BLD-Final | 11/24/2003 | 11/25/2003 | 11/25/2003 | A | PASS |
Dave Hannah
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore rolled over from yesterday. ok for perm occ 11/25/2003 9:26:28 AM
|
Permanent Occupancy | | 11/25/2003 | 11/25/2003 | | DONE |
|
|
|
|
BLD-Final | 11/21/2003 | 11/24/2003 | 11/24/2003 | P | FAIL |
Jim Storey
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore rolled over no insp. 11/24/2003 2:24:13 PM
|
FIRE-Final Inspection | 11/20/2003 | 11/21/2003 | 11/21/2003 | A | PASS |
Rick Jackson
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 11/6/2003 | 11/7/2003 | 11/7/2003 | A | PASS |
Dave Hannah
|
|
|
ceiling cover--ron; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover rest of the areas 11/7/2003 9:50:47 AM
|
BLD-Framing/Rough-in | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PART |
Dave Hannah
|
|
|
ceiling cover ron; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie area b ok 11/5/2003 2:54:19 PM
|
BLD-Wall cover | 10/30/2003 | 10/31/2003 | 10/31/2003 | A | NR |
Dave Hannah
|
|
|
Ron; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes crew will rework perm wires 10/31/2003 12:30:35 PM
|
BLD-Other | 10/23/2003 | 10/23/2003 | 10/23/2003 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/23/2003 at 7:50:01 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/9/2003 | 9/10/2003 | 9/10/2003 | A | PART |
Dave Hannah
|
|
|
RON; Phone #: ###-#### Internet Inspection Request from: Marc Lileks hard lids area c ok to cover 9/10/2003 11:05:00 AM
|
BLD-Framing/Rough-in | 8/26/2003 | 8/27/2003 | 8/27/2003 | A | PART |
Dave Hannah
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Annette Moore 8/27/2003 11:11:33 AM 8/27/2003 11:33:56 AM checked fire cualking ok to cover ceilings with hard lids area B 8/27/2003 11:35:32 AM
|
BLD-Framing/Rough-in | 7/29/2003 | 7/30/2003 | 7/30/2003 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 7/29/2003 at 3:00:21 PM. Contact: ###-####...soffits, part, area A...need clg insp & firestopping above lid 7/30/2003 9:57:49 AM
|
BLD-Framing/Rough-in | 7/28/2003 | 7/29/2003 | 7/29/2003 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 7/28/2003 at 9:43:01 AM. Contact: ###-####....area A, need firestop floor drains, walls ok, chk firesops at lid insp. 7/29/2003 4:19:19 PM
|
BLD-Framing/Rough-in | 7/9/2003 | 7/10/2003 | 7/10/2003 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 7/9/2003 at 3:07:33 PM. Contact: ###-####....walls ok area c, chk firestops & soffits w/ ceiling 7/10/2003 12:13:29 PM
|
BLD-Framing/Rough-in | 7/8/2003 | 7/9/2003 | 7/9/2003 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 7/8/2003 at 2:14:00 PM. Contact: ###-####...area c, c/n firestop boxes, patch wall penetrations, complete frame at soiled linen for 1hr separation...recall. 7/9/2003 12:19:50 PM
|
BLD-Framing/Rough-in | 7/8/2003 | 7/8/2003 | 7/8/2003 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 7/8/2003 at 7:52:09 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/24/2003 | 6/24/2003 | 6/24/2003 | P | PART |
Dave Hannah
|
|
|
area B walls only
|
BLD-Wall cover | 6/23/2003 | 6/24/2003 | 6/24/2003 | A | NR |
Dave Hannah
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Annette Moore on site to check progress on project with contractor ,he has started drilling and epoxying rebar ,they have had engineer on site several times a week and M.T.I. on to do spec inspection on rebar and epoxy also have had pull test done on that they have epoxyed all pass to date work is in progress 6/24/2003 10:58:08 AM
|
BLD-Conference | 3/28/2003 | 3/31/2003 | 3/31/2003 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 3/28/2003 at 10:43:28 AM. Contact: ###-####....referred to Dan Stuart for resubmittal 3/31/2003 5:53:46 PM
|
BLD-Conference | 3/26/2003 | 3/28/2003 | 3/28/2003 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 3/26/2003 at 2:58:17 PM. Contact: ###-####...need stamped resub for revisions 3/28/2003 1:31:19 PM
|
BLD-Aging Inspection | 3/14/2003 | 3/14/2003 | 3/14/2003 | | PASS |
Carl Dependahl
|
|
|
project in progress ...will submit for modifications 3/18/2003 10:16:59 AM
|
BLD-Conference | 10/9/2002 | 10/10/2002 | 10/10/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/09/2002 at 10:27:01. Contact: ###-####....work slow due to HVAC changes, etc...WIP. 10/10/02 8:57:36 AM
|
BLD-Conference | 9/20/2002 | 9/23/2002 | 9/23/2002 | A | PASS |
Carl Dependahl
|
|
|
WIP, hvac may be redesigned...slow. 9/23/2002 10:39:55 AM
|
BLD-Conference | 9/20/2002 | 9/20/2002 | 9/20/2002 | P | CANC |
Tom Arcoraci
|
|
|
stan; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|