Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD02-02471
StatusFinaled
Name JAYO CONSTRUCTION
Site Address 10172 W SMOKE RANCH DR
Project NameAlzheimers Care Facility
Customer Number 
ePlanReviewNo
Description
Area #1 * To construct a one story Type V1hr fully fire sprinklered care facility to include the north side only with 17 sleeping rooms, laundry and storage room per approved plans and attachments. Other work includes all site improvements, landscaping and paving. DRH02-00079 CUP02-00025. Fire sprinklers used for area
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/17/20039/18/20039/18/2003APASS
DetailsRuss Owen
cameron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok perm oc 9/17/2003 6:55:15 PM
BLD-Final9/17/20039/18/20039/18/2003APASS
DetailsRuss Owen
cameron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok perm oc 9/17/2003 6:55:15 PM
Permanent Occupancy 9/18/20039/18/2003 DONE
Details
Code Occupancy Approval  9/12/2003 PASS
LOOKS TO BE IN COMPLIANCE WITH DRH02-00079 FINAL SIGNED OFF.
BLD-Final9/4/20039/5/20039/5/2003ACANC
DetailsRuss Owen
CAMRON; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Final9/3/20039/4/20039/4/2003ACANC
DetailsRuss Owen
cameron; Phone #: ###-#### Internet Inspection Request from: Annette Moore
BLD-Final9/3/20039/4/20039/4/2003PPART
DetailsRuss Owen
cameron; Phone #: ###-#### Internet Inspection Request from: Annette Moore OK for a temp oc needes all required signatures on card for a PERM OC. 9/4/2003 12:32:05 AM
FIRE-Final Inspection9/4/20039/4/20039/4/2003PPASS
DetailsTroy Cobbley
Fire life safety and fire sprinklers finaled 9/4/2003 1:21:11 PM
FIRE-Final Inspection9/3/20039/4/20039/4/2003AFAIL
DetailsTroy Cobbley
cameron; Phone #: ###-#### Re-install the covers on the duct smoke detectors 9/4/2003 9:43:18 AM
BLD-Final8/28/20039/2/20039/2/2003APART
DetailsRuss Owen
cameron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Went for walk thru , needs all req signatures, and some corrections noted with contractor. 9/2/2003 11:34:46 PM
FIRE-Final Inspection8/29/20039/2/20039/2/2003AFAIL
DetailsTroy Cobbley
No items on the correction notice have been corrected 9/2/2003 10:38:57 AM
FIRE-Sprinkler Rough-in8/29/20039/2/20039/2/2003AFAIL
DetailsTroy Cobbley
No items on the correction notice have been corrected 9/2/2003 10:37:37 AM
FIRE-Final Inspection8/28/20038/29/20038/29/2003AFAIL
DetailsTroy Cobbley
repair emergency light in the north dining area, provide emergency light in the visiting area 8/29/2003 2:33:42 PM
FIRE-Final Inspection8/28/20038/29/20038/29/2003AFAIL
DetailsTroy Cobbley
repair emergency light in the north dining area, provide emergency light in the visiting area 8/29/2003 2:33:42 PM
Code Occupancy Approval Temp8/28/20038/27/20038/27/2003ADONE
DetailsScott M.Brown
BOND IN PLACE FOR LANDSCAPE TEMP OCCUPANCY SIGNED OFF. 8/28/2003 9:53:57 AM
BLD-Framing/Rough-in5/13/20035/14/20035/14/2003APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 5/13/2003 at 4:46:15 PM. Contact: ###-####. Extension of 5/8 gyp membrane around valve boxes (Laundry), and Boxed enclosures above ceiling speakers appears OK. 5/14/2003 9:56:18 AM
BLD-Framing/Rough-in5/12/20035/13/20035/13/2003PCANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/12/2003 at 7:55:32 PM. Contact: ###-####.
