Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD01-01634
StatusFinaled
Name DAVIES-REID TRIBAL ARTS
Site Address 515 W IDAHO ST
Project NameDAVIES-REID BLDG
Customer Number 
ePlanReviewNo
Description
(DAVIES-REID TRIBAL ARTS) This building is NOT fire sprinklered. To remodel an existing 5,084 square foot historic building to be used for retail sales. This building has two stories and a basement. The turret that was destroyed in a fire will be rebuilt. Selective demolition is also covered under this permit. Work is to include a wheelchair lift, new stairways, a seismic upgrade, and a restroom accessible to the disabled all per approved drawings, engineering, and plan review conditions on file. DRH01-00106 PC-0500-01 **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/13/200112/14/200112/14/2001APASS
DetailsCarl Dependahl
###-####; rec'd spec insp final report ok, hand rails installed, ok for c/o 12/14/2001 12:02:19 PM
Permanent Occupancy 12/14/200112/14/2001 DONE
Details
BLD-Final12/13/200112/13/200112/13/2001PNR
DetailsCarl Dependahl
fn occ bill ###-#### ...rec'd letter from arch re deletion of one stairway from bsmt; ok as two exits remain. Need spec insp's report re seismic upgrade. keep c/n 12/13/2001 3:09:11 PM
BLD-Final12/5/200112/6/200112/6/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/05/2001 at 15:18:07. Contact: ###-####...keep c/n, (spec insp seismic ties, complete firestops or box out pvc at bsmt lid.) ok for t/o 12/6/2001 12:50:22 PM
BLD-Final12/4/200112/5/200112/5/2001AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/04/2001 at 15:52:39. Contact: ###-####. east stair handrailling not compliant submital to tim hogland based on conversation with carl w. and the provitions in the ucbc./ need all handraills to extened and return/ need fire stopping listing for 3 " pipe penatration sw corner of basement. 12/5/2001 11:22:56 AM
BLD-Final12/3/200112/4/200112/4/2001PNR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/03/2001 at 13:55:54. Contact: ###-####.. needs zoning and fire prior to calling for final. 12/4/2001 4:01:57 PM
FIRE-Final Inspection12/3/200112/4/200112/4/2001APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/03/2001 at 13:55:09. Contact: ###-####. will remove deadbolt from rear exit door for structural inspector 12/4/2001 4:42:11 PM
BLD-Framing/Rough-in10/30/200110/31/200110/31/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/30/2001 at 14:50:48. Contact: ###-####.. Ok to cover rest room walls. 10/31/2001 11:21:34 AM
BLD-Framing/Rough-in10/29/200110/30/200110/30/2001PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/29/2001 at 13:32:21. Contact: ###-####. need ti fire block. 10/31/2001 9:13:56 AM
BLD-Conference10/26/200110/26/200110/26/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 10/26/2001 4:38:02 PM w/ supt re resubmittal...ok to realign elevator and hvac chases
BLD-Concrete10/3/200110/3/200110/3/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 10/3/2001 3:06:51 PM col ftgs at rear of bldg ok
BLD-Framing/Rough-in10/3/200110/3/200110/3/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 10/3/2001 5:46:12 PM seismic straps,blocks ok...bolts imbeds ok per mti
BLD-Framing/Rough-in10/3/200110/3/200110/3/2001PCANC
DetailsRuss Owen
###-#### BOB. trans to 340. 10/4/2001 10:18:02 AM
BLD-Footing9/12/20019/13/20019/13/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/12/2001 at 15:29:11. Contact: ###-####....c/n issued re spec insp agreement; shore dangerous outbuilding. 9/13/2001 4:43:17 PM