BLD-Aging Inspection | 7/22/2003 | 7/22/2003 | 7/22/2003 | | DONE |
Carl Dependahl
|
|
|
previously finalled, ok for l/c 7/22/2003 9:17:38 AM
|
BLD-Final | 5/21/2003 | 5/22/2003 | 5/22/2003 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:31 AM. Contact: ###-####. ok for c/o 5/22/2003 11:31:19 AM
|
BLD-Final | 5/21/2003 | 5/22/2003 | 5/22/2003 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:31 AM. Contact: ###-####. ok for c/o 5/22/2003 11:31:19 AM
|
FIRE-Final Inspection | 5/13/2003 | 5/13/2003 | 5/13/2003 | P | PASS |
Rick Jackson
|
|
|
|
FIRE-Final Inspection | 4/7/2003 | 4/7/2003 | 4/7/2003 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 4/7/2003 at 6:48:05 AM. Contact: ###-####. need detectors at all smoke/fire dampers; all rated doors not installed as shown on plans; audible not loud enough; need to relocate detectors within 5 ft of door with hold opens 4/7/2003 4:33:16 PM
|
BLD-Conference | 3/6/2003 | 3/7/2003 | 3/7/2003 | P | PASS |
Carl Dependahl
|
|
|
w/fire...seal all penetrations a 3/7/2003 5:04:30 PM t rated assy's 3/7/2003 5:07:14 PM
|
FIRE-Conference | 3/5/2003 | 3/7/2003 | 3/7/2003 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 3/5/2003 at 10:32:30 AM. met with Jason; reviewed plans and wlaked the project area; will need 60 minute doors on all storage/linen rooms as shown on plans; penetrations will need protection; will need to test alarms and review sprinkler plans 3/7/2003 10:31:57 AM
|
BLD-Framing/Rough-in | 10/23/2002 | 10/24/2002 | 10/24/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/23/2002 at 08:54:58. Contact: ###-####....walls, firestops ok at storage areas, c/n re perimeter wires etc..ok to continue, chk at final.... 10/24/02 12:34:16 PM
|
BLD-Framing/Rough-in | 9/16/2002 | 9/17/2002 | 9/17/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/16/2002 at 14:18:03. Contact: ###-####. wip on 4 th floor store room 9/17/2002 11:30:21 AM
|
BLD-Framing/Rough-in | 9/13/2002 | 9/16/2002 | 9/16/2002 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/13/2002 at 13:06:11. Contact: ###-####. no answer on phone 9/16/2002 3:48:33 PM
|
BLD-Framing/Rough-in | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 10:19:07. Contact: ###-####. walls ok at lounge area, patch roof/clg, verify s/f dampers 4/9/2002 5:24:10 PM
|
BLD-Aging Inspection | 1/7/2002 | 1/7/2002 | 1/10/2002 | | NR |
Carl Dependahl
|
|
|
st lukes, work may be postponed? 1/10/2002 12:03:56 PM
|