BLD-Final | 8/2/2002 | 8/2/2002 | 8/2/2002 | P | PASS |
Steven Webb
|
|
|
TROY ###-#### C. of C. #23296 issued. 8/2/2002 2:30:10 PM
|
BLD-Framing/Rough-in | 8/1/2002 | 8/2/2002 | 8/2/2002 | A | FAIL |
Steven Webb
|
|
|
STEVEN ; Phone #: ###-#### C/N--Final not framing--Provide prior c/notice--recall. 8/2/2002 8:54:30 AM
|
BLD-Final | 7/31/2002 | 7/31/2002 | 7/31/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### STEVE c/n on site 7/31/2002 2:42:16 PM
|
BLD-Framing/Rough-in | 5/10/2002 | 5/10/2002 | 5/10/2002 | P | PASS |
Steven Webb
|
|
|
###-####- troy ok to cover Energy--ok to cover 5/10/2002 2:11:12 PM
|
BLD-Framing/Rough-in | 5/9/2002 | 5/9/2002 | 5/9/2002 | P | PASS |
Steven Webb
|
|
|
###-#### bruce Prior c/n items completed--ok to insulate. 5/9/2002 4:14:14 PM
|
BLD-Framing/Rough-in | 5/7/2002 | 5/8/2002 | 5/8/2002 | A | PART |
Jim Storey
|
|
|
1. provide engineering to justify truss repair on 3 ply over grage and truss kot1 exstention of top chord west of stairway. bo4at trusses above grage require latral bracing at both ends of compretion web.
2. fire blk fire place at ceilling line 2 nd floor above garage.
3. c/n all other idems made ok ok to insulate.
|
BLD-Framing/Rough-in | 5/6/2002 | 5/6/2002 | 5/6/2002 | P | FAIL |
Steven Webb
|
|
|
###-#### steven C/n posted--Do not insulate 5/6/2002 3:36:48 PM
|
BLD-Framing/Rough-in | 4/16/2002 | 4/16/2002 | 4/16/2002 | P | PART |
Steven Webb
|
|
|
shear steve ###-#### SHEAR--Ext. ok to side. 4/16/2002 1:58:20 PM
|
BLD-Foundation | 3/22/2002 | 3/25/2002 | 3/25/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/22/2002 at 16:21:45. Contact: ###-####. wip 3/25/2002 9:28:39 AM
|
BLD-Footing | 3/21/2002 | 3/21/2002 | 3/21/2002 | P | PART |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 3/21/2002 2:07:57 PM wip--80% ready at time of inspection 3/21/2002 2:42:02 PM
|