BLD-Aging Inspection | 12/15/2003 | 12/15/2003 | 12/15/2003 | | PASS |
Jim Storey
|
|
|
3/4 12/15/2003 8:04:43 AM
|
FIRE-Final Inspection | 3/3/2003 | 3/4/2003 | 3/4/2003 | A | PASS |
Rick Jackson
|
|
|
BOYD; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Permanent Occupancy | | 3/4/2003 | 3/4/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/28/2003 | 2/28/2003 | 2/28/2003 | P | NR |
Rick Jackson
|
|
|
boyd; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie talked to Boyd and they to do some work on the generator 2/28/2003 1:32:40 PM
|
BLD-Final | 2/26/2003 | 2/27/2003 | 2/27/2003 | P | PART |
Jim Storey
|
|
|
###-#### ###-#### final occ ok pending fire sign off. 2/27/2003 4:22:02 PM
|
FIRE-Final Inspection | 2/27/2003 | 2/27/2003 | 2/27/2003 | P | FAIL |
Rick Jackson
|
|
|
need strobe replaced in room 2 restroom; need remote reset switches for detectors on northside; need 2 hr test paperwork for generator; need to test transfer switch for main power to generator; remove exit sign by FACP; need zones at FACP 2/27/2003 4:52:09 PM
|
Code Occupancy Approval | 2/11/2003 | 2/11/2003 | 2/11/2003 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 2/11/2003 2:04:54 PM
|
BLD-Final | 1/20/2003 | 1/21/2003 | 1/21/2003 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/20/2003 at 11:09:46. Contact: ###-####. contractor wanted mech final not bld. 1/21/2003 8:53:14 AM
|
BLD-Other | 1/17/2003 | 1/17/2003 | 1/17/2003 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/17/2003 at 07:32:37. Contact: ###-####. ceilling ok for cover pending mech and ele approval. 1/17/2003 10:08:21 AM
|
BLD-Framing/Rough-in | 10/29/2002 | 10/30/2002 | 10/30/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/29/2002 at 17:16:46. Contact: ###-####.west bay wall and east bay wall ok 10/30/2002 3:09:34 PM
|
BLD-Framing/Rough-in | 10/16/2002 | 10/17/2002 | 10/17/2002 | A | PART |
Jim Storey
|
|
|
framing ok pending other insp. 10/17/2002 10:09:47 AM
|
BLD-Framing/Rough-in | 10/15/2002 | 10/16/2002 | 10/16/2002 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/15/2002 at 10:54:15. Contact: ###-####.out of time. 10/16/2002 5:29:07 PM
|
BLD-Wall cover | 10/10/2002 | 10/11/2002 | 10/11/2002 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/10/2002 at 10:45:21. Contact: ###-####.exterior sheer ok for cover keth jones walk through with myself and approved aplacations that were noted on previous insp. 10/11/2002 1:54:24 PM
|
BLD-Framing/Rough-in | 9/25/2002 | 9/26/2002 | 9/26/2002 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/25/2002 at 13:23:19. Contact: ###-####.
|
BLD-Wall cover | 9/19/2002 | 9/19/2002 | 9/19/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/19/2002 at 07:22:57. Contact: ###-####. int shear wall north west side ok to rock over 9/19/2002 10:41:33 AM
|
BLD-Framing/Rough-in | 9/6/2002 | 9/9/2002 | 9/9/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/06/2002 at 11:41:17. Contact: ###-####.south wall framing bolts and holddowns ok for cover. 9/9/2002 10:06:22 AM
|
BLD-Footing | 8/7/2002 | 8/8/2002 | 8/8/2002 | A | PART |
Jim Storey
|
|
|
###-#### ###-####rebar ok special insp. pending. mti 8/8/2002 9:51:28 AM
|