BLD-Final | 7/26/2002 | 7/29/2002 | 7/29/2002 | A | PART |
Tom Arcoraci
|
|
|
jeremy; Phone #: ###-#### bathrooms behind eleavator shaft not complete 7/29/2002 2:19:19 PM
|
FIRE-Final Inspection | 7/25/2002 | 7/26/2002 | 7/26/2002 | P | PASS |
Rick Jackson
|
|
|
CALL PAUL AT ###-#### GO AFTER 2:00 PLEASE
|
BLD-Final | 7/23/2002 | 7/25/2002 | 7/25/2002 | P | CANC |
Carl Dependahl
|
|
|
call Paul first ###-#### paul, called to canc this inspection not ready yet
|
FIRE-Final Inspection | 7/23/2002 | 7/25/2002 | 7/25/2002 | A | FAIL |
Rick Jackson
|
|
|
call paul ###-#### need fire alarm approval prior to occupancy 7/25/2002 9:57:20 AM
|
BLD-Conference | 6/7/2002 | 6/7/2002 | 6/7/2002 | A | PASS |
Carl Dependahl
|
|
|
w/ ISI re frame insp...provide continuous studs at added tall wall, or equal...ok to continue
|
BLD-Framing/Rough-in | 6/5/2002 | 6/6/2002 | 6/6/2002 | A | FAIL |
Carl Dependahl
|
|
|
###-#### complete firestops at plbg penetrations at floor...see c/n. verify sprinkler r/i ok...ok to rock as noted. 6/6/2002 12:02:17 PM
|
BLD-Framing/Rough-in | 6/5/2002 | 6/6/2002 | 6/6/2002 | A | FAIL |
Carl Dependahl
|
|
|
###-#### complete firestops at plbg penetrations at floor...see c/n. verify sprinkler r/i ok...ok to rock as noted. 6/6/2002 12:02:17 PM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Carl Dependahl
|
|
|
firestops at floor ok 6/6/2002 3:33:26 PM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Carl Dependahl
|
|
|
keep c/n ...ok to cover int walls...chk kickers at next insp...floor firestops, straps ok 6/7/2002 11:22:58 AM
|