BLD-Final | 10/30/2003 | 10/30/2003 | 10/30/2003 | | DONE |
|
|
|
Final/Storey
|
BLD-Grading Inspection | 10/30/2003 | 10/30/2003 | 10/30/2003 | | PASS |
Rita DeYoung
|
|
|
Final grading and drainage approved
|
BLD-Conference | 10/15/2003 | 10/16/2003 | 10/16/2003 | A | PART |
Jim Storey
|
|
|
Russ; Phone #: ###-#### Internet Inspection Request from: Annette Moore final ok pending ele plm and pw. 10/16/2003 9:23:05 AM
|
BLD-Framing/Rough-in | 4/15/2003 | 4/16/2003 | 4/16/2003 | A | PASS |
Tony Young
|
|
|
justin shear nail; Phone #: ###-#### Internet Inspection Request from: Darla Downs
int. shear ok 4/16/2003 11:56:07 AM
|
BLD-Energy code compliance | 4/9/2003 | 4/10/2003 | 4/10/2003 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
need to call for int. shear later? 4/10/2003 12:32:56 PM
|
BLD-Framing/Rough-in | 4/8/2003 | 4/8/2003 | 4/8/2003 | P | PASS |
Tony Young
|
|
|
justin; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 4/2/2003 | 4/3/2003 | 4/3/2003 | A | FAIL |
Tony Young
|
|
|
justin; Phone #: ###-#### Internet Inspection Request from: Darla Downs
c/n posted 4/3/2003 12:39:03 PM
|
BLD-Framing/Rough-in | 4/1/2003 | 4/1/2003 | 4/1/2003 | P | FAIL |
Tony Young
|
|
|
JUSTIN; Phone #: ###-#### Internet Inspection Request from: Darla Downs
no inspection, need all trades 1st 4/1/2003 2:42:20 PM
|
BLD-Framing/Rough-in | 3/19/2003 | 3/20/2003 | 3/20/2003 | A | PART |
Tony Young
|
|
|
JUSTIN; Phone #: ###-#### Internet Inspection Request from: Annette Moore
verify new hold downs at frame insp. 3/20/2003 3:40:21 PM
|
BLD-Framing/Rough-in | 3/17/2003 | 3/18/2003 | 3/18/2003 | A | FAIL |
Tony Young
|
|
|
JUSTIN; Phone #: ###-#### Internet Inspection Request from: Darla Downs
need new eng. on missing hold downs, added windows, no cover allowed, also need to add blocks on all walls and king studs on tall walls 3/18/2003 10:30:51 AM
|
BLD-Foundation | 1/28/2003 | 1/29/2003 | 1/29/2003 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 1/28/2003 at 5:06:18 PM. Contact: ###-####. Perimeter walls pass--complete including steel per plans (except hd not installed); interior footings not complete at time of inspection -- work in progress. 1/29/2003 8:52:15 AM
|
BLD-Footing | 1/22/2003 | 1/24/2003 | 1/24/2003 | A | PART |
Tony Young
|
|
|
CURTIS; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
wip, ok so far 1/24/2003 11:30:08 AM
|
BLD-Grading Inspection | 1/22/2003 | 1/22/2003 | 1/22/2003 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade has been approved by the geotechnical engineer
|
BLD-Conference | 1/14/2003 | 1/15/2003 | 1/15/2003 | A | PASS |
Carl Dependahl
|
|
|
Just now starting work needed extension before end of Jaunary ###-#### carl
|