BLD-Final | 11/22/2002 | 11/22/2002 | 11/22/2002 | P | PASS |
Jim Sly
|
|
|
alice ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Perm Occ. 11/22/2002 4:18:59 PM
|
FIRE-Final Inspection | 11/21/2002 | 11/22/2002 | 11/22/2002 | A | PASS |
Troy Cobbley
|
|
|
access pad has been poured. life safety finaled 11/22/2002 8:53:54 AM
|
Permanent Occupancy | | 11/22/2002 | 11/22/2002 | | DONE |
|
|
|
|
Permanent Occupancy | | 11/22/2002 | 11/22/2002 | | DONE |
|
|
|
|
BLD-Final | 11/18/2002 | 11/18/2002 | 11/18/2002 | P | NR |
Jim Sly
|
|
|
or ###-####; Phone #: ###-#### Internet Inspection Request from: Amy Lawson Need Req signatures. 11/18/2002 3:40:19 PM
|
BLD-Conference | 11/5/2002 | 11/6/2002 | 11/6/2002 | A | PART |
Jim Sly
|
|
|
alice-or cell ###-####; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Walk thru...... 11/6/2002 9:02:26 AM
|
FIRE-Final Inspection | 11/5/2002 | 11/5/2002 | 11/5/2002 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Millers permission. The owner is to have the fire access pad installed by December 1, 2002. The existing gravel road will be reviewed by November 1, 2003 for paving. Please see letter to Dave dated Oct. 29, 2002. All other life/safety items are ok. 11/5/2002 3:11:10 PM
|
FIRE-Conference | 10/31/2002 | 10/31/2002 | 10/31/2002 | P | FAIL |
Troy Cobbley
|
|
|
door hardware is still incorrect and the building address has not been installed 10/31/2002 3:10:06 PM
|
FIRE-Final Inspection | 10/28/2002 | 10/28/2002 | 10/28/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide paved access road per review comments on the conditional use permit, provide paved section to provide 150' acess to building (parking lot) per note #2, remove plant from around the fire hydrant, provide parking signs per review notes #4 and #5, provide building address viewable from the named street see note #7, provide fire extinguisher per review note #9 and provide approved door hardware. the hardware on the office doors is not approved type
|
BLD-Framing/Rough-in | 8/30/2002 | 8/30/2002 | 8/30/2002 | A | PASS |
Dave Hannah
|
|
|
ok to start covering all c/n items completerd 8/30/2002 11:55:18 AM
|
BLD-Framing/Rough-in | 8/26/2002 | 8/26/2002 | 8/26/2002 | A | PART |
Dave Hannah
|
|
|
OK TO COVER EXT SHEAR AND 1 HR PROTECTION OK I also walked framing with alice 8/26/2002 1:18:44 PM
|
BLD-Conference | 8/21/2002 | 8/22/2002 | 8/22/2002 | A | DONE |
Dave Hannah
|
|
|
1 hr fire walls 8/22/2002 9:53:54 AM
|
BLD-Framing/Rough-in | 8/20/2002 | 8/20/2002 | 8/20/2002 | P | PART |
Dave Hannah
|
|
|
shear ok to start covering ext walls 8/20/2002 4:36:49 PM
|
BLD-Framing/Rough-in | 8/13/2002 | 8/14/2002 | 8/14/2002 | A | FAIL |
Dave Hannah
|
|
|
###-#### shear fail partly covered no blocking also one hour fire walls siding will be removed on fire walls so shear can be done and sheet rock installed also no draft stops no truss engineering no framing inspection done at this time told contractor not to cover any thing and when to schd inspections 8/14/2002 9:32:22 AM
|
BLD-Foundation | 6/13/2002 | 6/13/2002 | 6/13/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/13/2002 at 10:34:43. Contact: ###-####.
|
BLD-Footing | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | PASS |
Jim Sly
|
|
|
###-#### tim Letter from Eng. 2500psi No special insp. 6/12/2002 9:31:48 AM
|
BLD-Conference | 6/10/2002 | 6/11/2002 | 6/11/2002 | A | PART |
Jim Sly
|
|
|
TIM ###-#### Special insp Req (concrete) or letter from Eng spec design strength 2500psi 6/11/2002 11:02:43 AM
|