BLD-Final | 11/3/2003 | 11/4/2003 | 11/4/2003 | A | PASS |
Jim Sly
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie All signatures for shell bldg....OK 11/4/2003 12:06:30 PM
|
BLD-Final | 10/31/2003 | 11/3/2003 | 11/3/2003 | P | NR |
Jim Sly
|
|
|
Scott; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
FIRE-Final Inspection | 10/31/2003 | 11/3/2003 | 11/3/2003 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 11/4/2003 9:47:55 AM
|
Code Occupancy Approval | | | 11/3/2003 | | PASS |
|
|
|
ALL IN AS REQUIRED FINAL SIGNED OFF.
|
BLD-Conference | 10/31/2003 | 10/31/2003 | 10/31/2003 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/31/2003 at 7:33:11 AM. Contact: ###-####.
|
BLD-Final | 10/29/2003 | 10/30/2003 | 10/30/2003 | P | NR |
Jim Sly
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
FIRE-Final Inspection | 10/29/2003 | 10/30/2003 | 10/30/2003 | P | PASS |
Troy Cobbley
|
|
|
life safety finaled 10/30/2003 12:03:29 PM
|
BLD-Framing/Rough-in | 10/20/2003 | 10/21/2003 | 10/21/2003 | A | PASS |
Jim Sly
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Annette Moore Grid OK. 10/21/2003 11:15:24 AM
|
BLD-Conference | 10/3/2003 | 10/6/2003 | 10/6/2003 | P | PASS |
Tom Arcoraci
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Barbara Moore needs 6 8 head room to kids room 10/6/2003 3:25:04 PM
|
BLD-Framing/Rough-in | 9/9/2003 | 9/10/2003 | 9/10/2003 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/9/2003 at 5:58:56 PM. Contact: ###-####. 9/10/2003 2:35:09 PM
|
BLD-Framing/Rough-in | 9/2/2003 | 9/3/2003 | 9/3/2003 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 9/2/2003 at 6:26:15 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/26/2003 | 8/27/2003 | 8/27/2003 | P | PASS |
Tom Arcoraci
|
|
|
###-#### russ//ext nail inspection ok pending plumb insp 8/27/2003 3:32:52 PM
|
BLD-Framing/Rough-in | 8/26/2003 | 8/27/2003 | 8/27/2003 | P | CANC |
Tom Arcoraci
|
|
|
###-#### russ//ext nailing inspection
|
BLD-Framing/Rough-in | 8/22/2003 | 8/25/2003 | 8/25/2003 | P | FAIL |
Jim Sly
|
|
|
russ ###-####--? NR.....Talked to Russ (superintendant) Needs Plan (sheet) showing shear panel locations.... 8/25/2003 4:50:39 PM
|
BLD-Framing/Rough-in | 6/13/2003 | 6/16/2003 | 6/16/2003 | P | PART |
Tom Arcoraci
|
|
|
###-#### roof ok 6/16/2003 2:53:48 PM
|
BLD-Foundation | 5/8/2003 | 5/8/2003 | 5/8/2003 | P | PASS |
Russ Owen
|
|
|
###-#### interior footing complete. 5/8/2003 4:47:19 PM
|
BLD-Foundation | 5/1/2003 | 5/1/2003 | 5/1/2003 | A | PASS |
Russ Owen
|
|
|
|
BLD-Foundation | 4/29/2003 | 4/30/2003 | 4/30/2003 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/29/2003 at 9:31:51 PM. Contact: ###-####.
|
BLD-Foundation | 4/30/2003 | 4/30/2003 | 4/30/2003 | P | FAIL |
Russ Owen
|
|
|
Add top bar horizontal to basement wall. 4/30/2003 5:18:07 PM
|
BLD-Framing/Rough-in | 4/25/2003 | 4/28/2003 | 4/28/2003 | A | FAIL |
Russ Owen
|
|
|
###-#### c/n posted. 4/28/2003 5:09:01 PM
|
BLD-Footing | 4/24/2003 | 4/25/2003 | 4/25/2003 | A | PASS |
Russ Owen
|
|
|
mike-- ###-####
|