BLD-Final | 11/2/2001 | 11/2/2001 | 11/2/2001 | P | PASS |
Dave Hannah
|
|
|
###-#### SCOTT
|
BLD-Final | 9/27/2001 | 9/27/2001 | 9/27/2001 | P | PART |
Tony Young
|
|
|
ok as long as other trades are ok, owner said bond is in place for exterior and landscape 9/27/2001 4:32:19 PM
|
FIRE-Final Inspection | 9/24/2001 | 9/24/2001 | 9/24/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 9/24/2001 11:17:18 AM
|
BLD-Framing/Rough-in | 9/19/2001 | 9/19/2001 | 9/19/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 11:15:27. Contact: ###-####.
shell framing and shear ok, need to have trades finish south 1/2 of shell w/ T. I. permit. 9/19/2001 3:04:43 PM
|
BLD-Framing/Rough-in | 9/6/2001 | 9/6/2001 | 9/6/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 09/06/2001 at 11:06:21. Contact: ###-####.
east/west ext. fire walls ok to cover 9/6/2001 2:47:54 PM
|
BLD-Framing/Rough-in | 8/31/2001 | 9/4/2001 | 9/4/2001 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/31/2001 at 12:01:32. Contact: ###-####.
|
BLD-Energy code compliance | 8/28/2001 | 8/29/2001 | 8/29/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/28/2001 at 16:42:20. Contact: ###-####.
north 1/2 of shell ok 8/29/2001 2:29:48 PM
|
BLD-Framing/Rough-in | 8/28/2001 | 8/29/2001 | 8/29/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/28/2001 at 12:25:29. Contact: ###-####.
need to verify later in pm 8/29/2001 9:21:39 AM
|
BLD-Framing/Rough-in | 8/27/2001 | 8/28/2001 | 8/28/2001 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/27/2001 at 17:05:20. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/28/2001 | 8/28/2001 | 8/28/2001 | P | PART |
Tony Young
|
|
|
ok to cover north side, need eng. fix on posts on bearing walls 8/28/2001 4:29:38 PM
|
BLD-Framing/Rough-in | 8/23/2001 | 8/24/2001 | 8/24/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/23/2001 at 19:42:52. Contact: ###-####.ext. shear ok on east and west side 8/24/2001 10:28:48 AM
|
BLD-Conference | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PART |
Tony Young
|
|
|
firewall and floor ?s 8/19/2001 11:01:05 PM
will need arch. approval on floor, firewall per plan. 8/20/2001 10:14:15 AM
|
BLD-Conference | 8/17/2001 | 8/17/2001 | 8/17/2001 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 07:37:37. Contact: ###-####.
|
BLD-Foundation | 7/24/2001 | 7/25/2001 | 7/25/2001 | A | PART |
Tony Young
|
|
|
###-####
wip, verbal corrections 7/25/2001 11:06:30 AM
|
BLD-Footing | 7/24/2001 | 7/24/2001 | 7/24/2001 | P | PART |
Tony Young
|
|
|
###-####
wip, ok when ready 7/24/2001 3:38:47 PM
|
BLD-Conference | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PART |
Tony Young
|
|
|
###-#### Mike
soil ok w/ verbal corrections, compaction and removal of any debris 7/23/2001 4:38:18 PM
|