BLD-Final | 1/21/2004 | 1/21/2004 | 1/21/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/21/2004 at 7:05:37 AM. Contact: ###-####. OK for Perm Occ. :) 1/21/2004 3:13:19 PM
|
FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety, fire alarm and fire sprinklers finaled 1/21/2004 11:23:09 AM
|
FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 1/21/2004 11:24:04 AM
|
Permanent Occupancy | | 1/15/2004 | 1/15/2004 | | DONE |
|
|
|
|
BLD-Other | 1/13/2004 | 1/14/2004 | 1/14/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/13/2004 at 9:03:51 AM. Contact: ###-####. Grid in alternate OK 1/15/2004 8:07:26 AM
|
BLD-Other | 12/23/2003 | 12/24/2003 | 12/24/2003 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/23/2003 at 1:47:54 PM. Contact: ###-####.
|
BLD-Final | 12/22/2003 | 12/23/2003 | 12/23/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/22/2003 at 9:13:59 AM. Contact: ###-####. Temp Occ. OK for Sanctuary (Bldg B) Verified approval from Dave Miller over the phone. 12/23/2003 4:09:23 PM 12/23/2003 4:14:38 PM
|
FIRE-Final Inspection | 12/22/2003 | 12/23/2003 | 12/23/2003 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave millers permission until the existing building is completed. Battery calcs, map, breaker locks and breaker box location. Existing building needs to be inspected 12/23/2003 1:23:58 PM
|
FIRE-Final Inspection | 12/22/2003 | 12/22/2003 | 12/22/2003 | P | FAIL |
Troy Cobbley
|
|
|
provide "no parking fire lane" text on the fire lane curbing, install door hardware and building address, secure new area from the existing area before a temp occupancy is signed 12/22/2003 4:12:08 PM
|
BLD-Wall cover | 12/10/2003 | 12/11/2003 | 12/11/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/10/2003 at 10:35:14 AM. Contact: ###-####. Ceiling grid OK. 12/11/2003 11:19:36 AM
|
BLD-Wall cover | 10/21/2003 | 10/21/2003 | 10/21/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/21/2003 at 7:11:08 AM. Contact: ###-####. Need details and listed assemblies for type v1hr alternate. 10/21/2003 4:29:16 PM
|
BLD-Wall cover | 10/17/2003 | 10/20/2003 | 10/20/2003 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/17/2003 at 9:25:09 AM. Contact: ###-####.
|
BLD-Conference | 10/7/2003 | 10/8/2003 | 10/8/2003 | A | DONE |
Jim Sly
|
|
|
per your request
|
BLD-Framing/Rough-in | 9/5/2003 | 9/8/2003 | 9/8/2003 | A | PART |
Jim Sly
|
|
|
BRIAN; Phone #: ###-#### Internet Inspection Request from: Marc Lileks Looked at wood framing in Alternate section.....Archit to address V 1hr at ceiling this area. 9/8/2003 10:11:39 AM
|
BLD-Framing/Rough-in | 7/23/2003 | 7/24/2003 | 7/24/2003 | A | PART |
Jim Sly
|
|
|
###-#### bryaN Conf on Work in progress. 7/24/2003 9:40:03 AM
|
BLD-Conference | 5/14/2003 | 5/15/2003 | 5/15/2003 | A | FAIL |
Jim Sly
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Annette Moore Architect to resubmit changes for plan modification review for alternate area. 5/15/2003 12:15:08 PM
|
BLD-Footing | 5/2/2003 | 5/5/2003 | 5/5/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/2/2003 at 4:17:31 PM. Contact: ###-####. Footings at alternate sections 2 and 5 OK pending MTI insp and approvals. 5/5/2003 2:35:38 PM
|
BLD-Footing | 4/29/2003 | 4/30/2003 | 4/30/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/29/2003 at 12:19:23 PM. Contact: ###-####. Footing at South wall connecting New to old Bldg......OK pending MTI spec insp and approvals. 4/30/2003 9:16:21 AM
|
BLD-Footing | 4/7/2003 | 4/8/2003 | 4/8/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/7/2003 at 12:08:02 PM. Contact: ###-####. Footing (pads) at N.W. corner of new Bldg. OK pend Special insp and appr. 4/8/2003 2:58:29 PM
|
BLD-Footing | 3/19/2003 | 3/20/2003 | 3/20/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/19/2003 at 4:24:19 PM. Contact: ###-####. Last of the foundation...OK Pending MTI insp and approvals. 3/20/2003 3:41:07 PM
|
BLD-Footing | 3/12/2003 | 3/13/2003 | 3/13/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/12/2003 at 9:33:12 AM. Contact: ###-####. Footing for bell tower, S. E. section (using as drive thru) and Misc pads OK pending MTI insp and approvals. 3/13/2003 3:21:50 PM
|
BLD-Footing | 3/7/2003 | 3/10/2003 | 3/10/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/7/2003 at 9:01:44 AM. Contact: ###-####. OK pend MTI insp and appr. 3/10/2003 4:49:20 PM
|
BLD-Footing | 3/6/2003 | 3/6/2003 | 3/6/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/6/2003 at 7:54:53 AM. Contact: ###-####. West part of South wall..... OK pending MTI insp and approvals. 3/6/2003 12:27:29 PM
|
BLD-Footing | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/3/2003 at 12:48:24 PM. Contact: ###-####. MTI insp and approvals. 3/4/2003 3:54:41 PM
|
BLD-Footing | 2/27/2003 | 2/28/2003 | 2/28/2003 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Columns at West wall and footings (for columns) at North wall near bell tower. OK pending MTI insp and approvals. 2/28/2003 3:05:53 PM
|
BLD-Footing | 2/24/2003 | 2/25/2003 | 2/25/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/24/2003 at 1:06:19 PM. Contact: ###-####. MTI 2/25/2003 10:35:38 AM
|
BLD-Foundation | 2/20/2003 | 2/21/2003 | 2/21/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/20/2003 at 12:34:02 PM. Contact: ###-####. Found wall for west end and large pads for columns and large beams spanning sanctuary. OK pend insp and appr MTI. 2/21/2003 10:36:34 AM
|
BLD-Foundation | 2/18/2003 | 2/19/2003 | 2/19/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/18/2003 at 7:08:28 AM. Contact: ###-####. OK pend. MTI insp and appr. 2/19/2003 10:16:06 AM
|
BLD-Footing | 2/14/2003 | 2/18/2003 | 2/18/2003 | A | PART |
Tom Arcoraci
|
|
|
BRIAN; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Foundation | 2/13/2003 | 2/14/2003 | 2/14/2003 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Octagon wall (East) MTI on site. 2/14/2003 4:15:21 PM
|
BLD-Footing | 2/11/2003 | 2/12/2003 | 2/12/2003 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung East wall footings OK pending special insp and approval....(MTI) 2/12/2003 3:36:38 PM
|
BLD-Foundation | 2/5/2003 | 2/6/2003 | 2/6/2003 | A | PART |
Jim Sly
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Part of the Footings were poured on an MIS permit for Early start......MTI has been on site full time for all footings.....Have finaled MIS permit. 2/6/2003 9:49:38 AM
|