Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-01347
StatusFinaled
Name ST LUKES STL200408
Site Address 190 E BANNOCK ST
Project NameST LUKES-4 NORTH / SOUTH
Customer NumberSTL200-408
ePlanReviewNo
Description
(ST LUKES - 4 SOUTH & 4 NORTH of 4TH FLOOR)(NURSE STATION CORE REMODEL) To remodel approximately 4,300 sq. ft. portion of the 4th floor, Central & North Wings. To perform selective demolision as per plans; to construct new non-bearing, non-combustible, fire-resistive walls to create new room layout & support use's as per approved plans; to separate the Storage, Soiled Linen & Clean Supply rooms from adjacent areas with 1-hour occupancy separation rooms per Table 3-C, UBC; to refurbish the interiors and add new cabinetry & millwork; provide accessibility compliance; upgrades to electrical, plumbing, mechanical, fire sprinklers and alarm systems to meet hospital needs and maintain compliance with current adopted codes per approved plans on file. NOTE: This building is fully sprinklered. A "LETTER OF COMPLETION / COMPLIANCE IS REQUIRED AS A CONDITION OF THIS PERMIT BEFORE THE REMODELED AREAS ARE APPROVED FOR OCCUPANCY & USE. (P.C.#0428-01) / drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection7/22/20037/22/20037/22/2003 DONE
DetailsCarl Dependahl
previously finalled, ok for l/c 7/22/2003 9:17:38 AM
BLD-Final5/21/20035/22/20035/22/2003APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:31 AM. Contact: ###-####. ok for c/o 5/22/2003 11:31:19 AM
BLD-Final5/21/20035/22/20035/22/2003APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:31 AM. Contact: ###-####. ok for c/o 5/22/2003 11:31:19 AM
FIRE-Final Inspection5/13/20035/13/20035/13/2003PPASS
DetailsRick Jackson
FIRE-Final Inspection4/7/20034/7/20034/7/2003AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 4/7/2003 at 6:48:05 AM. Contact: ###-####. need detectors at all smoke/fire dampers; all rated doors not installed as shown on plans; audible not loud enough; need to relocate detectors within 5 ft of door with hold opens 4/7/2003 4:33:16 PM
BLD-Conference3/6/20033/7/20033/7/2003PPASS
DetailsCarl Dependahl
w/fire...seal all penetrations a 3/7/2003 5:04:30 PM t rated assy's 3/7/2003 5:07:14 PM
FIRE-Conference3/5/20033/7/20033/7/2003AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 3/5/2003 at 10:32:30 AM. met with Jason; reviewed plans and wlaked the project area; will need 60 minute doors on all storage/linen rooms as shown on plans; penetrations will need protection; will need to test alarms and review sprinkler plans 3/7/2003 10:31:57 AM
BLD-Framing/Rough-in10/23/200210/24/200210/24/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 10/23/2002 at 08:54:58. Contact: ###-####....walls, firestops ok at storage areas, c/n re perimeter wires etc..ok to continue, chk at final.... 10/24/02 12:34:16 PM
BLD-Framing/Rough-in9/16/20029/17/20029/17/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/16/2002 at 14:18:03. Contact: ###-####. wip on 4 th floor store room 9/17/2002 11:30:21 AM
BLD-Framing/Rough-in9/13/20029/16/20029/16/2002ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 09/13/2002 at 13:06:11. Contact: ###-####. no answer on phone 9/16/2002 3:48:33 PM
BLD-Framing/Rough-in4/9/20024/9/20024/9/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/09/2002 at 10:19:07. Contact: ###-####. walls ok at lounge area, patch roof/clg, verify s/f dampers 4/9/2002 5:24:10 PM
BLD-Aging Inspection1/7/20021/7/20021/10/2002 NR
DetailsCarl Dependahl
st lukes, work may be postponed? 1/10/2002 12:03:56 PM