BLD-Final | 6/27/2002 | 6/27/2002 | 6/27/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/27/2002 at 09:57:02. Contact: ###-####. C. of C. #22482 6/27/2002 3:29:34 PM
|
BLD-Energy code compliance | 5/1/2002 | 5/2/2002 | 5/2/2002 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 15:42:08. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/1/2002 | 5/2/2002 | 5/2/2002 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 15:41:30. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 04/30/2002 at 08:43:16. Contact: ###-####.c/n on site ok to insulate 4/30/2002 3:37:54 PM
|
BLD-Framing/Rough-in | 4/15/2002 | 4/16/2002 | 4/16/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/15/2002 at 14:52:31. Contact: ###-####. SHEAR--ok to side 4/16/2002 8:25:11 AM
|
BLD-Foundation | 3/20/2002 | 3/20/2002 | 3/20/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 07:20:35. Contact: ###-####. wip--90% ready at time of inspection 3/20/2002 2:39:52 PM
|
BLD-Footing | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 03/18/2002 at 08:30:22. Contact: ###-####. work in progress checked setbacks all ok 3/18/2002 4:49:10 PM
|