BLD-Final | 12/13/2002 | 12/16/2002 | 12/16/2002 | A | PASS |
Steven Webb
|
|
|
###-#### Fire final passed on 12/13/02-regular C. of O can be issued. 12/16/2002 8:49:04 AM
|
FIRE-Final Inspection | 12/13/2002 | 12/16/2002 | 12/16/2002 | A | CANC |
Troy Cobbley
|
|
|
inspection already done 12/16/2002 10:55:34 AM
|
Permanent Occupancy | | 12/16/2002 | 12/16/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/13/2002 | 12/13/2002 | 12/13/2002 | P | PASS |
Troy Cobbley
|
|
|
fire alarm finaled
|
BLD-Final | 10/2/2002 | 10/3/2002 | 10/3/2002 | A | PART |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok for temp occ 10/3/2002 9:07:34 AM
|
FIRE-Final Inspection | 10/3/2002 | 10/3/2002 | 10/3/2002 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given on the fire alarm system per Dave Miller's approval until the additional strobes are added in the rooms and the existing horn/strobes in the rooms are relocated
|
BLD-Final | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | FAIL |
Tony Young
|
|
|
jerry -###-####
need trades signed off 1st 9/4/2002 10:51:42 AM
|
BLD-Other | 7/24/2002 | 7/24/2002 | 7/24/2002 | P | NR |
Dave Hannah
|
|
|
jerry ###-#### please call before going out contractor still working on 1 hr around elec boxs 7/24/2002 4:05:17 PM
|
BLD-Framing/Rough-in | 7/18/2002 | 7/19/2002 | 7/19/2002 | A | FAIL |
Russ Owen
|
|
|
JIM ###-####
c/n posted, also noted 2 electrical panels in 1 hr corridor, and no top plate protection. 7/19/2002 10:37:20 AM
|
BLD-Framing/Rough-in | 7/10/2002 | 7/10/2002 | 7/10/2002 | P | PART |
Tony Young
|
|
|
###-#### jim
insulation ok,, ok to rock pending mech. ok/// then call for nailing on 1st layer of rock 7/10/2002 4:32:06 PM
|
BLD-Framing/Rough-in | 7/8/2002 | 7/8/2002 | 7/8/2002 | P | FAIL |
Tony Young
|
|
|
jim- ###-#### r/i
c/n,, ok to insulate 7/10/2002 12:51:21 PM
|
BLD-Framing/Rough-in | 7/1/2002 | 7/1/2002 | 7/1/2002 | P | FAIL |
Jim Sly
|
|
|
jim- ###-####-fr insp C/N on site. 7/2/2002 3:42:39 AM
|
FIRE-Final Inspection | 6/27/2002 | 6/28/2002 | 6/28/2002 | A | PART |
Troy Cobbley
|
|
|
Inspection was not for a final. Inspection was for a tenting inspection. Tenting is OK. Sprinklers OK for cover 6/28/2002 4:04:37 PM
|
BLD-Framing/Rough-in | 6/26/2002 | 6/27/2002 | 6/27/2002 | P | NR |
Tony Young
|
|
|
jim- ###-#### fr
|
BLD-Framing/Rough-in | 6/24/2002 | 6/25/2002 | 6/25/2002 | P | NR |
Tony Young
|
|
|
JIM ###-#### R/I
|
FIRE-Sprinkler Rough-in | 6/24/2002 | 6/25/2002 | 6/25/2002 | A | FAIL |
Rick Jackson
|
|
|
JIM- ###-#### R/I insulation needs to be stapled to joist or secured 6/25/2002 8:26:12 AM
|
BLD-Framing/Rough-in | 5/28/2002 | 5/29/2002 | 5/29/2002 | P | PART |
Tony Young
|
|
|
ext. shear ok, verify alt. hds at frame 5/29/2002 4:52:40 PM
|
BLD-Framing/Rough-in | 5/28/2002 | 5/28/2002 | 5/28/2002 | P | CANC |
Tony Young
|
|
|
###-#### jim
|
BLD-Framing/Rough-in | 5/22/2002 | 5/23/2002 | 5/23/2002 | A | FAIL |
Tony Young
|
|
|
JIM ###-#### SHEER NAILING
not nailed per plan, and 2 hds are under window, called jim 5/23/2002 9:42:23 AM
|
BLD-Foundation | 4/2/2002 | 4/3/2002 | 4/3/2002 | A | PART |
Tony Young
|
|
|
late am ###-####
wip 4/3/2002 12:48:14 PM
|
BLD-Foundation | 4/1/2002 | 4/2/2002 | 4/2/2002 | A | PART |
Tony Young
|
|
|
###-#### MIKE
ftgs ok, cleared up differences between arch. drawing and engineering on size of ftgs, also depth of frost level,,,all ok 4/2/2002 10:19:20 AM
|