BLD-Final | 10/11/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Tom Arcoraci
|
|
|
ok for perm
|
BLD-Framing/Rough-in | 10/10/2002 | 10/11/2002 | 10/11/2002 | A | CANC |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson
|
Permanent Occupancy | | 10/11/2002 | 10/11/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled
|
BLD-Final | 10/8/2002 | 10/9/2002 | 10/9/2002 | P | PART |
Tom Arcoraci
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for perm when fire signs 10/9/2002 3:49:42 PM
|
FIRE-Final Inspection | 10/8/2002 | 10/9/2002 | 10/9/2002 | A | FAIL |
Troy Cobbley
|
|
|
one duct smoke detector is mounted in an enclosure but the other is not and needs to be. Contractor to provide enclosure and test detectors 10/9/2002 12:22:52 PM
|
FIRE-Final Inspection | 9/23/2002 | 9/24/2002 | 9/24/2002 | A | NR |
Troy Cobbley
|
|
|
inspection was actually just a conference. I went over door hardware issues with the owner, fire extinguisher and possible hvac automatic shutdown 9/24/2002 10:25:15 AM
|
FIRE-Final Inspection | 9/23/2002 | 9/24/2002 | 9/24/2002 | A | NR |
Troy Cobbley
|
|
|
inspection was actually just a conference. I went over door hardware issues with the owner, fire extinguisher and possible hvac automatic shutdown 9/24/2002 10:25:15 AM
|
BLD-Final | 9/20/2002 | 9/23/2002 | 9/23/2002 | A | NR |
Tom Arcoraci
|
|
|
DON; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 6/6/2002 | 6/7/2002 | 6/7/2002 | A | PART |
Tom Arcoraci
|
|
|
###-#### don needs plumbing permit ok after plumbing ok 6/7/2002 10:48:04 AM
|
BLD-Framing/Rough-in | 5/3/2002 | 5/3/2002 | 5/3/2002 | P | PART |
Tom Arcoraci
|
|
|
###-#### JOHN ok for grout 5/3/2002 1:25:34 PM
|
BLD-Conference | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | PASS |
Tom Arcoraci
|
|
|
###-#### JOHN needs eng ok for epoxy rebar change 4/30/2002 2:44:55 PM
|