BLD-Final | 7/10/2002 | 7/11/2002 | 7/11/2002 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 13:35:46. Contact: ###-####.
c/n posted 7/10/2002 1:00:33 PM
|
BLD-Grading Inspection | 7/8/2002 | 7/8/2002 | 7/8/2002 | | PASS |
Rita DeYoung
|
|
|
Final grading and drainage is approved.
|
BLD-Energy code compliance | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PASS |
Tony Young
|
|
|
###-#### john
|
BLD-Framing/Rough-in | 3/12/2002 | 3/12/2002 | 3/12/2002 | P | PART |
Tony Young
|
|
|
###-#### JOHN
ok to insulate// strap beams, top plates 3/12/2002 2:20:12 PM
|
BLD-Framing/Rough-in | 2/26/2002 | 2/26/2002 | 2/26/2002 | P | PART |
Carl Dependahl
|
|
|
###-#### shear nailing...ext nailing ok 2/26/2002 5:43:17 PM
|
BLD-Aging Inspection | 1/15/2002 | 1/15/2002 | 1/15/2002 | | PART |
Tony Young
|
|
|
wip 1/16/2002 9:52:33 AM
|
BLD-Foundation | 11/15/2001 | 11/15/2001 | 11/15/2001 | P | PART |
Tony Young
|
|
|
###-#### STEVE
|
BLD-Foundation | 11/8/2001 | 11/9/2001 | 11/9/2001 | A | PART |
Tony Young
|
|
|
###-#### STEVE
|
BLD-Footing | 11/7/2001 | 11/8/2001 | 11/8/2001 | A | PART |
Tony Young
|
|
|
###-#### STEVE
not pouring yet, need soils report, finish setting up 11/8/2001 12:07:16 PM
|
BLD-Conference | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PART |
Russ Owen
|
|
|
###-#### STEVE
|
BLD-Conference | 11/7/2001 | 11/7/2001 | 11/7/2001 | P | CANC |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 11/7/2001 12:55:58 PM I had called this number at 11:00am left message to call me back , at 3:00pm icalled back left another message to call me I do not know the location of this job, It does not show on my 3 maps I have. 11/7/2001 3:15:51 PM
|