BLD-Conference | 2/2/2005 | 2/2/2005 | 2/2/2005 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Final | 2/2/2005 | 2/2/2005 | 2/2/2005 | P | PASS |
Dave Hannah
|
|
|
inspection for occ ok for perm occ dave had carles c/n we went tough all the items and I walked the project allc/n items comlpted 2/2/2005 1:39:50 PM
|
BLD-Final | 2/2/2005 | 2/2/2005 | 2/2/2005 | P | DONE |
Dave Hannah
|
|
|
inspection for occ
|
FIRE-Final Inspection | 2/2/2005 | 2/2/2005 | 2/2/2005 | A | PASS |
Rick Jackson
|
|
|
Final okay 2/2/2005 10:49:18 AM
|
FIRE-Final Inspection | 2/2/2005 | 2/2/2005 | 2/2/2005 | A | PASS |
Rick Jackson
|
|
|
|
Permanent Occupancy | | 2/2/2005 | 2/2/2005 | | DONE |
|
|
|
|
BLD-Aging Inspection | 2/20/2004 | 2/20/2004 | 2/20/2004 | | DONE |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 8/6/2003 | 8/6/2003 | 8/6/2003 | | PASS |
Carl Dependahl
|
|
|
WIP... 8/6/2003 11:28:09 AM WIP... statde work complete?? need engs ok for mezz welds8/6/2003 11:28:09 AM 8/6/2003 11:30:19 AM
|
BLD-Final | 5/15/2003 | 5/16/2003 | 5/16/2003 | A | NR |
Carl Dependahl
|
|
|
david; Phone #: ###-#### Internet Inspection Request from: Darla Downs...keep c/n. 5/16/2003 10:40:41 AM
|
FIRE-Final Inspection | 5/15/2003 | 5/16/2003 | 5/16/2003 | A | PART |
Rick Jackson
|
|
|
david; Phone #: ###-#### Internet Inspection Request from: Darla Downs balance report for new hood needed 5/16/2003 4:20:29 PM
|
BLD-Final | 5/14/2003 | 5/14/2003 | 5/14/2003 | P | PART |
Carl Dependahl
|
|
|
Dave...###-#### c/n, occ load signs, door listings, misc finish, obtain other finals; ok for t/o except kitchen. 5/14/2003 6:31:24 PM obtain complete mech finals 5/14/2003 6:32:58 PM
|
BLD-Framing/Rough-in | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PART |
Carl Dependahl
|
|
|
dave, shaft ok...need other insps for final. 5/14/2003 11:21:59 AM
|
BLD-Final | 5/12/2003 | 5/13/2003 | 5/13/2003 | P | NR |
Carl Dependahl
|
|
|
DAVID; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 5/12/2003 | 5/13/2003 | 5/13/2003 | P | PART |
Carl Dependahl
|
|
|
dave ; Phone #: ###-#### Internet Inspection Request from: Annette Moore...wip, shaft. 5/14/2003 9:58:35 AM
|
BLD-Final | 5/9/2003 | 5/12/2003 | 5/12/2003 | A | CANC |
Carl Dependahl
|
|
|
david; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 5/12/2003 | 5/12/2003 | 5/12/2003 | P | PART |
Carl Dependahl
|
|
|
shaft over hood ok...duct by 350 5/12/2003 4:05:12 PM
|
BLD-Conference | 4/16/2003 | 4/16/2003 | 4/16/2003 | P | PART |
Carl Dependahl
|
|
|
Shaft...wip, ok to "3 side" shaft for duct insp by Mechanical insp 4/16/2003 2:03:35 PM
|
BLD-Framing/Rough-in | 4/15/2003 | 4/16/2003 | 4/16/2003 | A | PART |
Carl Dependahl
|
|
|
###-#### walls ok, door moved for 18" clr (ADA). 4/16/2003 12:20:02 PM
|
BLD-Conference | 4/11/2003 | 4/14/2003 | 4/14/2003 | A | PASS |
Carl Dependahl
|
|
|
dave @ devcon...shaft & framing; ###-####; add 18" clr at pull side door at lower level, verify 18" clr to combustibles for hood add drywall as needed...ok to continue, obtain all trade & fire insps prior to frame insp. 4/14/2003 11:40:17 AM
|
BLD-Aging Inspection | 3/18/2003 | 3/18/2003 | 3/18/2003 | | PASS |
Carl Dependahl
|
|
|
met workmen onsite advised to call for insps as req'd 3/18/2003 9:19:56 AM
|