BLD-Final | 10/1/2002 | 10/2/2002 | 10/2/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/01/2002 at 10:58:06. Contact: ###-####. ok for perm occ. 10/2/2002 3:46:22 PM
|
Permanent Occupancy | | 10/2/2002 | 10/2/2002 | | DONE |
|
|
|
|
BLD-Final | 9/27/2002 | 9/30/2002 | 9/30/2002 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/27/2002 at 11:50:35. Contact: ###-####.
|
FIRE-Final Inspection | 9/27/2002 | 9/30/2002 | 9/30/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 9/30/2002 11:16:21 AM
|
FIRE-Final Inspection | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | FAIL |
Troy Cobbley
|
|
|
paint curbing as discussed, paint parking stall in front of the fire hydrant, provide emergency lighting in sanctuary as per the UBC and provide two "fire lane-park in marked stalls only" signs at the entrances to the property 9/26/2002 2:59:29 PM
|
Code Occupancy Approval | | | 9/24/2002 | | PASS |
|
|
|
PHASE I -complies with CUP01-0053
|
BLD-Conference | 9/18/2002 | 9/18/2002 | 9/18/2002 | P | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/18/2002 at 11:16:55. Contact: ###-####. discussion on min requirements for finished space 9/19/2002 9:29:55 AM
|
BLD-Conference | 9/13/2002 | 9/16/2002 | 9/16/2002 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/13/2002 at 11:44:13. Contact: ###-####. need to have the permit rewriten to show what areas are to be left unfinshed 9/16/2002 12:06:42 PM
|
BLD-Other | 7/30/2002 | 7/30/2002 | 7/30/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/30/2002 at 07:19:15. Contact: ###-####.ok but need fire rating data on panels fo exit passege ways 7/30/2002 2:37:46 PM
|
BLD-Conference | 6/7/2002 | 6/10/2002 | 6/10/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/07/2002 at 08:04:19. Contact: ###-####.Talked with contractor about a ladder acces to projector, told him to contact the architect about relocation of this as , I would not accept the new location. due to clearance problems. 6/10/2002 11:33:27 AM
|
BLD-Energy code compliance | 5/20/2002 | 5/21/2002 | 5/21/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/20/2002 at 09:05:50. Contact: ###-####. partial insulation inspection south wing 90 % complete, Note: no commercial energy code addopted by Boise City. 5/21/2002 10:24:09 AM
|
BLD-Framing/Rough-in | 5/16/2002 | 5/17/2002 | 5/17/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/16/2002 at 08:36:00. Contact: ###-####.south office area ok to insulate 5/17/2002 10:54:47 AM
|
BLD-Energy code compliance | 5/8/2002 | 5/9/2002 | 5/9/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 09:25:53. Contact: ###-####.north office area ok to cover walls 5/9/2002 8:53:04 AM
|
BLD-Framing/Rough-in | 5/6/2002 | 5/7/2002 | 5/7/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/06/2002 at 11:19:24. Contact: ###-####. shear at front entry roof sheeting front entry framing onnorth and front entry ok 5/7/2002 12:06:14 PM
|
BLD-Framing/Rough-in | 4/26/2002 | 4/29/2002 | 4/29/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/26/2002 at 13:31:09. Contact: ###-####. ext shear and partial roof nailing ok 4/29/2002 9:19:09 AM
|
BLD-Framing/Rough-in | 4/17/2002 | 4/18/2002 | 4/18/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/17/2002 at 09:29:39. Contact: ###-####. Roof deck nailing at north area, nailing ok from roof access to west exteior wall, note used alternate staples as shown on plans, no exterior wall inspection at this time, Also this building is non-rated construction due to fire sprinklers. 4/18/2002 11:12:42 AM
|
BLD-Footing | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 16:40:34. Contact: ###-####. pending spec insp 4/10/2002 9:46:10 AM
|
BLD-Footing | 2/21/2002 | 2/22/2002 | 2/22/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/21/2002 at 14:36:16. Contact: ###-####.tilt up panels sign off by mti 2/22/2002 2:03:48 PM
|
BLD-Footing | 2/18/2002 | 2/19/2002 | 2/19/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/18/2002 at 09:43:47. Contact: ###-####. OK pend MTI report and appr. 2/19/2002 12:44:41 PM
|
BLD-Footing | 2/12/2002 | 2/13/2002 | 2/13/2002 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/12/2002 at 16:11:55. Contact: ###-####. tilt up panels checked bar with project super mti will also inspect and test concrete 2/13/2002 3:45:47 PM
|
BLD-Footing | 2/4/2002 | 2/5/2002 | 2/5/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/04/2002 at 12:32:56. Contact: ###-####. mti doing spec inspection 2/5/2002 9:22:50 AM
|
BLD-Footing | 1/31/2002 | 2/1/2002 | 2/1/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/31/2002 at 11:51:30. Contact: ###-####. work was inspected by mti 2/1/2002 11:12:51 AM
|
BLD-Footing | 1/23/2002 | 1/24/2002 | 1/24/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/23/2002 at 13:36:55. Contact: ###-####.
|
BLD-Footing | 1/21/2002 | 1/22/2002 | 1/22/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 12:58:54. Contact: ###-####. mti has done inspection and pulled concrete sample 1/23/2002 9:08:14 AM
|
BLD-Footing | 1/16/2002 | 1/17/2002 | 1/17/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/16/2002 at 13:15:06. Contact: ###-####. mti on site they have inspected the rebar and are testing thwe concrete all ok 1/18/2002 9:04:09 AM
|