BLD-Framing/Rough-in5/11/20035/12/20035/12/2003AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/11/2003 at 8:57:58 PM. Contact: ###-####.needs speaker cans and some penetrations protected. 5/12/2003 10:45:15 AM
BLD-Framing/Rough-in5/12/20035/12/20035/12/2003PPART
DetailsRuss Owen
CAMERON; Phone #: ###-#### Internet Inspection Request from: Annette Moore.Ok to insulate all items complete except speakers not yet in boxes in hall. 5/12/2003 3:43:14 PM
BLD-Framing/Rough-in5/8/20035/9/20035/9/2003PPART
DetailsRuss Owen
###-#### Still has some areas to address went over this with contractor. 5/9/2003 3:38:27 PM 5/9/2003 3:39:14 PM
BLD-Framing/Rough-in5/7/20035/8/20035/8/2003APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/7/2003 at 4:54:53 PM. Contact: ###-####.Meet with all trades, contractor and fire caulk rep about penetrations. 5/8/2003 11:28:00 AM
BLD-Framing/Rough-in5/7/20035/7/20035/7/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/7/2003 at 1:07:29 AM. Contact: ###-####. Went to job site, and talked with electrician and plumber about fire stoping. I have not yet been provided all of the various fire stoping details. I spoke with Cameron this moring about this. Also there are items in the ceiling that need to be addressed. Note: fire stoping was brought up at the first framing inspection when the only piping in the building was some abs vent pipe. Which was around the 14th of april. This is not ready for a frame inspection as I should not have to be adressing these issues they should have allready had these items completed, as this is a common 1 hour fire resistive building I should not have to be the one to instruct them how to maintaing the fire resistive construction. 5/7/2003 2:58:02 PM
BLD-Framing/Rough-in5/5/20035/6/20035/6/2003APART
DetailsRuss Owen
Trusses ok need fire resistive assemblies. for products. 5/6/2003 2:41:08 PM
BLD-Framing/Rough-in5/2/20035/5/20035/5/2003PCANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/2/2003 at 5:35:59 PM. Contact: ###-####.out of time. 5/5/2003 5:44:59 PM
BLD-Framing/Rough-in5/1/20035/2/20035/2/2003PNR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/1/2003 at 12:12:47 PM. Contact: ###-####. Needs other trades before. calling for framing. called and left message. 5/2/2003 4:44:32 PM
BLD-Framing/Rough-in4/21/20034/21/20034/21/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 4/21/2003 at 6:53:36 AM. Contact: ###-####.ext drywall ok. 4/22/2003 10:26:01 AM
BLD-Framing/Rough-in4/17/20034/18/20034/18/2003APART
DetailsRuss Owen
Ok to drywall front 4/18/2003 11:35:56 AM
BLD-Framing/Rough-in4/17/20034/17/20034/17/2003PPART
DetailsRuss Owen
camron; Phone #: ###-#### Internet Inspection Request from: Darla Downs. Rear wall ok frontwall needs addl staples. 4/18/2003 10:38:12 AM
BLD-Framing/Rough-in4/15/20034/16/20034/16/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 4/15/2003 at 8:14:50 PM. Contact: ###-####. roof only ok to cover. 4/16/2003 4:50:02 PM
FIRE-Conference4/15/20034/16/20034/16/2003ACANC
DetailsTroy Cobbley
conference was set up by the plumbing contractor . He wanted to know how to install the fire caulking for his plumbing pipe penatrations. I spoke to Dennis with Meridian Plumbling and told him to install it per the manufacturers recommendations and also gave him Russ Owens phone number 4/16/2003 4:20:03 PM
BLD-Framing/Rough-in4/14/20034/15/20034/15/2003PFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 4/14/2003 at 7:45:11 PM. Contact: ###-####.posted a c/n. 4/16/2003 11:02:31 AM
BLD-Framing/Rough-in4/11/20034/14/20034/14/2003AFAIL
DetailsRuss Owen
posted c/n shear walls and roof. 4/14/2003 1:26:36 PM
FIRE-Supply Line Cover4/13/20034/14/20034/14/2003PPASS
DetailsTroy Cobbley
Underground sprinkler piping is ok to cover 4/14/2003 2:04:35 PM
BLD-Footing3/18/20033/19/20033/19/2003PNR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 3/18/2003 at 7:27:03 PM. Contact: ###-####. BILL CALLED TO CANC THIS INSPECTION, NOT READY.
BLD-Footing3/17/20033/18/20033/18/2003APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 3/17/2003 at 5:08:30 PM. Contact: ###-####. interior 3/18/2003 11:07:48 AM
BLD-Footing3/14/20033/17/20033/17/2003ANR
DetailsRuss Owen
bill; Phone #: ###-#### Internet Inspection Request from: Annette Moore. interior footings. 3/17/2003 10:23:43 AM
BLD-Footing3/17/20033/17/20033/17/2003PFAIL
DetailsRuss Owen
c/n posted in job trailer. 3/17/2003 4:04:40 PM
FIRE-Conference2/20/20032/21/20032/21/2003ADONE
DetailsTroy Cobbley
cameron; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Foundation2/18/20032/19/20032/19/2003ACANC
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung out of time 2/19/2003 10:27:25 AM
BLD-Foundation2/19/20032/19/20032/19/2003PPASS
DetailsDave Hannah
rebar in, forms 95% ,contractor and I went over hold down locations 2/19/2003 5:37:25 PM
BLD-Footing2/14/20032/14/20032/14/2003PPART
DetailsRuss Owen
bill; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie .footing 2/14/2003 4:53:47 PM
BLD-Footing2/6/20032/7/20032/7/2003PNR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 2/6/2003 at 6:07:21 PM. Contact: ###-####.