BLD-Final | 2/20/2003 | 2/20/2003 | 2/20/2003 | P | PASS |
Tony Young
|
|
|
###-#### perry please call for access
l of c issued 2/20/2003 3:49:54 PM
|
BLD-Final | 1/15/2003 | 1/16/2003 | 1/16/2003 | A | CANC |
Russ Owen
|
|
|
call first ###-####out of time rcalled for pm. 1/16/2003 12:55:29 PM
|
BLD-Final | 1/16/2003 | 1/16/2003 | 1/16/2003 | P | FAIL |
Russ Owen
|
|
|
This 1/16/2003 1:35:39 PMThis is not ready pre-inspection only, no plans and I have not much of an idea as to the work that was permited. I left a c/n for some items ,may need more pending plans and other mis from inspector with prior history. 1/16/2003 1:38:17 PM
|
BLD-Final | 1/15/2003 | 1/15/2003 | 1/15/2003 | P | CANC |
Jim Storey
|
|
|
CALL FIRST ###-####
|
BLD-Conference | 10/30/2002 | 10/31/2002 | 10/31/2002 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
on attic issues, no firedoor reqd, guard rails, etc. 10/31/2002 10:43:09 AM
|
BLD-Conference | 10/4/2002 | 10/7/2002 | 10/7/2002 | A | PART |
Tony Young
|
|
|
###-#### KYLE
conf. on storage area, stairs, guardrail, handrail to meet code 10/7/2002 11:27:53 AM
|
BLD-Conference | 8/22/2002 | 8/23/2002 | 8/23/2002 | A | PASS |
Tony Young
|
|
|
###-#### TERRY PLEASE CALL 1ST
head room above winder stairs should finish out ok w/ 1/2" sheetrock. to get 6' 8" 8/23/2002 12:29:31 PM
|
BLD-Conference | 8/23/2002 | 8/23/2002 | 8/23/2002 | P | PASS |
Tony Young
|
|
|
see other notes 8/23/2002 4:02:20 PM
|
BLD-Framing/Rough-in | 8/16/2002 | 8/19/2002 | 8/19/2002 | A | PASS |
Dave Hannah
|
|
|
###-#### perry everything on c/n list completed but for stairs they will need to be cheched at final 8/19/2002 10:46:55 AM
|
BLD-Energy code compliance | 8/12/2002 | 8/12/2002 | 8/12/2002 | P | PART |
Dave Hannah
|
|
|
terry; Phone #: ###-#### seal package holes foamed but still needs to seal around bottom plate 8/12/2002 2:38:26 PM
|
BLD-Framing/Rough-in | 8/12/2002 | 8/12/2002 | 8/12/2002 | P | PART |
Dave Hannah
|
|
|
terry; Phone #: ###-#### 4 of 6 items complete ok to insulate 8/12/2002 2:37:13 PM
|
BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 | P | FAIL |
Tony Young
|
|
|
###-#### perry
c/n posted 7/11/2002 2:52:50 PM
|
BLD-Conference | 7/2/2002 | 7/2/2002 | 7/2/2002 | P | PART |
Tony Young
|
|
|
see other notes 7/2/2002 1:34:04 PM
|
BLD-Conference | 6/28/2002 | 7/2/2002 | 7/2/2002 | A | PART |
Tony Young
|
|
|
richard- ###-#### for conf
conf on stairs and loft w/ guardrail per code,,, storage only, just open to bed rooms 7/2/2002 1:33:43 PM
|
BLD-Conference | 6/28/2002 | 7/1/2002 | 7/1/2002 | A | CANC |
Jim Sly
|
|
|
richard- ###-#### for conf Richard preferred to talk to insp over this area on stair issue. 7/1/2002 10:54:39 PM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/11/2002 | 6/11/2002 | A | NR |
Carl Dependahl
|
|
|
shear wall brian ###-#### c/n...need eng'g...spec insp for moment frame??? recall 6/11/2002 1:04:01 PM
|
BLD-Framing/Rough-in | 6/11/2002 | 6/11/2002 | 6/11/2002 | P | FAIL |
Carl Dependahl
|
|
|
shear nailing, /c/n onsite...$42 fee due if eng'g not onsite for next insp...left msg w/ supt. 6/11/2002 1:09:10 PM
|
BLD-Wall cover | 4/1/2002 | 4/2/2002 | 4/2/2002 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/01/2002 at 13:33:07. Contact: ###-####.Need attached egineering not on plan,also does not appear to be completed, contractor on site will recall. 4/2/2002 4:42:29 PM
|
BLD-Conference | 3/21/2002 | 3/21/2002 | 3/21/2002 | P | PASS |
Alan Hauser
|
|
|
went over hvac with heating contractor 3/21/2002 3:11:06 PM
|
BLD-Aging Inspection | 1/28/2002 | 1/28/2002 | 1/28/2002 | | PART |
Tony Young
|
|
|
|
BLD-Aging Inspection | 11/28/2001 | 11/28/2001 | 11/28/2001 | | PART |
Tony Young
|
|
|
wip 11/28/2001 9:37:52 AM
|
BLD-Conference | 9/27/2001 | 9/27/2001 | 9/27/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/27/2001 9:34:39 AM w/ Bob Eason re concrete insp & found modification
|
BLD-Foundation | 9/26/2001 | 9/27/2001 | 9/27/2001 | A | PART |
Tony Young
|
|
|
###-#### BOBwip, 9/27/2001 11:32:55 AM
|
BLD-Foundation | 9/24/2001 | 9/24/2001 | 9/24/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/24/2001 at 07:28:21. Contact: ###-####....ext portion fnd wall; hd's & imbeds not set; add'l eng'g req'd to change configuration of wall below existing dwelling to block. design is 2500psi. 9/24/2001 12:01:14 PM
|
BLD-Footing | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PART |
Tony Young
|
|
|
###-####
basement ftgs, wip, ok 9/20/2001 11:45:05 AM
|