Permit Information
Permit NumberBLD02-00720
StatusExpired
Name BOISE CITY (ANNE FRANK MEMORIAL)
Site Address 800 S 8TH ST
Project NameANNE FRANK MEMORIAL
Customer Number 
ePlanReviewNo
Description
(ANNE FRANK HUMAN RIGHTS MEMORIAL) To construct retaining walls exceeding 4 feet in height to retain earth in the landscaping of a public memorial per engineered approved plans on file. Site reviewed and approved for location in flood plain by H. Wayne Gibbs and Public Works. Zoning approval not required. Special inspection required per attached condition. Note: No other site development is under the scope of the UBC. P.C.#0199-02 (mys)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/26/20042/26/20042/26/2004 DONE
DetailsDave Hannah
BLD-Aging Inspection8/12/20038/12/20038/12/2003 FAIL
DetailsCarl Dependahl
contractor not at site... 8/12/2003 1:19:39 PM
BLD-Conference9/10/20029/10/20029/10/2002PPASS
DetailsCarl Dependahl
w/GS...memorial need handrails, spec insp reports , etc. 9/10/2002 4:33:54 PM
BLD-Footing7/23/20027/24/20027/24/2002APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/23/2002 at 17:12:43. Contact: . forming in prgess ok to cover 7/24/2002 10:01:45 AM
BLD-Foundation7/2/20027/3/20027/3/2002APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 07/02/2002 at 20:10:53. Contact: ###-####.
BLD-Footing6/25/20026/25/20026/25/2002PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/25/2002 at 10:03:44. Contact: ###-####. WIP STRATA DOING INSPS 6/25/2002 2:51:39 PM
BLD-Footing6/20/20026/20/20026/20/2002PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/20/2002 at 07:25:20. Contact: ###-####. 6/20/2002 2:34:26 PM ending stratas report 6/20/2002 2:34:52 PM
BLD-Footing6/13/20026/14/20026/13/2002ACANC
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/13/2002 at 11:40:14. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/13/2002 at 13:44:11.
BLD-Foundation6/12/20026/12/20026/12/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/12/2002 at 07:04:01. Contact: ###-####.
BLD-Concrete6/6/20026/7/20026/7/2002APART
DetailsJim Storey
wip 6/7/2002 11:09:01 AM
BLD-Footing6/6/20026/7/20026/7/2002APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 06/06/2002 at 17:21:16. Contact: ###-####. wip 6/7/2002 11:09:10 AM
BLD-Concrete6/5/20026/6/20026/6/2002APART
DetailsCarl Dependahl
strata onsite...pend report. 6/6/2002 9:50:39 AM
BLD-Footing6/5/20026/6/20026/6/2002APART
DetailsCarl Dependahl
darren ###-#### masonry ok pend report. 6/6/2002 3:04:22 PM
BLD-Concrete6/5/20026/5/20026/5/2002PPART
DetailsCarl Dependahl
strata onsite 6/5/2002 5:40:12 PM
BLD-Framing/Rough-in6/4/20026/5/20026/5/2002APART
DetailsCarl Dependahl
block wall- darrin ###-#### ...pend spec insp report 6/5/2002 2:28:24 PM
BLD-Concrete6/3/20026/4/20026/4/2002APART
DetailsCarl Dependahl
DARREN ###-####...masonry, pending spec insp report. 6/4/2002 9:12:36 AM
BLD-Concrete6/3/20026/3/20026/3/2002PPART
DetailsCarl Dependahl
masonry, 1st lift, east side...visual insp ok...has spec. insp.
BLD-Conference6/3/20026/3/20026/3/2002PPASS
DetailsCarl Dependahl
darren...re spec insp req's; need scope -of- work statement...Strata has been onsite, left initial written report, no apparent discrepancies for 1st lift, east side of bridge 6/3/2002 3:36:15 PM
BLD-Conference5/29/20025/29/20025/29/2002PCANC
DetailsCarl Dependahl
"pre-con" resub for masonry is approved by Marlene; need spec insp for masonry( & concrete all ready placed??? approved by 425) will advise who will do insps; met w/ Mickelson Masony foreman, advised not to grout prior to insp.
BLD-Footing5/28/20025/29/20025/29/2002PNR
DetailsCarl Dependahl
FT INSP DARREN ###-#### FTGS ONLY...OK TO USE # 6 bar in lieu of # 4 5/29/2002 5:02:15 PM
BLD-Footing5/24/20025/28/20025/28/2002PNR
DetailsCarl Dependahl
ft insp -- darin- ###-####...need verts installed. 5/28/2002 4:01:37 PM
BLD-Footing5/24/20025/28/20025/28/2002PCANC
DetailsCarl Dependahl
DARREN ###-####
BLD-Footing5/23/20025/24/20025/24/2002APART
DetailsDave Hannah
###-#### ftg for area south of 9th st ok to pour 5/24/2002 9:55:56 AM
BLD-Conference5/15/20025/15/20025/15/2002PPASS
DetailsCarl Dependahl
met w/ Les Bock & contractor....requests change to masonry ret. wall; supply calcs & soils report...& written letter with reasoning and requesting change. If all else ok, I'd allow change