BLD-Final | 2/28/2002 | 3/1/2002 | 3/1/2002 | A | PART |
Carl Dependahl
|
|
|
Pat ###-#### struct appears ok, need soils report/bond/p.wks ok. 3/1/2002 10:11:40 AM
|
BLD-Grading Inspection | 3/1/2002 | 3/1/2002 | 3/1/2002 | | BOND |
Rita DeYoung
|
|
|
Grading complete and approved. Downspouts must be connected. Upon receipt of a $500.00 bond the grading and drainage is conditionally approved.
|
BLD-Framing/Rough-in | 12/11/2001 | 12/11/2001 | 12/11/2001 | P | PASS |
Tony Young
|
|
|
###-####
|
BLD-Framing/Rough-in | 12/10/2001 | 12/10/2001 | 12/10/2001 | P | PART |
Tony Young
|
|
|
###-####
framing matters ok, need sprinklers signed off 12/10/2001 3:47:06 PM
|
BLD-Framing/Rough-in | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | NR |
Tony Young
|
|
|
###-#### 12/5/2001 4:46:07 PM ###-#### 12/5/2001 4:46:07 PM 12/5/2001 4:46:50 PM
|
BLD-Framing/Rough-in | 12/5/2001 | 12/6/2001 | 12/6/2001 | P | PART |
Tony Young
|
|
|
###-####
need fire sprinklers finished, engineering on front and rear wall, finish hold downs, fix trusses per specs, ok to insulate 12/6/2001 3:07:12 PM
|
BLD-Framing/Rough-in | 12/5/2001 | 12/5/2001 | 12/5/2001 | A | NR |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 12/5/2001 4:41:32 PM
|
BLD-Framing/Rough-in | 11/12/2001 | 11/13/2001 | 11/13/2001 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/12/2001 at 14:48:03. Contact: ###-####. c/n on site 11/13/2001 9:52:25 AM
|
BLD-Foundation | 10/1/2001 | 10/1/2001 | 10/1/2001 | P | PART |
Tony Young
|
|
|
###-#### JARED SHEER WALL ALSO
poured 10/1/2001 4:31:43 PM
|
BLD-Footing | 9/28/2001 | 9/28/2001 | 9/28/2001 | P | PART |
Tony Young
|
|
|
ft insp- jerrad ###-####
pending letter from soil eng. 9/28/2001 3:28:48 PM
|