Columbia Village Pump House * To construct a 425 sq. ft. pump house to cover an existing water pump. All work to be per the approved plans and attached engineering; conditions and notes attached.. Additional value and seperate mechanical permit required to install optional air handler. PC#754-01 pep
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/14/20033/21/20033/21/2003APASS
DetailsDave Hannah
follow up to 5 day notice pass ok for c.c 3/21/2003 9:45:11 AM
BLD-Aging Inspection3/11/20033/12/20033/12/2003AFAIL
DetailsJim Storey
waiting for follow up from dave mortsen job super.no action form phone call earler in week. 5 day notice posted on site no one around. p paine will recieve 5 day notice for on file copy. clone insp for 25 day notice insp. 3/14/2003 10:03:05 AM
BLD-Aging Inspection3/11/20033/11/20033/11/2003 PART
DetailsJim Storey
dave with mortsen said he would have the job super call me to follow up with insp and provide aproved plan. 3/11/2003 5:04:53 PM
BLD-Energy code compliance1/29/20021/29/20021/29/2002PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 01/29/2002 at 07:04:54. Contact: ###-####. Insulation verified in building BUT per Table 5-A of 97 UBC opening IS NOT allowed (even with damper) on a S-2-type with in 5 feet even if protected. 1/29/2002 1:49:30 PM
BLD-Framing/Rough-in1/29/20021/29/20021/29/2002APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 01/29/2002 at 07:03:49. Contact: ###-####. ok to insulate---fire damper needed in 1-hr fire wall prior to passing at final. 1/29/2002 8:52:18 AM
BLD-Framing/Rough-in1/22/20021/25/20021/25/2002PFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 01/22/2002 at 14:55:55. Contact: ###-####. 30"' X 30" supply air cannot be in 1-Hour opening unless smoke and fire damper is installed with an equi. fire rating. Relocation outside the 1-Hr wall is also an option. 1/25/2002 2:26:41 PM
BLD-Wall cover12/12/200112/12/200112/12/2001PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 12/12/2001 at 10:23:06. Contact: ###-####. shear 12/12/2001 3:00:54 PM
BLD-Foundation11/26/200111/26/200111/26/2001PPART
DetailsSteven Webb
JACK ###-#### house wip--garage not ready 11/26/2001 2:34:50 PM
BLD-Footing11/20/200111/20/200111/20/2001PPASS
DetailsSteven Webb
Engineering recieved from Keith Jones--footing per his engineering. 11/20/2001 1:16:30 PM
BLD-Footing11/8/200111/9/200111/9/2001AFAIL
DetailsSteven Webb
###-#### JACK Electrical conduit which run through footing are not per as the approved plans indicate. Contractor to re-locate conduit which agrees with plans or modifiy plans to eliminate conduit positioned in footings. Do not pour. 11/9/2001 11:38:39 AM
BLD-Footing11/6/200111/7/200111/7/2001APART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 11/06/2001 at 19:25:01. Contact: ###-####. Contractor to conference with electrical inspector -- will call for re-inspection. 11/7/2001 11:12:50 AM
BLD-Footing11/2/200111/5/200111/5/2001ADONE
DetailsSteven Webb
###-#### JACK Conference not footing--reviewed approved plans ok to modify to concrete as long as a min. of 12" footer and 6" stem wall is obtained. 11/5/2001 10:53:10 AM