/20028/22/20028/22/2002AFAIL
DetailsJim Storey
###-#### need exit signage/ 8/22/2002 2:27:58 PM
BLD-Final12/19/200112/20/200112/20/2001PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/19/2001 at 13:02:12. Contact: ###-####. Ok for temp oc pending conditions on permit for a perm co. 12/20/2001 2:23:01 PM
FIRE-Final Inspection12/19/200112/20/200112/20/2001PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/19/2001 at 13:00:36. Contact: ###-####.
FIRE-Final Inspection12/13/200112/13/200112/13/2001PFAIL
DetailsRick Jackson
Added by Inspector: 409 On 12/13/2001 4:44:31 PM sprinklers in concealed combustible spaces or cover; c/n issued
BLD-Framing/Rough-in11/15/200111/15/200111/15/2001PPART
DetailsCarl Dependahl
celing ###-#### dan, c/n re grid clg. ok to continue 11/15/2001 4:32:45 PM
BLD-Framing/Rough-in10/30/200110/31/200110/31/2001AFAIL
DetailsTony Young
###-#### DAN CEILING
c/n posted, need trades, seismic pods 10/31/2001 10:59:00 AM
BLD-Framing/Rough-in9/24/20019/24/20019/24/2001PPART
DetailsSteven Webb
fr ###-####- phil Southwest portion of building--floor--pending mechanical approval. 9/24/2001 2:28:46 PM
BLD-Framing/Rough-in9/20/20019/21/20019/21/2001APART
DetailsDave Hannah
fr insp- bill ###-#### ok to cover rooms #117-121,128-132,141-143,136,138,139 micro lame beams 3ok but 4 needs point load blocking floor to ftg 9/21/2001 12:45:01 PM