To construct a new 23,710 square foot, one story, auto body repair shop with related office and storage area and associated site improvements. The building is constructed on a pre-engineered metal building frame with masonry and steel stud exterior walls. All construction per the approved plans and attached comment list. PC#806-02/DRH02-00147/CUP02-00101/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/20/200310/21/200310/21/2003APASS
DetailsRuss Owen
Dennis; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Ok perm oc. 10/20/2003 6:00:07 PM
Permanent Occupancy 10/21/200310/21/2003 DONE
Details
BLD-Final10/8/200310/8/200310/8/2003PFAIL
DetailsRuss Owen
Dennis, ###-#### - please call 1st so he can meet you there stil has not completed prior c/n. 10/8/2003 5:00:51 PM
Code Occupancy Approval10/3/200310/3/200310/3/2003APASS
DetailsWm. Michael Meloy
Compliance met/ 10/3/2003 12:22:06 PM
BLD-Final7/17/20037/18/20037/18/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 7/17/2003 at 5:04:10 PM. . would be ok for a temp oc if fire/lifesafety approved , c/n posted by me for other item.. 7/18/2003 5:38:19 PM 7/18/2003 5:39:39 PM
FIRE-Final Inspection7/18/20037/18/20037/18/2003PPASS
DetailsRick Jackson
don -- ###-####
BLD-Framing/Rough-in7/7/20037/8/20037/8/2003APASS
DetailsRuss Owen
martin grid; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. Grid ok,I have a detail for 1 hr fire wall at deck also from architect.. 7/8/2003 11:35:24 AM
BLD-Framing/Rough-in6/26/20036/26/20036/26/2003PPART
DetailsRuss Owen
new detail for entry way droped soffit support. 6/27/2003 12:42:48 PM
BLD-Framing/Rough-in6/16/20036/17/20036/17/2003APART
DetailsRuss Owen
there is a soffit hanging down at the entry aea that needs detailing, I posted a c/n. also recived a letter from architect about the 1 hr wall termination they will stop at the ceiling assembly as can not be done as typical detail shows on plans.. 6/18/2003 1:54:23 PM 6/18/2003 1:54:52 PM 6/18/2003 1:55:13 PM
BLD-Conference6/16/20036/16/20036/16/2003PPART
DetailsRuss Owen
Stoped by to check progress, talked with framer he has supplied letter of intent for fire wall to stop at roof assembly and addressed the continuity of the 1 hr wall at the north side that was not detailed on plans,which will be a shaft wall, also there is a droped soffit hard lid that needs to be addressed at the waiting room and east end small exterior side building need roof froming detail, will be back at an am inspection to go over these items in detal and leave a request for info. 6/16/2003 5:38:45 PM
BLD-Framing/Rough-in6/3/20036/3/20036/3/2003PFAIL
DetailsRuss Owen
george; Phone #: ###-#### Internet Inspection Request from: Annette Moore. c/n posted/fire wall. 6/3/2003 5:29:17 PM
BLD-Framing/Rough-in5/29/20035/29/20035/29/2003PPART
DetailsRuss Owen
george; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. Went over general requirements did tell them to get details for fire wall continuity, and also needs alltrades signed off prior to a frame inspection. 5/29/2003 5:50:03 PM
BLD-Framing/Rough-in5/20/20035/21/20035/21/2003APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 5/20/2003 at 2:10:48 PM. Contact: ###-####.Front entry ok for canopy brakets. 5/21/2003 2:38:26 PM
BLD-Framing/Rough-in5/16/20035/19/20035/19/2003AFAIL
DetailsRuss Owen
Posted a c/n also talked with engineer about front canopy he will field verify. 5/19/2003 11:49:40 AM
BLD-Framing/Rough-in5/15/20035/16/20035/16/2003AFAIL
DetailsJim Sly
martin store front only; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Walked the whole jobsite incl lithia motors and can't find any supers............. 5/16/2003 9:27:24 AM
BLD-Framing/Rough-in5/16/20035/16/20035/16/2003PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/16/2003 at 9:36:19 AM. Contact: ###-####. out of time 5/16/2003 4:44:00 PM
BLD-Framing/Rough-in5/7/20035/7/20035/7/2003PPART
DetailsRuss Owen
john; Phone #: ###-#### Internet Inspection Request from: Annette Moore Roof area ok will get an insulation so as to comply with energy code.5/8/2003 9:48:14 AM 5/8/2003 9:49:05 AM
BLD-Other4/4/20034/7/20034/7/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 4/4/2003 at 1:39:15 PM. Went over occupancy at front reception. 4/7/2003 4:16:12 PM
BLD-Footing3/18/20033/18/20033/18/2003PPART
DetailsRuss Owen
Work requires special inspection. 3/18/2003 4:30:33 PM
BLD-Footing3/11/20033/12/20033/12/2003APART
DetailsJim Storey
john; Phone #: ###-#### Internet Inspection Request from: Annette Moore south and west end of ft and grade beams rebar ok special insp approved. 3/12/2003 9:27:37 AM