FIRE-Final Inspection | 5/15/2002 | 5/15/2002 | 5/15/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 5/15/2002 1:36:18 PM
|
Permanent Occupancy | | 5/15/2002 | 5/15/2002 | | DONE |
|
|
|
|
BLD-Final | 5/13/2002 | 5/14/2002 | 5/14/2002 | P | FAIL |
Russ Owen
|
|
|
bob- ###-#### call 1st before insp---fn occ--. Needs fire/life/safety inspection, Which has a c/n for door hardware, Note door hardware is not shown on this plan, and must have been shown on original plan and this is not on site at this time, Note door hardware is typically checked an occupancy inspection, not vanila finish. There is 1 door in the ware house that has key locking hardware also 2 doors out of office to sidewalk. 5/14/2002 6:08:25 PM
|
FIRE-Final Inspection | 5/13/2002 | 5/14/2002 | 5/14/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide approved door hardware on the exterior office doors or remove hardware 5/14/2002 10:53:39 AM
|