Permit Information
Permit NumberBLD01-03230
StatusFinaled
Name GSA (NATURAL RESOURCE CENTER)
Site Address 1387 S VINNELL WAY
Project NameBLM BLDG-ALL FLOORS
Customer Number 
ePlanReviewNo
Description
**(GSA-NATURAL RESOURCE CENTER)**(BLM BLDG-ALL FLOORS) Remodel the interior of an existing 3 story 91,740 sq ft office building per approved plans on file. Work will involve all 3 floors. Work to include, (1st floor) removal of partitions and counters, construction of 64 lf of new noncombustible partitions in two different locations, patch and repair suspended ceiling system, (2nd floor) removal of partitions, relocation of egress doors & infill existing corridor walls, construction of 127 lf of nonconbustible partitions in two separate places, construction of 25 lf of tenant demising wall, patch and repair suspended ceiling system, remove an existing mop sink and cap plumbing. (3rd Floor) Removal of partitions, patch and repair suspended ceiling system, no new partitions to be constructed on the 3rd floor. This building is fully fire sprinklered, any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. (pc#936-01) RmH (PLAN MODIFICATION) (12-27-02) PLAN MODIFICATION IS TO CONSTRUCT ADDITIONAL OFFICE AREAS 0N THE SECOND FLOOR, FOUR NEW INDIVIDUAL OFFICE SPACES ARE TO BE CONSTRUCTED, WORK WILL INCLUDE, THE INSTALLATION OF FULL HIGHT OFFICE PARTITION WALLS, NEW ELECTRICAL WORK, MECHANICAL AND FIRE SPRINKLER RELOCATION. NOTE: ANY ALTERATIONS OR MODIFICATIONS TO THE FIRE SPRINKLER SYSTEM SHALL BE PER NFPA #13 AS REGULATED BY THE FIRE DEPARTMENT. (RMH)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/2/20047/2/20047/2/2004PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 7/2/2004 at 9:32:46 AM. Contact: ###-####. C/C issued. 7/2/2004 3:50:51 PM
BLD-Other6/22/20046/23/20046/23/2004APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/22/2004 at 11:27:20 AM. Contact: ###-####. 6/23/2004 11:28:18 AM Call Steve.....Meet in Lobby. checking Mfg walls for bracing. 6/23/2004 11:29:59 AM
BLD-Final3/31/20044/1/20044/1/2004PFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 3/31/2004 at 11:51:00 AM. Contact: ###-####. Needs the electrical permit finaled, which is expired, electrical inspector has talked with tri-state electric. Also the tops of the pre-fab walls, hve not been tied off. 4/1/2004 12:28:02 AM
BLD-Final3/24/20043/25/20043/25/2004APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 3/24/2004 at 2:48:10 PM. Contact: ###-####. needs elec final and plumb final maybe ,ok for final when these are complete 3/25/2004 9:18:08 AM 3/25/2004 9:19:57 AM
FIRE-Final Inspection3/19/20043/19/20043/19/2004PPASS
DetailsTroy Cobbley
Fire life safety, fire alarm and fire sprinklers finaled
BLD-Aging Inspection1/13/20041/13/20041/13/2004 CANC
DetailsRuss Owen
Fire /life safety will check out. 1/20/2004 1:24:36 PM
BLD-Conference5/13/20035/13/20035/13/2003ACANC
DetailsRuss Owen
talked with steve he has submitted plans to the fire life/safety plan review division.
BLD-Aging Inspection3/26/20033/26/20033/26/2003 CANC
DetailsRuss Owen
called steve will be submitting plans in about 2 weeks to resolve fire/life safety insp. 3/27/2003 3:16:44 PM
FIRE-Final Inspection12/23/200212/30/200212/30/2002PFAIL
DetailsTroy Cobbley
###-#### STEVE The fire door for the 2nd floor freight elevator does not latch when the fire alarm system is activated, provide a/v's within 15' of the ends of the corridors on the first and second floors, provide verification of fire/smoke damper activation per review comment #6, revise zone description and the FACP text so they match the device test and then retest, verify signals with the monitoring company, verify with the inspector the current draw on the notification circuits, provide map per review note #7, test the initiating devices. No area or duct smoke detectors were tested due to zone descriptions not matching. Do not final permit until the owner has the approved building plans on site 12/30/2002 4:23:28 PM
FIRE-Final Inspection4/12/20024/19/20024/19/2002AFAIL
DetailsTroy Cobbley
wall mounted device are wrong candella, wall listed devices mounted on ceiling. Review comments were not followed. Elevator recalled is wrong. I stopped inspection. Entire inspection needs to be started over. 4/19/2002 12:48:22 PM
BLD-Framing/Rough-in3/28/20023/29/20023/29/2002APART
DetailsRuss Owen
###-####- steve r/i 2nd floor south side partition ok after ele. 3/29/2002 12:28:21 PM
BLD-Other2/20/20022/21/20022/21/2002APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/20/2002 at 16:27:59. Contact: ###-####.
BLD-Framing/Rough-in2/7/20022/7/20022/7/2002PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/07/2002 at 10:12:02. Contact: ###-####.
BLD-Other1/29/20021/29/20021/29/2002PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/29/2002 at 08:58:25. Contact: ###-####.grid work in lower flor east side small arae on plans. 1/30/2002 9:15:40 AM
BLD-Framing/Rough-in1/22/20021/23/20021/23/2002ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 01/22/2002 at 14:34:32. Contact: ###-####.need trades signed off 1/23/2002 11:00:44 AM
BLD-Framing/Rough-in1/23/20021/23/20021/23/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 415 On 1/23/2002 10:57:35 AM steve 321--9168. most new walls are complete. 1/24/2002 9:50:20 AM