Permanent Occupancy | | 9/24/2003 | 9/24/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/21/2003 | 8/21/2003 | 8/21/2003 | P | PASS |
Troy Cobbley
|
|
|
fire alarm, fire sprinkler and fire life safety finaled
|
FIRE-Final Inspection | 8/19/2003 | 8/20/2003 | 8/20/2003 | P | FAIL |
Troy Cobbley
|
|
|
matt ###-#### nac circuit not connected yet and the hvac units could not be put in heat mode for testing of the duct smoke detectors 8/20/2003 3:31:59 PM
|
BLD-Conference | 8/12/2003 | 8/13/2003 | 8/13/2003 | A | PASS |
Tom Arcoraci
|
|
|
ok for perm occ see 8-6-03 insp by 407 8/13/2003 8:30:45 AM
|
BLD-Conference | 8/11/2003 | 8/11/2003 | 8/11/2003 | P | CANC |
Russ Owen
|
|
|
out of time. 8/12/2003 5:41:06 PM
|
BLD-Final | 8/6/2003 | 8/6/2003 | 8/6/2003 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/6/2003 at 8:59:33 AM. Contact: ###-####.ok perm oc. 8/6/2003 3:40:16 PM
|
BLD-Final | 7/29/2003 | 7/30/2003 | 7/30/2003 | P | PART |
Russ Owen
|
|
|
Ok for a temp oc as fire life safey has given a temp , my prior c/n is for aportion of counter to be accessable, new c/n posted and called contractor. 7/30/2003 2:48:29 PM
|
BLD-Final | 5/29/2003 | 5/30/2003 | 5/30/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/29/2003 at 3:50:58 PM. Contact: ###-####. Needs accesible counter and fire life safety approval, then possible for a temp oc. 5/30/2003 3:05:24 PM
|
FIRE-Final Inspection | 5/29/2003 | 5/30/2003 | 5/30/2003 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Millers permission since an upgrade agreement has been reached on upgrading the fire alarm system 5/30/2003 2:55:54 PM
|
BLD-Final | 5/28/2003 | 5/29/2003 | 5/29/2003 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/28/2003 at 3:56:37 PM. Contact: ###-####.This needs fire life safety prior. 5/29/2003 5:52:59 PM
|
FIRE-Final Inspection | 5/28/2003 | 5/29/2003 | 5/29/2003 | A | FAIL |
Troy Cobbley
|
|
|
Remove the bar locking the double doors in the installation area. Gary said he would install automatic flush bolts 5/29/2003 10:38:45 AM
|
BLD-Other | 5/15/2003 | 5/15/2003 | 5/15/2003 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/15/2003 at 6:12:59 AM. Contact: ###-####. ceiling t grid
|
BLD-Framing/Rough-in | 4/24/2003 | 4/25/2003 | 4/25/2003 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/24/2003 at 4:07:05 PM. Contact: ###-####.
|