BLD-Final | 8/7/2002 | 8/7/2002 | 8/7/2002 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/07/2002 at 09:45:13. Contact: ###-####.
|
BLD-Final | 8/6/2002 | 8/6/2002 | 8/6/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 10:53:31. Contact: ###-####....need plans onsite, recall 8/6/2002 5:07:54 PM
|
FIRE-Final Inspection | 8/2/2002 | 8/2/2002 | 8/2/2002 | P | PASS |
Rick Jackson
|
|
|
|
Permanent Occupancy | | 8/2/2002 | 8/2/2002 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 7/11/2002 | 7/12/2002 | 7/12/2002 | P | PART |
Carl Dependahl
|
|
|
DAVE ###-#### wip, complete plbg, ok to use extended office area 7/12/2002 3:01:26 PM
|
FIRE-Alarm Testing | 7/3/2002 | 7/9/2002 | 7/9/2002 | A | PASS |
Rick Jackson
|
|
|
###-#### loren please call 1st alrms tested okay; need rated doors at restroom areas 7/9/2002 10:09:24 AM
|
BLD-Framing/Rough-in | 7/2/2002 | 7/3/2002 | 7/3/2002 | A | PART |
Tom Arcoraci
|
|
|
###-#### samm wip 7/3/2002 11:51:57 AM
|
BLD-Framing/Rough-in | 6/27/2002 | 6/27/2002 | 6/27/2002 | P | FAIL |
Carl Dependahl
|
|
|
r/i- sam- ###-#### c/n, extend 1hr assy's to deck, seal penetrations at wa 6/27/2002 4:08:48 PM lls & floors 6/27/2002 4:09:00 PM
|
BLD-Conference | 6/26/2002 | 6/26/2002 | 6/26/2002 | P | PASS |
Carl Dependahl
|
|
|
###-#### SAM ADA clr at rest rm.ok due to existing stand pipe ( 19" to c.l.) Awaiting archs detail re corridor walls 6/26/2002 2:33:10 PM
|
FIRE-Conference | 6/24/2002 | 6/25/2002 | 6/25/2002 | A | PART |
Rick Jackson
|
|
|
###-#### exit signs to installed as redlined on approved plans 6/25/2002 8:01:34 AM
|
BLD-Conference | 6/20/2002 | 6/21/2002 | 6/21/2002 | A | PASS |
Carl Dependahl
|
|
|
###-#### CALL FIRST need arch's detail to maintain 1hr corridors around core 6/21/2002 2:35:46 PM
|
BLD-Conference | 6/21/2002 | 6/21/2002 | 6/21/2002 | P | CANC |
Carl Dependahl
|
|
|
|