BLD-Final | 7/16/2002 | 7/17/2002 | 7/17/2002 | A | FAIL |
Tony Young
|
|
|
fn carol- ###-####
c/n posted,, no inspection made 7/17/2002 1:15:49 PM
|
BLD-Energy code compliance | 12/10/2001 | 12/11/2001 | 12/11/2001 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/10/2001 at 15:00:35. Contact: .
|
BLD-Framing/Rough-in | 12/5/2001 | 12/6/2001 | 12/6/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/05/2001 at 16:00:51. Contact: . ok to cover ext shear ok . ok to insulate framing ok 12/6/2001 2:59:06 PM
|
BLD-Framing/Rough-in | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | NR |
Tony Young
|
|
|
12/5/2001 4:37:38 PM
|
BLD-Footing | 10/29/2001 | 10/30/2001 | 10/30/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/29/2001 at 15:09:03. Contact: ###-####. new ftg under old slab 10/30/2001 1:01:10 PM
|
BLD-Conference | 10/22/2001 | 10/22/2001 | 10/22/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 10/22/2001 2:27:57 PM . 10/22/2001 2:40:08 PM. Talked with contractor about the plans and the requirements for load bearing walls to have footings to frost depth. Posted c/n. Note: This structure is 494 sq ft and will be insulated and completly drywalled on the inside, and only has 13 percent of floor area in window openings. This proposed structure is designed no different than any typical R-3 addition. And by code should not be constructed on a slab, Even if room use is labled screened room on plan/permit. 10/22/2001 2:55:52 PM
|
BLD-Footing | 10/12/2001 | 10/15/2001 | 10/15/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/12/2001 at 16:28:28. Contact: . NOTE, This is an addition of a frost depth mono pouer slab approx 8 foot ext,onto an existing slab with no footing as shown on approved plans this area can not be used as heated habitible space .Existing slab should have been required to have a frost depth footing as it supports a trussed roofed screen room with ceiling fans shown on plans and plan also indicates room to be used year round ? New footing as per approved plans. 10/15/2001 10:57:39 AM
|