Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD02-00373
StatusFinaled
Name CIVIC PLAZA PA-2 APARTMENTS
Site Address 252 E FRONT ST
Project NameID WATER CENTER-PA2 BLDG D
Customer Number 
ePlanReviewNo
Description
Civic Plaza Apartments PA-2 * (Section 4 of 6) * To construct two four-hour area separation walls to divide this building into six separate buildings. This section is 5 stories and 25 units, @ 4,666 sq.ft. per floor, above a three-hour occupancy separation per UBC Section 311.2.2.1. NOTE: This building is fully fire sprinklered for story increase. All construction per the aproved plans, attached comment list and CABO/ANSI A117.9-1992. MJP PC#111-02 DRH-01-00186 CUP01-00120
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/11/20045/11/20045/11/2004APASS
DetailsDave Hannah
Permanent Occupancy 5/11/20045/11/2004 DONE
Details
BLD-Final2/24/20042/25/20042/25/2004APART
DetailsDave Hannah
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for temp occ 2/25/2004 12:37:33 PM
FIRE-Final Inspection2/24/20042/25/20042/25/2004APASS
DetailsRick Jackson
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Final2/23/20042/24/20042/24/2004ACANC
DetailsDave Hannah
Dennis; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Final2/20/20042/23/20042/23/2004AFAIL
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Code Occupancy Approval  2/23/2004 DONE
BLD-Final2/19/20042/20/20042/20/2004AFAIL
DetailsTroy James
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore Checked doors for closure, seal and hardware. 2/20/2004 11:13:53 AM
BLD-Final2/17/20042/18/20042/18/2004ANR
DetailsDave Hannah
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore
FIRE-Final Inspection2/17/20042/18/20042/18/2004AFAIL
DetailsRick Jackson
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore need signs on FACP and sprinkler room doors; signs in stairwells; extinguishers in lobby and fire pump room; lobby doors can't locked to trap people in lobby area; need extinguishers in penthouse rooms and on all floors; need smoke seals on all rated doors and they must latch; need to verify emergency lighting in corridors; stairwells and exit systems must be free of construction materials; update keys in knox box; complete elevator recall/shunt and sign-off 2/18/2004 3:43:29 PM 2/18/2004 3:44:23 PM
BLD-Final2/9/20042/9/20042/9/2004PNR
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in2/4/20042/4/20042/4/2004PPART
DetailsDave Hannah
dennis ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
BLD-Aging Inspection8/20/20038/20/20038/20/2003 PASS
DetailsCarl Dependahl
PA2 wip 8/20/2003 9:33:29 AM
BLD-Conference6/20/20036/20/20036/20/2003PPASS
DetailsCarl Dependahl
need modification detail for shaft 6/20/2003 5:15:40 PM
BLD-Framing/Rough-in6/19/20036/20/20036/20/2003APART
DetailsCarl Dependahl
4hr wall, wip, ok. 6/20/2003 2:32:16 PM
BLD-Framing/Rough-in5/5/20035/9/20035/9/2003ACANC
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in5/5/20035/8/20035/9/2003APART
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore; prelim only, wip. 5/9/2003 11:55:50 AM
BLD-Framing/Rough-in5/5/20035/7/20035/7/2003APART
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...rec'd eng's ok for ISI's eng'd design of 4hr wall framing...wip ok, extend to/thru corridors as req'd. 5/7/2003 5:00:40 PM
BLD-Framing/Rough-in5/5/20035/6/20035/6/2003APART
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore firewall wip 5/6/2003 3:50:50 PM
BLD-Conference4/18/20034/21/20034/21/2003PPASS
DetailsCarl Dependahl
Need stamped eng'g & arch's ok for altered framing 4/21/2003 5:00:49 PM
BLD-Conference4/14/20034/14/20034/14/2003PPASS
DetailsCarl Dependahl
re 4hr walls...build per eng'g 4/14/2003 5:45:50 PM
BLD-Conference3/25/20033/25/20033/25/2003PPASS
DetailsCarl Dependahl
met arch onsite...keep c/n re struct obsevation; Margie will obtain eng's schedule of insps....will advise 3/25/2003 5:44:00 PM